DC
/

AiNET

OperatingUnclassifiedBuildingPrince George's County, Maryland
10% profile completeness
13 claims from 6 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
43,100 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Baltimore Gas & Electric CO · PJM
Substation: Beltsville Substation (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    AiNET
  2. substation
    Beltsville Substation[1]
    Proximity onlyUnverified
    Nearest mapped substation, 2.57 km away. Proximity does not establish that it serves the site.
  3. transmission
    230 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.08 km away). Not confirmed as the supply path.
  4. utility
    Baltimore Gas & Electric CO[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[3]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
39.05266, -76.92606
County
Prince George's County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Beltsville Substation[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
2.6 km[1]Likelyderived
Highest-voltage line nearby
230 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
16.21¢/kWh[5]Confirmed

Maryland statewide average, July 2026.

State avg. commercial price
17.51¢/kWh[5]Confirmed

Maryland statewide average, July 2026.

Generation within 50 km
4.06 GW[6]Confirmedderived

113 EIA-reported plants within 50 km.

Generation queued in county
1.79 GW[4]Confirmedderived

5 active generation interconnection requests in Prince George's County: Gas 845 MW, Solar + storage 810 MW, Storage 115 MW, Solar 19 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV lineTransmission line0.08 km230 kV[1]
Wheelabrator Baltimore Refuse · Wheelabrator Environmental SystemsPower plant (Biomass)34.9 km61 MW[6]
Brandon Shores · Brandon Shores LLCPower plant (Coal)36.5 km1.27 GW[6]
Herbert A Wagner · H.A. Wagner LLCPower plant (Petroleum)37.2 km841 MW[6]
Keys Energy Center · PSEG Keys Energy Center, LLCPower plant (Natural Gas)40.6 km763 MW[6]
Philadelphia · Constellation Power Source Generation, LLCPower plant (Petroleum)41.5 km60 MW[6]
Brandywine Power Facility · KMC Thermo, LLCPower plant (Natural Gas)43.1 km230 MW[6]
Covanta Fairfax Energy · Covanta Fairfax IncPower plant (Biomass)48.2 km98 MW[6]
Dickerson Power · Dickerson Power, LLCPower plant (Natural Gas)49.6 km299 MW[6]
Beltsville Substation · PEPCOSubstation2.57 km—[1]
Largest queued generation in this countyFuelQueue statusMWSource
Burches Hill-Chalk Point 500kVPJM AH2-269AGasIn study · proposed 2026-11845 MW[4]
Chalk Point 230kVPJM AH1-552Solar + storageIn study · proposed 2025-06810 MW[4]
Talbert 230kVPJM AH2-332StorageIn study · proposed 2025-12115 MW[4]
Ritchie 69 kVPJM AG2-520SolarIn study · proposed 2024-0317 MW[4]
TBD 69kVPJM AH2-065SolarIn study · proposed 2022-122 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
43,100 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

13
FieldValueSourceConfidenceAs ofStatus
NameAiNETway/363017375 name=AiNET[1] Likely2026-09-27Shown
StatusOperating[1] derivedUnverified2026-09-27Shown
UtilityBaltimore Gas & Electric COterritory 1167: BALTIMORE GAS & ELECTRIC CO (INVESTOR OWNED, EXELON CORP)[2] derivedLikely2022Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[3] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Nearest mapped substationBeltsville Substationway/224818414[1] derivedLikely2026-09-28Shown
Distance to substation2.6 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.79 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price16.21¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price17.51¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km4.06 GW[6] derivedConfirmed202502Shown
Building footprint43,100 sq ft[1] derivedLikely2026-09-27Shown