DC
/

Goodnight

Under constructionAI campusCampusClaude, Armstrong County, Texas
60% profile completeness
30 claims from 11 sources
Current facility power
Not yet sourced
Planned capacity
1.29 GW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Dec 15, 2026[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H1 2028
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
Southwestern Public Service CO · SPP
Substation: On-site substation

Power reality

Announced
1.29 GW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
1.3 GW[1]
Building 1, Building 2, Buildings 3–6 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — SPP does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2025-05-19 (1.4 years).
  • Stated date: Next projected milestone: 2026-12-15 (modeled/speculative)[1]
  • Required: 1.29 GW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H1 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionMay 19, 2025
    Model estimate · Satellite imagery
    • May 19, 2025 · Reported status: under construction[1]
    • May 19, 2025 · Construction start[1]
    • May 19, 2025 · Land clearing begins[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Goodnight
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    2 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Southwestern Public Service CO[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    SPP[3]
    Service territoryLikely
    Balancing authority: SWPP
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

QueueRelationshipStageMW req.MW appr.QueuedExpected in servicePOI / TOSource · as of
ERCOT 23INR0637
Goodnight Wind II · FGE Goodnight II, LLC · Wind
Possibly related generation
Speculative
Generation request name/developer shares “goodnight” with this facility, in the same county. Not confirmed as serving it.
Interconnection agreement executed
SS Completed, FIS Completed, IA
261.1——Jun 6, 2027tap 345kV 23900 Alibates - 23914 Tule Canyon CKT2[4] Sep 1, 2026

On-site & dedicated generation

  • 1 on-site power generator outline traced on satellite imagery[1]
    Epoch AI satellite annotations (fuel type and capacity not identified)
    Unknown typeBehind-the-meterLikely
  • ERCOT 23INR0637 Goodnight Wind II (Wind, 261.1 MW requested)[4]
    Generation request name/developer shares “goodnight” with this facility, in the same county. Not confirmed as serving it.
    WindArrangement unknown261 MWSpeculative

Location & imagery

Mapped outline
Coordinates
35.02016, -101.30226
Address
10001 Lima Rd, Claude, TX 79019[1]Likely
County
Armstrong County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Google[1]Speculative
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Capital & construction
Contractor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Google[1]Speculative
End user
Utility

Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Greenbelt Electric Coop, INC, Swisher Electric Coop, INC.

Energy partner
Contractor
Crusoe[1]Confirmed

Power (all fields)

Planned capacity
1.29 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-10-01); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
SPP[3]Likelyderived

Location falls inside overlapping SPP and ERCOT footprints; chosen by the balancing areas of the overlapping utilities.

Balancing authority
SWPP[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
7.07¢/kWh[5]Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[5]Confirmed

Texas statewide average, July 2026.

Generation within 50 km
2.11 GW[6]Confirmedderived

13 EIA-reported plants within 50 km.

Generation queued in county
3.25 GW[4]Confirmedderived

5 active generation interconnection requests in Armstrong County: Wind 1,705 MW, Storage 1,043 MW, Solar 504 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Goodnight · FGE Goodnight I, LLCPower plant (Wind)8.5 km266 MW[6]
Route 66 Wind Plant · Onward EnergyPower plant (Wind)23.8 km150 MW[6]
Grandview Wind Farm, LLC · RWE Renewables Americas, LLCPower plant (Wind)24.3 km211 MW[6]
Colbeck'S Corner, LLC · RWE Renewables Americas, LLCPower plant (Wind)28.1 km200 MW[6]
Salt Fork Wind Project, LLC · Southern Power CoPower plant (Wind)38 km174 MW[6]
Pattern Panhandle Wind LLC · Pattern Operators LPPower plant (Wind)45.5 km218 MW[6]
Pattern Panhandle Wind 2 LLC · Pattern Operators LPPower plant (Wind)47.4 km182 MW[6]
Nichols · Southwestern Public Service CoPower plant (Natural Gas)49.9 km457 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
Zeus Armstrong BESSERCOT 25INR0587 · Armstrong BESS, LLCStorageUnder construction · proposed 2028-041.04 GW[4]
Complex Serenity WindERCOT 28INR0215 · Serenity Wind, LLCWindIn study · proposed 2029-04971 MW[4]
Zeus Armstrong SolarERCOT 25INR0586 · Armstrong Solar, LLCSolarUnder construction · proposed 2028-04504 MW[4]
Serenity WindERCOT 27INR0443 · Serenity Wind, LLCWindIn study · proposed 2028-09473 MW[4]
Goodnight Wind IIERCOT 23INR0637 · FGE Goodnight II, LLCWindIA signed · proposed 2027-06261 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    May 19, 2025[1]
  5. First operational
    Dec 15, 2026[1]
    Projected
  6. Expected completion
    Oct 1, 2027[1]
    Projected
Planned capacity
1.29 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-10-01); not necessarily full build-out.

