DC
/

Indiana

Facilities
12
5 campuses
Power online
1.33 GW
2 sites reporting
Under construction
1.04 GW
planned MW at active sites
Planned
—
0 planned sites (MW not disclosed)
AI campuses
3
1.33 GW online · 1.04 GW pipeline
AI compute
0.89M
H100-equivalents (est.)
Capital (reported + est.)
$17.7B

Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Average industrial electricity price: 9.16¢/kWh (EIA).

AI data center capacity over time

Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly

0 MW1 GW2 GW3 GW4 GW2026202720282029
Observed (satellite-tracked) Projected

Construction pipeline by expected completion

MW from phases with a projected completion date

2026
2027
2028

Power reality

Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.

  • Announced4.07 GW
  • Interconnection requests—
  • Contracted / approved—
  • Under construction2.25 GW
  • Operational1.33 GW

838 MW announced at 2 sites has no grid, construction or operating record yet.

Pending MW by time to power

Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.

Largest gaps: announced vs documented
Verified operating: 2Under construction: 1Announced only: 2Unverified: 7

Interconnection queues

Active requests to connect to the grid (MISO, PJM). Requests are applications, not commitments — most never get built.

Generation seeking interconnection79.9 GW · 412 requests
Solar 41.06 GWStorage 15.45 GWGas 7.76 GWSolar + storage 5.8 GWWind 5.76 GWHybrid 3.68 GW

Markets

Click through to drill down

Online Under construction + planned
NameFacilitiesOnlinePipeline
Northern Indiana (New Carlisle)41.09 GW—
Chicago1——

Largest operators & owners

Online + pipeline MW at linked facilities

Online Under construction + planned

Largest customers & end users

Tenants and workload owners, where sourced

Online Under construction + planned

Utility exposure

Most likely retail utility by location (approximate)

Online Under construction + planned

Grid operators (ISO / RTO)

By facility location

Online Under construction + planned
  • PJM1.09 GW + 1.04 GW · 3 sites
  • MISO241 MW + 0 MW · 9 sites

Largest facilities

By online + pipeline MW

FacilityStatusOnlinePipeline
Anthropic-Amazon New CarlisleOperating1.09 GW—
Google Fort WayneUnder construction—1.04 GW
Meta JeffersonvilleOperating241 MW—

Facilities by status

  • Operating9
  • Under construction1
  • Unknown2