Meta Montgomery

Operating + expandingAI campusCampusMontgomery, Montgomery County, Alabama
80% profile completeness
31 claims from 9 sources
Current facility power
199 MW[1]
Likelyestimated
Planned capacity
465 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$5.8B[1]
Likelyestimated
First operational
Jun 18, 2026[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Alabama Power CO · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
465 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
266 MW[1]
Buildings 3–4, Buildings 5–6 under construction (satellite-tracked phases)
Operational
199 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2027-02-02 (modeled/speculative)[1]
  • Required: 465 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionMar 1, 2025
    Model estimate · Satellite imagery
    • Mar 1, 2025 · Reported status: under construction[1]
    • Mar 1, 2025 · Construction start[1]
    • Mar 1, 2025 · Land clearing begins.[1]
    • Jun 18, 2026 · Reported status: expanding[1]
  3. EnergizationJun 18, 2026
    Satellite imagery
    • Jun 18, 2026 · We estimate Buildings 1 and 2 are operational.[1]
  4. OperationalJun 18, 2026
    Satellite imagery
    • Jun 18, 2026 · We estimate Buildings 1 and 2 are operational.[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Montgomery
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Alabama Power CO[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[4]
    Service territoryLikely
    Balancing authority: SOCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
32.27079, -86.32757
Address
Co Rd 42, Montgomery, AL 36105, USA[1]Likely
County
Montgomery County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Capital & construction
Contractor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Location falls inside this utility's retail service territory.

Contractor

Power (all fields)

Current facility power
199 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
153 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
465 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-02-23); not necessarily full build-out.

Estimated annual consumption
1,220 GWh/yr[3]Speculativeestimated

199 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[4]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
SOCO[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
8.42¢/kWh[5]Confirmed

Alabama statewide average, July 2026.

State avg. commercial price
14.83¢/kWh[5]Confirmed

Alabama statewide average, July 2026.

Generation within 50 km
2.02 GW[6]Confirmedderived

7 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Black Bear Solar 1 · Lightsource Renewable Energy Asset Management, LLCPower plant (Solar)8.2 km100 MW[6]
General Electric Plastic · Alabama Power CoPower plant (Natural Gas)19.1 km85 MW[6]
International Paper Prattville Mill · International Paper CoPower plant (Biomass)21.3 km85 MW[6]
E B Harris Electric Generating Plant · Southern Power CoPower plant (Natural Gas)26.2 km1.32 GW[6]
Walter Bouldin Dam · Alabama Power CoPower plant (Hydroelectric)35.1 km224 MW[6]
Jordan Dam · Alabama Power CoPower plant (Hydroelectric)39.3 km129 MW[6]
Jones Bluff · USCE-Mobile DistrictPower plant (Hydroelectric)43.3 km82 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Mar 1, 2025[1]
  5. First operational
    Jun 18, 2026[1]
  6. Expected completion
    Feb 23, 2027[1]
    Projected
Planned capacity
465 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-02-23); not necessarily full build-out.

Buildings (planned)
6[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
2[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2operational199 MWJun 18, 2026[1]
Buildings 3–4under construction67 MWFeb 2, 2027 (projected)[1]
Buildings 5–6under construction199 MWFeb 23, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$5.8B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed
Compute (H100-equivalents)
174,500[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Mar 1, 2025[1]→2Jun 18, 2026[1]
  • Status
    Under constructionMar 1, 2025[1]→Operating + expandingJun 18, 2026[1]

Timeline

Construction start: Mar 1, 2025[1]
First operational: Jun 18, 2026[1]
  1. Mar 1, 2025[1]

    Land clearing begins.

  2. Jul 4, 2025[1]

    Building 1 and 2 under construction, with all chillers visible.

  3. Mar 20, 2026[1]

    Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.

  4. Jun 18, 2026199 MW facility power· 2 buildings operational[1]

    We estimate Buildings 1 and 2 are operational.

  5. Feb 2, 2027Projected266 MW facility power· 4 buildings operational[1]

    Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.

  6. Feb 23, 2027Projected465 MW facility power· 6 buildings operational[1]

    Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.

All claims (provenance audit)

31
FieldValueSourceConfidenceAs ofStatus
NameMeta Montgomery[1] Likely2026-06-18Shown
StatusUnder construction[1] derivedLikely2025-03-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-07-04Superseded / alternative
StatusUnder construction[1] derivedLikely2026-03-20Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-06-18Shown
Facility typeAI campus[1] derivedLikely2026-06-18Shown
AddressCo Rd 42, Montgomery, AL 36105, USA[1] Likely2026-06-18Shown
OwnerMetaOwner: Meta[1] Confirmed2026-06-18Shown
End usersMetaUsers: Meta[1] Confirmed2026-06-18Shown
UtilityAlabama Power COterritory 195: ALABAMA POWER CO (INVESTOR OWNED, SOUTHERN COMPANY)[2] derivedLikely2022Shown
ConstructionHensel PhelpsConstruction companies: Hensel Phelps[1] Confirmed2026-06-18Shown
Current facility power199 MW[1] estimatedLikely2026-06-18Shown
Current IT capacity153 MW[1] estimatedLikely2026-06-18Shown
Planned capacity465 MW[1] estimatedLikely2026-06-18Shown
Estimated annual consumption1,220 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[4] derivedLikely—Shown
Balancing authoritySOCO[2] derivedLikely—Shown
State avg. industrial price8.42¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price14.83¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km2.02 GW[6] derivedConfirmed202502Shown
Buildings (planned)6[1] derivedLikely2026-06-18Shown
Buildings operational2[1] estimatedLikely2026-06-18Shown
Buildings operational0[1] estimatedLikely2025-03-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-07-04Superseded / alternative
Buildings operational0[1] estimatedLikely2026-03-20Superseded / alternative
Capital cost / investment$5.8B[1] estimatedLikely2026-06-18Shown
Compute (H100-equivalents)174,500[1] estimatedLikely2026-06-18Shown
Chip typesB300[1] Confirmed2026-06-18Shown
Construction startMar 1, 2025[1] derivedLikely2026-06-18Shown
First operationalJun 18, 2026[1] derivedLikely2026-06-18Shown
Expected completionFeb 23, 2027[1] estimatedSpeculative2026-06-18Shown