What changed — Omaha Public Power District

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Aug 2, 2026
    Meta Sarpy · NE
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating
    • New capacity online: Building 1 is operational (estimate).
    Source: Epoch AI
  2. Jun 30, 2026
    Google Omaha · NE
    • Current IT capacity: 158 MW → 237 MW
    • Current facility power: 189 MW → 284 MW
    • Buildings operational: 2 → 3
    • New capacity online: Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
    Source: Epoch AI
  3. May 4, 2026
    Google Papillion · NE
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  4. Nov 19, 2024
    Google Omaha · NE
    • Current IT capacity: 79 MW → 158 MW
    • Current facility power: 95 MW → 189 MW
    • Buildings operational: 1 → 2
    • New capacity online: Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).
    Source: Epoch AI
  5. Aug 3, 2024
    Google Papillion · NE
    • Current IT capacity: 79 MW → 237 MW
    • Current facility power: 95 MW → 284 MW
    • Buildings operational: 1 → 3
    • New capacity online: Building 3 looks operational.
    Source: Epoch AI
  6. Aug 1, 2024
    Meta Sarpy · NE
    • Construction started: Building 1 grading underway.
    Source: Epoch AI
  7. Apr 8, 2024
    Google Omaha · NE
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.
    Source: Epoch AI