Applied Digital
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityApplied Digital
- →substationHarwood Substation (69 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 1.03 km away. Proximity does not establish that it serves the site.
- →transmissionMaple River - Winger 230kV[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.88 km away). Not confirmed as the supply path.
- →utilityNorthern States Power CO - Minnesota[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Street address- Coordinates
- 46.97417, -96.87394
- Address
- County
- Cass County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Otter Tail Power CO, Wapa-- Western Area Power Administration, Cass County Elec Coop INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
North Dakota statewide average, July 2026.
- State avg. commercial price
North Dakota statewide average, July 2026.
- Generation within 50 km
13 EIA-reported plants within 50 km.
- Generation queued in county
5 active generation interconnection requests in Cass County: Hybrid 481 MW, Solar 400 MW, Wind 200 MW, Storage 200 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 69 kV line · Minnkota Power Cooperative | Transmission line | 0.31 km | 69 kV | [1] |
| Maple River - Winger 230kV · Minnkota Power Cooperative | Transmission line | 0.88 km | 230 kV | [1] |
| American Crystal Sugar Moorhead · American Crystal Sugar Co | Power plant (Coal) | 11.7 km | 5 MW | [6] |
| Moorhead Wind Turbine · City of Moorhead - (MN) | Power plant (Wind) | 13.8 km | 1 MW | [6] |
| Centennial Generating Station · City of Moorhead - (MN) | Power plant (Petroleum) | 15.4 km | 10 MW | [6] |
| Uss Buckaroo Solar LLC Csg · Standard Solar | Power plant (Solar) | 28.3 km | 1 MW | [6] |
| Agassiz Beach LLC · CHI Operations Inc | Power plant (Wind) | 33.4 km | 2 MW | [6] |
| Kindred School · Kindred Public School | Power plant (Petroleum) | 37.5 km | 2 MW | [6] |
| Halstad · City of Halstad - (MN) | Power plant (Petroleum) | 41.9 km | 4 MW | [6] |
| Hillsboro · City of Hillsboro - (ND) | Power plant (Petroleum) | 49.1 km | 4 MW | [6] |
| Harwood Substation · Minnkota Power Cooperative | Substation | 1.03 km | 69 kV | [1] |
| Prosper Substation · Minnkota Power Cooperative | Substation | 1.37 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J3163 at BISONMISO J3163 | Hybrid | In study · proposed 2028-03 | 481 MW | [4] |
| J3833 at Buffalo 115 kVMISO J3833 | Wind | In study · proposed 2028-09 | 200 MW | [4] |
| J3522 at BisonMISO J3522 | Solar | In study · proposed 2028-08 | 200 MW | [4] |
| J1588 at BISONMISO J1588 | Solar | IA signed · proposed 2023-09 | 200 MW | [4] |
| S1079 at BISONMISO S1079 | Storage | In study · proposed 2028-07 | 200 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
13| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Applied Digitalnode/13639231258 name=Applied Digital | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 6805 County Rd 81 N, Harwood, ND 58042 | [1] | Likely | 2026-09-27 | Shown |
| Utility | Northern States Power CO - Minnesotaterritory 13781: NORTHERN STATES POWER CO - MINNESOTA (INVESTOR OWNED, XCEL ENER | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [3] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Harwood Substation (69 kV)way/837429641 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.28 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 8.21¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.22¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 34 MW | [6] derived | Confirmed | 202502 | Shown |