Wulf Compute Data Center II
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- From “System impact study”, large loads have typically taken 1.5–3.5 more years to first power (editorial range; see Methodology).
- Stated dates slip; the window allows up to 2 years past the stated date at this stage.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Feasibility study
ISO/RTO queue
- NYISO load request 1732 (250 MW): Status 5 (SRIS/SIS in progress); proposed initial backfeed: 07-2030 (queue status as of 2026-09-27)[1]
- System impact study
ISO/RTO queue
- NYISO load request 1732 (250 MW): Status 5 (SRIS/SIS in progress); proposed initial backfeed: 07-2030 (queue status as of 2026-09-27)[1]
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: ISO/RTO queue.
Grid path
- →facilityWulf Compute Data Center II
- →substationKintigh 345kV sub-station[1]Queue POIConfirmedPoint of interconnection in NYISO load request 1732
- →transmission345 kV[1]Queue POILikelyVoltage at the requested point of interconnection (Kintigh 345kV sub-station)
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
NYISO 1732 Wulf Compute Data Center II · TeraWulf Brookings LLC | This site's load request Confirmed Site record created from this queue entry. | System impact study Status 5 (SRIS/SIS in progress); proposed initial backfeed: 07-2030 | 250 | — | Mar 29, 2025 | Jul 2030 | Kintigh 345kV sub-station TO: NYSEG | [1] Sep 27, 2026 |
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 43.20113, -78.74460
- County
- Niagara County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
Interconnection customer on the load request.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
The request is in this ISO's queue.
- Interconnection status
- Load interconnection request
NYISO load interconnection request 1732 (Data center (AI)).
- Contracted / committed power
- Not yet sourced
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
All claims (provenance audit)
7| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Wulf Compute Data Center II | [1] | Confirmed | 2026-09-27 | Shown |
| Status | Planned | [1] derived | Confirmed | 2026-09-27 | Shown |
| Facility type | Unclassified | [1] derived | Confirmed | 2026-09-27 | Shown |
| Developer | TeraWulf Brookings LLC | [1] | Likely | 2026-09-27 | Shown |
| ISO / RTO | NYISO | [1] | Confirmed | 2026-09-27 | Shown |
| Interconnection status | NYISO load request 1732: 250 MW, in study at Kintigh 345kV sub-stationStatus 5 (SRIS/SIS in progress); proposed initial backfeed: 07-2030 · requested | [1] | Confirmed | 2026-09-27 | Shown |
| Load interconnection request | 250 MW | [1] | Confirmed | 2026-09-27 | Shown |