Meta Montgomery
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Montgomery
- →substationOn-site substation[1]Satellite imageryLikely4 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 32.27079, -86.32757
- Address
- County
- Montgomery County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
- Contractor
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-02-23); not necessarily full build-out.
- Estimated annual consumption
199 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Alabama statewide average, July 2026.
- State avg. commercial price
Alabama statewide average, July 2026.
- Generation within 50 km
7 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Black Bear Solar 1 · Lightsource Renewable Energy Asset Management, LLC | Power plant (Solar) | 8.2 km | 100 MW | [6] |
| General Electric Plastic · Alabama Power Co | Power plant (Natural Gas) | 19.1 km | 85 MW | [6] |
| International Paper Prattville Mill · International Paper Co | Power plant (Biomass) | 21.3 km | 85 MW | [6] |
| E B Harris Electric Generating Plant · Southern Power Co | Power plant (Natural Gas) | 26.2 km | 1.32 GW | [6] |
| Walter Bouldin Dam · Alabama Power Co | Power plant (Hydroelectric) | 35.1 km | 224 MW | [6] |
| Jordan Dam · Alabama Power Co | Power plant (Hydroelectric) | 39.3 km | 129 MW | [6] |
| Jones Bluff · USCE-Mobile District | Power plant (Hydroelectric) | 43.3 km | 82 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startMar 1, 2025[1]
- First operationalJun 18, 2026[1]
- Expected completionFeb 23, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-02-23); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Mar 1, 2025[1]
Land clearing begins.
- Jul 4, 2025[1]
Building 1 and 2 under construction, with all chillers visible.
- Mar 20, 2026[1]
Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.
We estimate Buildings 1 and 2 are operational.
Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.
Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.
All claims (provenance audit)
31| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Montgomery | [1] | Likely | 2026-06-18 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-03-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-07-04 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-20 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-06-18 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-18 | Shown |
| Address | Co Rd 42, Montgomery, AL 36105, USA | [1] | Likely | 2026-06-18 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-06-18 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-06-18 | Shown |
| Utility | Alabama Power COterritory 195: ALABAMA POWER CO (INVESTOR OWNED, SOUTHERN COMPANY) | [2] derived | Likely | 2022 | Shown |
| Construction | Hensel PhelpsConstruction companies: Hensel Phelps | [1] | Confirmed | 2026-06-18 | Shown |
| Current facility power | 199 MW | [1] estimated | Likely | 2026-06-18 | Shown |
| Current IT capacity | 153 MW | [1] estimated | Likely | 2026-06-18 | Shown |
| Planned capacity | 465 MW | [1] estimated | Likely | 2026-06-18 | Shown |
| Estimated annual consumption | 1,220 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | SOCO | [2] derived | Likely | — | Shown |
| State avg. industrial price | 8.42¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.83¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.02 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 6 | [1] derived | Likely | 2026-06-18 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-06-18 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-07-04 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-20 | Superseded / alternative |
| Capital cost / investment | $5.8B | [1] estimated | Likely | 2026-06-18 | Shown |
| Compute (H100-equivalents) | 174,500 | [1] estimated | Likely | 2026-06-18 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-06-18 | Shown |
| Construction start | Mar 1, 2025 | [1] derived | Likely | 2026-06-18 | Shown |
| First operational | Jun 18, 2026 | [1] derived | Likely | 2026-06-18 | Shown |
| Expected completion | Feb 23, 2027 | [1] estimated | Speculative | 2026-06-18 | Shown |