What changed — South Central Power Company
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Mar 12, 2026
- Oct 31, 2025Google Lancaster · OH
- Current IT capacity: 68 MW → 137 MW
- Current facility power: 82 MW → 164 MW
- Buildings operational: 1 → 2
- New capacity online: Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.
Source: Epoch AI - Jan 1, 2024Google Lancaster · OH
- Buildings operational: 0 → 1
- Status: Under construction → Operating + expanding
- New capacity online: Building 1 operational. This is estimated based on construction progress in October 2023. This also corresponds to a 2023 article where a Google spokesperson says that the "the Lancaster data center will open later th…
Source: Epoch AI