What changed — CPS Energy (City of San Antonio)
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Mar 31, 2026Microsoft SAT14 · TX
- Current IT capacity: 19 MW → 47 MW
- Current facility power: 26 MW → 66 MW
- Buildings operational: 1 → 2
- Status: Operating + expanding → Operating
- New capacity online: Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the si…
Source: Epoch AI - Jul 1, 2024Microsoft SAT14 · TX
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously inc…
Source: Epoch AI