Comcast
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityComcast
- →substationDix Substation (40 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.48 km away. Proximity does not establish that it serves the site.
- →transmission120 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.91 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 42.21390, -83.19821
- Address
- County
- Wayne County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wyandotte Municipal Serv Comm.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Michigan statewide average, July 2026.
- State avg. commercial price
Michigan statewide average, July 2026.
- Generation within 50 km
22 EIA-reported plants within 50 km.
- Generation queued in county
7 active generation interconnection requests in Wayne County: Storage 950 MW, Gas 50 MW, Other 8 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 40 kV line | Transmission line | 0.47 km | 40 kV | [1] |
| Trunk 5140 · DTE Energy | Transmission line | 0.55 km | 40 kV | [1] |
| 120 kV line | Transmission line | 1.91 km | 120 kV | [1] |
| Jupiter - Navarre · ITC | Transmission line | 1.93 km | 120 kV | [1] |
| Jupiter - Taurus · ITC | Transmission line | 1.95 km | 120 kV | [1] |
| Jupiter - Taurus;Jupiter - Navarre · ITC | Transmission line | 1.98 km | 120 kV | [1] |
| Dearborn Industrial Generation · Dearborn Industrial Gen Inc | Power plant (Natural Gas) | 10.5 km | 739 MW | [6] |
| Delray · DTE Electric Company | Power plant (Natural Gas) | 12 km | 127 MW | [6] |
| Sumpter · Wolverine Power Supply Coop | Power plant (Natural Gas) | 28 km | 308 MW | [6] |
| Fermi · DTE Electric Company | Power plant (Nuclear) | 28.3 km | 1.19 GW | [6] |
| Northeast (Mi) · DTE Electric Company | Power plant (Natural Gas) | 29.4 km | 101 MW | [6] |
| Monroe (Mi) · DTE Electric Company | Power plant (Coal) | 38 km | 3.08 GW | [6] |
| Hancock · DTE Electric Company | Power plant (Natural Gas) | 42.4 km | 93 MW | [6] |
| University of Michigan · University of Michigan | Power plant (Natural Gas) | 44.8 km | 57 MW | [6] |
| Dix Substation · DTE Energy | Substation | 0.48 km | 40 kV | [1] |
| DTE Energy substation · DTE Energy | Substation | 1.89 km | 24 kV | [1] |
| Jupiter Substation · ITC | Substation | 1.92 km | 120 kV | [1] |
| Substation 7 · Wyandotte Municipal Services | Substation | 2.98 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J3872 at RIVER ROUGEMISO J3872 | Storage | In study · proposed 2029-01 | 350 MW | [4] |
| J1902 at IRONTONMISO J1902 | Storage | In study · proposed 2024-09 | 200 MW | [4] |
| J1900 at Brownstown 12 120kVMISO J1900 | Storage | In study · proposed 2024-09 | 200 MW | [4] |
| J2991 at Dayton 120kV SubstationMISO J2991 | Storage | In study · proposed 2025-09 | 200 MW | [4] |
| J1262 at Waterman 120kV SubstationMISO J1262 | Gas | IA signed · proposed 2019-06 | 25 MW | [4] |
| J1798 at Waterman 120kVMISO J1798 | Gas | IA signed · proposed 2021-06 | 25 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
15| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Comcastway/812630939 name=Comcast | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 14312 Northline Road, Southgate, MI 48195 | [1] | Likely | 2026-09-27 | Shown |
| Operator | Comcastoperator=Comcast | [1] | Likely | 2026-09-27 | Shown |
| Utility | DTE Electricterritory 5109: DTE ELECTRIC COMPANY (INVESTOR OWNED, DTE ENERGY) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [3] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Dix Substation (40 kV)way/810517914 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.5 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 120 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.01 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.81¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 16.46¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.91 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 1,000 sq ft | [1] derived | Likely | 2026-09-27 | Shown |