What changed — Turin Management LLC

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Aug 29, 2025
    Incremental Load Request for Remington Factory Redevelopment · NY
    • Permit / site plan filed: NYISO load interconnection request 1740 filed (400 MW).
    Source: New York ISO
  2. May 2, 2025
    Remington Factory Redevelopment · NY
    • Permit / site plan filed: NYISO load interconnection request 1735 filed (100 MW).
    Source: New York ISO