Lumen Technologies
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityLumen Technologies
- →substationBryan Substation (66 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 1.98 km away. Proximity does not establish that it serves the site.
- →transmissionJohanna - Santiago; Ellis - Santiago (220 kV)[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.63 km away). Not confirmed as the supply path.
- →utilitySouthern California Edison[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 33.71697, -117.80604
- Address
- County
- Orange County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
California statewide average, July 2026.
- State avg. commercial price
California statewide average, July 2026.
- Generation within 50 km
161 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Orange County: Storage 400 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Johanna - Bryan - Irvine;Villa Park - Bryan · Southern California Edison | Transmission line | 1.03 km | 66 kV | [1] |
| Johanna - Santiago; Ellis - Santiago · Southern California Edison | Transmission line | 1.63 km | 220 kV | [1] |
| Santiago - Estrella #1 · Southern California Edison | Transmission line | 1.66 km | 66 kV | [1] |
| Johanna - Bryan - Irvine · Southern California Edison | Transmission line | 1.68 km | 66 kV | [1] |
| 66 kV line · Southern California Edison | Transmission line | 1.96 km | 66 kV | [1] |
| Villa Park - Bryan · Southern California Edison | Transmission line | 1.97 km | 66 kV | [1] |
| Aes Huntington Beach Energy Project · AES Huntington Beach Energy, LLC | Power plant (Natural Gas) | 17.9 km | 630 MW | [6] |
| Haynes · Los Angeles Department of Water & Power | Power plant (Natural Gas) | 27.6 km | 1.6 GW | [6] |
| Aes Alamitos Energy Center · AES Alamitos Energy, LLC | Power plant (Natural Gas) | 27.8 km | 603 MW | [6] |
| Aes Alamitos LLC · AES Alamitos LLC | Power plant (Natural Gas) | 27.9 km | 1.14 GW | [6] |
| Walnut Creek Energy Park · Walnut Creek LLC | Power plant (Natural Gas) | 34.9 km | 501 MW | [6] |
| Long Beach Generation LLC · Long Beach Generation LLC | Power plant (Natural Gas) | 39.1 km | 260 MW | [6] |
| Watson Cogeneration · ARCO Products Co-Watson | Power plant (Natural Gas) | 42 km | 398 MW | [6] |
| Harbor · Los Angeles Department of Water & Power | Power plant (Natural Gas) | 42.9 km | 428 MW | [6] |
| Bryan Substation · Southern California Edison | Substation | 1.98 km | 66 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| TYRELL ENERGY STORAGECAISO 2125 | Storage | IA signed · proposed 2032-05 | 300 MW | [4] |
| LOS NIETOSCAISO 2129 | Storage | IA signed · proposed 2032-03 | 100 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
14| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Lumen Technologiesway/441502816 name=Lumen Technologies | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 14452 Franklin Avenue, Tustin, 92780 | [1] | Likely | 2026-09-27 | Shown |
| Utility | Southern California Edisonterritory 17609: SOUTHERN CALIFORNIA EDISON CO (INVESTOR OWNED, SOUTHERN CALIFOR | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | CAISOCALIFORNIA INDEPENDENT SYSTEM OPERATOR | [3] derived | Likely | — | Shown |
| Balancing authority | CISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Bryan Substation (66 kV)way/66983703 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 220 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 400 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 25.11¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 30.56¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 8.53 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 85,900 sq ft | [1] derived | Likely | 2026-09-27 | Shown |