Buildings (planned)
6[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1under construction133 MWDec 15, 2026 (projected)[1]
Building 2under construction133 MWFeb 15, 2027 (projected)[1]
Buildings 3–6under construction1.03 GWOct 1, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B300, Rubin[1]Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: May 19, 2025[1]
First operational: Dec 15, 2026[1]
  1. May 19, 2025[1]

    Land clearing begins

  2. Oct 16, 2025[1]

    Building 1 and 2 under construction.

  3. Dec 23, 2025[1]

    Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.

  4. Apr 16, 2026[1]

    Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.

  5. Dec 15, 2026Projected133 MW facility power· 1 buildings operational[1]

    Building 1 operational. This regulatory document lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not be met. From the timeline seen at the Abilene, Texas site for the same building styles we estimate operability to occur 8 months after the state seen in April 2026.

  6. Feb 15, 2027Projected265 MW facility power· 2 buildings operational[1]

    Building 2 operational. The completion date for Building 2 Tenant Improvement is 2026-11-07, about 2 months later than Building 1. We therefore add 2 months to the Building 1 operational date.

  7. Oct 1, 2027Projected1.29 GW facility power· 6 buildings operational[1]

    6 buildings are operational. This is based on: 1. A regulatory filing for Building 6 with a completion date of 2027-07-30. Normally there is a follow-up filing for "tenant improvement" which involves building the interior, with a completion date 1-3 months after the initial filing. 2. A project deadline of EOY 2027 in the original tax abatement agreement 3. The similar 8-building project in Abilene taking an estimated 2 years and 2 months.

All claims (provenance audit)

30
FieldValueSourceConfidenceAs ofStatus
NameGoodnight[1] Likely2026-04-16Shown
StatusUnder construction[1] derivedLikely2025-05-19Superseded / alternative
StatusUnder construction[1] derivedLikely2025-10-16Superseded / alternative
StatusUnder construction[1] derivedLikely2025-12-23Superseded / alternative
StatusUnder construction[1] derivedLikely2026-04-16Shown
Facility typeAI campus[1] derivedLikely2026-04-16Shown
Address10001 Lima Rd, Claude, TX 79019[1] Likely2026-04-16Shown
OwnerGoogleOwner: Google[1] Speculative2026-04-16Shown
End usersGoogle DeepMindUsers: Google DeepMind[1] Speculative2026-04-16Shown
UtilitySouthwestern Public Service COterritory 17718: SOUTHWESTERN PUBLIC SERVICE CO (INVESTOR OWNED, XCEL ENERGY INC[2] derivedUnverified2022Shown
Energy partnersSerenaEnergy companies: Serena[1] Confirmed2026-04-16Shown
ConstructionCrusoeConstruction companies: Crusoe[1] Confirmed2026-04-16Shown
ConstructionHoffman ConstructionConstruction companies: Hoffman[1] Confirmed2026-04-16Shown
Planned capacity1.29 GW[1] estimatedLikely2026-04-16Shown
ISO / RTOSPPSOUTHWEST POWER POOL | ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[3] derivedLikely—Shown
Balancing authoritySWPP[2] derivedLikely—Shown
Generation queued in county3.25 GW[4] derivedConfirmed2026-09-01Shown
State avg. industrial price7.07¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km2.11 GW[6] derivedConfirmed202502Shown
Buildings (planned)6[1] derivedLikely2026-04-16Shown
Buildings operational0[1] estimatedLikely2026-04-16Shown
Buildings operational0[1] estimatedLikely2025-05-19Superseded / alternative
Buildings operational0[1] estimatedLikely2025-10-16Superseded / alternative
Buildings operational0[1] estimatedLikely2025-12-23Superseded / alternative
Chip typesB300[1] Confirmed2026-04-16Shown
Chip typesRubin[1] Confirmed2026-04-16Shown
Construction startMay 19, 2025[1] derivedLikely2026-04-16Shown
First operationalDec 15, 2026[1] estimatedSpeculative2026-04-16Shown
Expected completionOct 1, 2027[1] estimatedSpeculative2026-04-16Shown