What changed — TeraWulf Brookings LLC
RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.
- Mar 29, 2025Wulf Compute Data Center II · NY
- Permit / site plan filed: NYISO load interconnection request 1732 filed (250 MW).
Source: New York ISO