DC
/

Compass Meridian

UnknownUnclassifiedCampusMeridian, Lauderdale County, Mississippi
10% profile completeness
9 claims from 5 sources
Current facility power
Not yet sourced
Planned capacity
500 MW[1]
Likely
Floor area
Not yet sourced
Buildings (planned)
Likely
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H2 2028 – H2 2032
Low confidencewindow, not a prediction
Project verification
Announced only
Only announcements or press coverage found.
Current stage
Announced
Furthest stage with documented evidence
Utility · ISO
Mississippi Power · None (non-RTO region)
Substation: Not identified

Power reality

Announced
500 MW[1]
Reported by Edison Electric Institute
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
  • ⚠ No grid, construction or operating record yet backs the 500 MW announced.
  • ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
  • ⚠ No recorded land acquisition found.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Announced (furthest stage with documented evidence)[1]
  • No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
  • Required: 500 MW
Assumptions
  • From “Announced”, large loads have typically taken 2–5 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H2 2028 – H2 2032

Project verification

Development
  1. AnnouncedSep 11, 2026
    Utility filing / announcement
    • Sep 11, 2026 · Planned capacity reported: 500 MW[1]
  2. Land acquired
  3. Planning / zoning
  4. Permitting
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under construction
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Utility filing / announcement.

Grid path

  1. facility
    Compass Meridian
  2. substation
    Not identified
    UnknownUnverified
    No substation mapped within 3 km and none named in filings.
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Mississippi Power[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    None (non-RTO region)[2]
    Service territoryLikely
    Balancing authority: SOCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

County-level (approximate)

Location is approximate (county-level (approximate)); the marker does not identify the exact site.

Coordinates
32.40428, -88.66217
County
Lauderdale County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Developer

“Compass Datacenters / Data Center Meridian, MS”

Utility

“Compass Datacenters / Data Center Meridian, MS” Listed by EEI under this member utility.

No tenants or end users identified in our sources yet.

Power (all fields)

Planned capacity
500 MW[1]Likely

“Approx. 500 MW to be supplied over eight buildings.” — Approximate.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[2]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
SOCO[3]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
7.66¢/kWh[4]Confirmed

Mississippi statewide average, July 2026.

State avg. commercial price
13.65¢/kWh[4]Confirmed

Mississippi statewide average, July 2026.

Generation within 50 km
1.1 GW[5]Confirmedderived

6 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Meridian III · SR Meridian III, LLCPower plant (Solar)11.9 km53 MW[5]
Sweatt · Mississippi Power CoPower plant (Natural Gas)14.7 km32 MW[5]
Meridian · Tennessee Valley AuthorityPower plant (Petroleum)17.1 km9 MW[5]
Meridian II · SR Meridian II, LLCPower plant (Solar)18.3 km5 MW[5]
Ratcliffe · Mississippi Power CoPower plant (Natural Gas)29.4 km704 MW[5]
Kemper County · Tennessee Valley AuthorityPower plant (Natural Gas)44.1 km293 MW[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —
Planned capacity
500 MW[1]Likely

“Approx. 500 MW to be supplied over eight buildings.” — Approximate.

Buildings (planned)
8[1]Likely

“Approx. 500 MW to be supplied over eight buildings.”

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

9
FieldValueSourceConfidenceAs ofStatus
DeveloperCompass Datacenters[1] Confirmed2026-09-11Shown
UtilityMississippi Power[1] Confirmed2026-09-11Shown
Planned capacity500 MW[1] Likely2026-09-11Shown
ISO / RTONone (non-RTO region)[2] derivedLikely—Shown
Balancing authoritySOCO[3] derivedLikely—Shown
State avg. industrial price7.66¢/kWh[4] Confirmed2026-07Shown
State avg. commercial price13.65¢/kWh[4] Confirmed2026-07Shown
Generation within 50 km1.1 GW[5] derivedConfirmed202502Shown
Buildings (planned)8[1] Likely2026-09-11Shown