What changed — Sharka LLC

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. Jul 1, 2026
    Google Midlothian · TX
    • Current IT capacity: 69 MW → 103 MW
    • Current facility power: 82 MW → 123 MW
    • Status: Operating + expanding → Operating
    Source: Epoch AI
  2. Apr 19, 2026
    Google Midlothian · TX
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is probably mostly operational despite some cooling towers yet to be installed. In the original building permit Google only expected to build 6 new cooling towers, but they've extended the row further. This…
    Source: Epoch AI
  3. Nov 28, 2023
    Google Midlothian · TX
    • Construction started: Visible land clearing around the area for Building 1
    Source: Epoch AI