Carrier Services Group
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityCarrier Services Group
- →substationUnnamed substation[1]Proximity onlyUnverifiedNearest mapped substation, 0.32 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.96 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.04110, -80.63280
- Address
- County
- Mahoning County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
18 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Mahoning County: Solar + storage 150 MW, Solar 61 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 69 kV line | Transmission line | 0.95 km | 69 kV | [1] |
| 138 kV line | Transmission line | 0.96 km | 138 kV | [1] |
| 23 kV line | Transmission line | 1.83 km | 23 kV | [1] |
| Niles Power Plant · Niles Power, LLC | Power plant (Petroleum) | 17 km | 26 MW | [6] |
| Hickory Run Energy Station · Hickory Run Energy, LLC | Power plant (Natural Gas) | 17.8 km | 938 MW | [6] |
| Clean Energy Future-Lordstown, LLC · Clean Energy Future-Lordstown, LLC | Power plant (Natural Gas) | 21.9 km | 858 MW | [6] |
| New Castle Plant · New Castle Power, LLC | Power plant (Natural Gas) | 24.9 km | 331 MW | [6] |
| South Field Energy · South Field Energy, LLC | Power plant (Natural Gas) | 45.3 km | 1.21 GW | [6] |
| Shell Chemical Appalachia LLC · Shell Chemical Appalachia LLC | Power plant (Natural Gas) | 48.1 km | 257 MW | [6] |
| Pine 1 Solar · BE-Pine1 LLC | Power plant (Solar) | 49.4 km | 17 MW | [6] |
| Beaver Valley · Energy Harbor Nuclear Generation LLC | Power plant (Nuclear) | 49.5 km | 1.81 GW | [6] |
| Unnamed substation | Substation | 0.32 km | — | [1] |
| Mathews Substation · Ohio Edison | Substation | 1.2 km | 69 kV | [1] |
| Unnamed substation | Substation | 1.25 km | 69 kV | [1] |
| Unnamed substation | Substation | 1.44 km | 69 kV | [1] |
| Unnamed substation | Substation | 1.82 km | 69 kV | [1] |
| Bancroft Substation · Ohio Edison | Substation | 2.04 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Lordstown - Mansfield 345 kVPJM AH1-639 | Solar + storage | In study · proposed 2025-10 | 150 MW | [4] |
| Bluebell-Sancap Tap 69 kVPJM AG2-591 | Solar | In study · proposed 2024-06 | 61 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
14| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Carrier Services Groupway/1210421871 name=Carrier Services Group | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 5635 South Avenue, Boardman, OH 44512 | [1] | Likely | 2026-09-27 | Shown |
| Utility | Ohio Edisonterritory 13998: OHIO EDISON CO (INVESTOR OWNED, FIRSTENERGY CORP) | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substationway/829417085 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 211 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.5 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 75,500 sq ft | [1] derived | Likely | 2026-09-27 | Shown |