DC
/

Digital Crossroad

OperatingUnclassifiedBuildingHammond, Lake County, Indiana
30% profile completeness
16 claims from 7 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
116,100 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
NIPSCO · MISO
Substation: State Line Substation (138 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Digital Crossroad
  2. substation
    State Line Substation (138 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.15 km away. Proximity does not establish that it serves the site.
  3. transmission
    Burnham - Calumet 345 kV[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.39 km away). Not confirmed as the supply path.
  4. utility
    NIPSCO[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    MISO[3]
    Service territoryLikely
    Balancing authority: MISO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
41.70740, -87.51997
Address
100 Digital Crossroad Drive, Hammond, IN 46320[1]Likely
County
Lake County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:
NIPSCO[2]Likely

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility
NIPSCO[2]Likely

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
MISO[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
MISO[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
State Line Substation (138 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.2 km[1]Likelyderived
Highest-voltage line nearby
345 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.16¢/kWh[5]Confirmed

Indiana statewide average, July 2026.

State avg. commercial price
13.30¢/kWh[5]Confirmed

Indiana statewide average, July 2026.

Generation within 50 km
3.81 GW[6]Confirmedderived

63 EIA-reported plants within 50 km.

Generation queued in county
1.5 GW[4]Confirmedderived

9 active generation interconnection requests in Lake County: Storage 800 MW, Solar 600 MW, Unknown 100 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Burnham - Calumet 345 kV · Commonwealth EdisonTransmission line0.39 km345 kV[1]
345 kV lineTransmission line0.46 km345 kV[1]
Burnham - Calumet 345 kV & State Line - Harbor 138 kV · Commonwealth EdisonTransmission line0.47 km345 kV[1]
Burnham - State Line 345 kVTransmission line0.49 km345 kV[1]
Burnham - State Line 345 kV & 138 kV · Commonwealth EdisonTransmission line1.66 km345 kV[1]
Burnham - Calumet 345 kV & Burnham - State Line 138 kV · Commonwealth EdisonTransmission line1.66 km345 kV[1]
Calumet Energy Team LLC · IPA Operations Inc - CalumetPower plant (Natural Gas)4 km326 MW[6]
Whiting Clean Energy · BP Alternative EnergyPower plant (Natural Gas)5.1 km513 MW[6]
Fisk Street · Midwest Generations EME LLCPower plant (Petroleum)19.4 km197 MW[6]
Crete Energy Venture LLC · Earthrise Energy, PBCPower plant (Natural Gas)32 km300 MW[6]
Arcelormittal Burns Harbor · Cleveland-Cliffs Burns Harbor LLCPower plant (Other)32.7 km175 MW[6]
University Park North · LSP University Park LLCPower plant (Natural Gas)35.2 km540 MW[6]
University Park South · University Park Energy LLCPower plant (Natural Gas)35.4 km300 MW[6]
Lincoln Generating Facility · Earthrise Energy, PBCPower plant (Natural Gas)49.6 km623 MW[6]
State Line Substation · Commonwealth EdisonSubstation0.15 km138 kV[1]
Unnamed substationSubstation0.24 km—[1]
State Line Substation · Commonwealth EdisonSubstation0.31 km—[1]
Unnamed substationSubstation0.41 km138 kV[1]
State Line Substation · Commonwealth EdisonSubstation0.47 km345 kV[1]
Unnamed substationSubstation1.88 km69 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
J1058 at Schahfer-St. John 345kV Line TapMISO J1058SolarUnder construction · proposed 2021-10300 MW[7]
J2215 at SCHAHFER GEN STA - ST. JOHN 345.0kVMISO J2215StorageIn study · proposed 2024-09300 MW[7]
Olive-Reynolds 345 kVPJM AE2-045SolarIA signed · proposed 2022-12200 MW[4]
Lake - 270888 345kVPJM AI2-023StorageIn study · proposed 2028-12200 MW[4]
R5076 at SCHAHFER GEN STA - ST. JOHN 345.0kVMISO R5076StorageIn study · proposed 2024-06200 MW[7]
J1386 at Green Acres 138 kV SubstationMISO J1386SolarIA signed · proposed 2022-07100 MW[7]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
116,100 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

16
FieldValueSourceConfidenceAs ofStatus
NameDigital Crossroadway/978934687 name=Digital Crossroad[1] Likely2026-09-27Shown
StatusOperating[1] derivedUnverified2026-09-27Shown
Websitehttps://digitalcrossroad.com/data-centers/indiana-data-center/[1] Likely2026-09-27Shown
Address100 Digital Crossroad Drive, Hammond, IN 46320[1] Likely2026-09-27Shown
OperatorDigital Crossroadoperator=Digital Crossroad[1] Likely2026-09-27Shown
UtilityNIPSCOterritory 13756: NORTHERN INDIANA PUB SERV CO (INVESTOR OWNED, NISOURCE INC)[2] derivedLikely2022Shown
ISO / RTOMISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC..[3] derivedLikely—Shown
Balancing authorityMISO[2] derivedLikely—Shown
Nearest mapped substationState Line Substation (138 kV)way/978934685[1] derivedLikely2026-09-28Shown
Distance to substation0.2 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.5 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price9.16¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price13.30¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km3.81 GW[6] derivedConfirmed202502Shown
Building footprint116,100 sq ft[1] derivedLikely2026-09-27Shown