DC
/

Atlas Powr Williston Datacenter

OperatingUnclassifiedBuildingWilliams County, North Dakota
20% profile completeness
14 claims from 6 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Mountrail-Williams Elec Coop · SPP
Substation: Atlas Power Datacenter Substation (230 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Atlas Powr Williston Datacenter
  2. substation
    Atlas Power Datacenter Substation (230 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.2 km away. Proximity does not establish that it serves the site.
  3. transmission
    Pioneer - Judson (345 kV)[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.18 km away). Not confirmed as the supply path.
  4. utility
    Mountrail-Williams Elec Coop[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    SPP[3]
    Service territoryLikely
    Balancing authority: SWPP
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
48.14595, -103.77277
County
Williams County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Most likely retail provider among 7 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Montana-Dakota Utilities CO, Basin Electric Power Coop, Lower Yellowstone R E A, INC, Burke-Divide Electric Coop INC, Sheridan Electric Coop, INC.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
SPP[3]Likelyderived

Location falls inside overlapping MISO and SPP footprints; chosen by the balancing areas of the overlapping utilities.

Balancing authority
SWPP[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Atlas Power Datacenter Substation (230 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.2 km[1]Likelyderived
Highest-voltage line nearby
345 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
8.21¢/kWh[5]Confirmed

North Dakota statewide average, July 2026.

State avg. commercial price
8.22¢/kWh[5]Confirmed

North Dakota statewide average, July 2026.

Generation within 50 km
598 MW[6]Confirmedderived

5 EIA-reported plants within 50 km.

Generation queued in county
1.95 GW[4]Confirmedderived

4 active generation interconnection requests in Williams County: Gas 1,490 MW, Wind 255 MW, Storage 200 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV lineTransmission line0.17 km230 kV[1]
Pioneer - Judson · Basin Electric Power CooperativeTransmission line0.18 km345 kV[1]
Judson - Patent Gate 345kV · Basin Electric Power CooperativeTransmission line0.22 km345 kV[1]
345 kV lineTransmission line0.26 km345 kV[1]
Judson - Williston · Basin Electric Power CooperativeTransmission line0.27 km230 kV[1]
Judson - Tande 345kV · Basin Electric Power CooperativeTransmission line0.4 km345 kV[1]
Pioneer Generation Station · Basin Electric Power CoopPower plant (Natural Gas)16.5 km233 MW[6]
Lonesome Creek Station · Basin Electric Power CoopPower plant (Natural Gas)41.4 km240 MW[6]
Culbertson Generation Station · Basin Electric Power CoopPower plant (Natural Gas)46.4 km85 MW[6]
Oreg 1 INC · Ormat Nevada IncPower plant (Other)46.9 km20 MW[6]
Oreg 2 INC · Ormat Nevada IncPower plant (Other)46.9 km20 MW[6]
Atlas Power Datacenter Substation · Atlas Power Holdings (ND) LLCSubstation0.2 km230 kV[1]
Mountrail-Williams Electric Cooperative substation · Mountrail-Williams Electric CooperativeSubstation0.32 km115 kV[1]
Judson Substation · Basin Electric Power CooperativeSubstation0.34 km345 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
GEN-2024-082 at Springbrook - Tande 345 kV LineSPP GEN-2024-082GasIn study · proposed 2030-03745 MW[4]
GEN-2024-081 at Springbrook - Tande 345 kV LineSPP GEN-2024-081GasIn study · proposed 2029-02745 MW[4]
GEN-2018-067 at 115kV Strandahl sub SPP GEN-2018-067WindIA signed · proposed 2028-05255 MW[4]
GEN-2024-329 at Pleasant Valley 115 kV SubstationSPP GEN-2024-329StorageIn study · proposed 2028-01200 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Site area
32.9 acres[1]Likelyderived

Area of the mapped OSM site outline.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

14
FieldValueSourceConfidenceAs ofStatus
NameAtlas Powr Williston Datacenterway/1545814424 name=Atlas Powr Williston Datacenter[1] Likely2026-09-27Shown
StatusOperating[1] derivedUnverified2026-09-27Shown
OperatorAtlas Power Holdings (ND) LLCoperator=Atlas Power Holdings (ND) LLC[1] Likely2026-09-27Shown
UtilityMountrail-Williams Elec Coopterritory 20413: MOUNTRAIL-WILLIAMS ELEC COOP (COOPERATIVE, MOUNTRAIL-WILLIAMS E[2] derivedUnverified2022Shown
ISO / RTOSPPMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | SOUTHWEST POWER P[3] derivedLikely—Shown
Balancing authoritySWPP[2] derivedLikely—Shown
Nearest mapped substationAtlas Power Datacenter Substation (230 kV)way/1545814434[1] derivedLikely2026-09-28Shown
Distance to substation0.2 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.95 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price8.21¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price8.22¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km598 MW[6] derivedConfirmed202502Shown
Site area32.9 acres[1] derivedLikely2026-09-27Shown