Google Lancaster
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationJan 1, 2024
Satellite imagery
- Jan 1, 2024 · Building 1 operational. This is estimated based on construction progress in [October 2023](https://earth.google.com/web/@39.72490515,-82.68845499,280.4138206a,1128.806013d,35y,-0h,[1]
- Oct 31, 2025 · Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.[1]
- OperationalJan 1, 2024
Satellite imagery
- Jan 1, 2024 · Building 1 operational. This is estimated based on construction progress in [October 2023](https://earth.google.com/web/@39.72490515,-82.68845499,280.4138206a,1128.806013d,35y,-0h,[1]
- Oct 31, 2025 · Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Lancaster
- →substationSatellite imageryLikely3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.27 km away
- →transmission138 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.28 km away). Not confirmed as the supply path.
- →utilitySouth Central Power Company[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 39.72403, -82.68972
- Address
- County
- Fairfield County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
164 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
11 EIA-reported plants within 50 km.
- Generation queued in county
7 active generation interconnection requests in Fairfield County: Solar 918 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.28 km | 138 kV | [5] |
| Renick Run Pumping Station 03-04 · City of Columbus - (OH) | Power plant (Petroleum) | 35.8 km | 2 MW | [8] |
| Yellowbud Solar, LLC · Yellowbud Solar LLC | Power plant (Solar) | 40.5 km | 274 MW | [8] |
| Ps St-8 Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 40.5 km | 2 MW | [8] |
| Denison Solar Array · AEP Onsite Partners, LLC | Power plant (Solar) | 41.5 km | 2 MW | [8] |
| Salt City Solar Project - Hybrid · Salt City Solar LLC | Power plant (Solar) | 41.6 km | 50 MW | [8] |
| Darby Power, LLC · Darby Power, LLC | Power plant (Natural Gas) | 41.8 km | 480 MW | [8] |
| Suburban Landfill Gas Recovery · WM Renewable Energy LLC | Power plant (Biomass) | 43.4 km | 6 MW | [8] |
| Atlanta Farms Solar · Dominion Renewable Energy | Power plant (Solar) | 45.5 km | 200 MW | [8] |
| Unnamed substation | Substation | 0.27 km | 138 kV | [5] |
| Unnamed substation | Substation | 0.29 km | 138 kV | [5] |
| Unnamed substation | Substation | 0.38 km | 138 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Muskingum-W. Millersport 345 kVPJM AE2-048 | Solar | IA signed · proposed 2022-06 | 220 MW | [6] |
| Harrison-Good Hope 138 kVPJM AG1-351 | Solar | In study · proposed 2023-12 | 142 MW | [6] |
| West Millersport 138 kVPJM AH1-032 | Solar | In study · proposed 2023-12 | 138 MW | [6] |
| West Millersport 138 kVPJM AG2-003 | Solar | In study · proposed 2023-12 | 120 MW | [6] |
| Muskingum River-W. Millersport 345 kVPJM AE2-136 | Solar | In study · proposed 2022-06 | 114 MW | [6] |
| West Millersport 138 kVPJM AG1-163 | Solar | In study · proposed 2023-12 | 100 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Oct 1, 2021[1]
Land clearing in progress for the site
Building 1 operational. This is estimated based on construction progress in October 2023. This also corresponds to a 2023 article where a Google spokesperson says that the "the Lancaster data center will open later this year".
Building 2 is close to completion. Structurally it is already complete, but there is still some equipment strewn around the building that suggests commissioning is ongoing.
Building 2 operational. This is supported by the state of Building 2 a month prior, which is entirely complete outside of some equipment that was removed later on.
At this point, Building 1 and 2 have since already been operational. Additionally, there is visible steam showing clear evidence of operational for both before this date.
Buildings on this campus
2All claims (provenance audit)
40| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Lancaster | [1] | Likely | 2026-03-12 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-01-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-11 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-31 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-03-12 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-03-12 | Shown |
| Address | 105 Whiley Rd, Lancaster, OH 43130 | [1] | Likely | 2026-03-12 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-03-12 | Shown |
| Utility | South Central Power Companyterritory 18085: SOUTH CENTRAL POWER COMPANY (COOPERATIVE, SOUTH CENTRAL POWER C | [2] derived | Likely | 2022 | Shown |
| Current facility power | 164 MW | [1] estimated | Likely | 2026-03-12 | Shown |
| Current facility power | 82 MW | [1] estimated | Likely | 2024-01-01 | Superseded / alternative |
| Current facility power | 82 MW | [1] estimated | Likely | 2025-09-11 | Superseded / alternative |
| Current facility power | 164 MW | [1] estimated | Likely | 2025-10-31 | Superseded / alternative |
| Current IT capacity | 137 MW | [1] estimated | Likely | 2026-03-12 | Shown |
| Current IT capacity | 68 MW | [1] estimated | Likely | 2024-01-01 | Superseded / alternative |
| Current IT capacity | 68 MW | [1] estimated | Likely | 2025-09-11 | Superseded / alternative |
| Current IT capacity | 137 MW | [1] estimated | Likely | 2025-10-31 | Superseded / alternative |
| Estimated annual consumption | 1,006 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1245829347 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 918 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.02 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-03-12 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-03-12 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-10-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-01-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-09-11 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-10-31 | Superseded / alternative |
| Capital cost / investment | $5.2B | [1] estimated | Likely | 2026-03-12 | Shown |
| Compute (H100-equivalents) | 130,400 | [1] estimated | Likely | 2026-03-12 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-03-12 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-03-12 | Shown |
| Construction start | Oct 1, 2021 | [1] derived | Likely | 2026-03-12 | Shown |
| First operational | Jan 1, 2024 | [1] derived | Likely | 2026-03-12 | Shown |