Google Cedar Rapids

Under constructionAI campusCampusLinn County, Iowa
60% profile completeness
25 claims from 8 sources
Current facility power
Not yet sourced
Planned capacity
314 MW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Dec 31, 2026[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H2 2027
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
MidAmerican Energy · MISO
Substation: On-site substation

Power reality

Announced
314 MW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
314 MW[1]
Building 1, Building 2, Building 3 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2024-06-14 (2.3 years).
  • Stated date: Next projected milestone: 2026-12-31 (modeled/speculative)[1]
  • Required: 314 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2027

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionJun 14, 2024
    Model estimate · Satellite imagery
    • Jun 14, 2024 · Reported status: under construction[1]
    • Jun 14, 2024 · Construction start[1]
    • Jun 14, 2024 · Land clearing begins.[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Google Cedar Rapids
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    3 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    MidAmerican Energy[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    MISO[3]
    Service territoryLikely
    Balancing authority: MISO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
41.91716, -91.72105
Address
5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404[1]Likely
County
Linn County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Google[1]Confirmed
End user
Utility

Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Interstate Power and Light CO, Linn County REC.

Power (all fields)

Planned capacity
314 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-05-23); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
MISO[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
MISO[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
9.99¢/kWh[5]Confirmed

Iowa statewide average, July 2026.

State avg. commercial price
13.27¢/kWh[5]Confirmed

Iowa statewide average, July 2026.

Generation within 50 km
1.11 GW[6]Confirmedderived

22 EIA-reported plants within 50 km.

Generation queued in county
2.61 GW[4]Confirmedderived

12 active generation interconnection requests in Linn County: Nuclear 1,261 MW, Solar 660 MW, Storage 595 MW, Gas 95 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Archer Daniels Midland Cedar Rapids · Archer Daniels Midland CoPower plant (Coal)2.8 km295 MW[6]
Prairie Creek · Interstate Power and Light CoPower plant (Natural Gas)7.4 km156 MW[6]
Amana Society Service Company · Amana Society Service CoPower plant (Petroleum)19.7 km22 MW[6]
Pleasant Creek Unit 2 · Interstate Power and Light CoPower plant (Solar)21.4 km150 MW[6]
Pleasant Creek Unit 1 · Interstate Power and Light CoPower plant (Solar)21.4 km50 MW[6]
Coralville Gt · MidAmerican Energy CoPower plant (Natural Gas)30.2 km63 MW[6]
University of Iowa Main Power Plant · University of IowaPower plant (Natural Gas)32.6 km41 MW[6]
Diamond Trail Wind Farm · MidAmerican Energy CoPower plant (Wind)45.6 km250 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
J3932 at Duane Arnold 161 kVMISO J3932NuclearIn study · proposed 2029-06646 MW[4]
J2268 at Duane ArnoldMISO J2268SolarIn study · proposed 2024-10400 MW[4]
J2469 at Sub K (Tiffin)-Duane Arnold 345kVMISO J2469StorageIn study · proposed 2027-10300 MW[4]
R5071 at Duane Arnold (ARNOLD 5)MISO R5071NuclearIn study251 MW[4]
J1444 at Duane Arnold 345kV SubstationMISO J1444SolarIA signed · proposed 2015-08200 MW[4]
R5069 at Duane Arnold (ARNOLD 5)MISO R5069NuclearIn study200 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Jun 14, 2024[1]
  5. First operational
    Dec 31, 2026[1]
    Projected
  6. Expected completion
    May 23, 2027[1]
    Projected
Planned capacity
314 MW[1]Likelyestimated

Projected facility power at the last tracked milestone (2027-05-23); not necessarily full build-out.

Buildings (planned)
4[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1under construction105 MWDec 31, 2026 (projected)[1]
Building 2under construction104 MWFeb 22, 2027 (projected)[1]
Building 3under construction105 MWMay 23, 2027 (projected)[1]
Building 4planned—Outlines traced on imagery; no completion date projected yet[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Jun 14, 2024[1]
First operational: Dec 31, 2026[1]
  1. Jun 14, 2024[1]

    Land clearing begins.

  2. Oct 27, 2025[1]

    Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.

  3. Dec 29, 2025[1]

    About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.

  4. Apr 16, 2026[1]

    Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.

  5. Dec 31, 2026Projected105 MW facility power· 1 buildings operational[1]

    Building 1 is operational. There is still work to be done since April, and Q4 2026 operational estimate was based on visible progress then.

  6. Feb 22, 2027Projected209 MW facility power· 2 buildings operational[1]

    Building 2 is operational. Based on Google Omaha Building 3 taking about 14 months from starting the roof to operation.

  7. May 23, 2027Projected314 MW facility power· 3 buildings operational[1]

    Building 3 is operational. Earlier satellite images suggest it was about 3 months behind Building 2.

All claims (provenance audit)

25
FieldValueSourceConfidenceAs ofStatus
NameGoogle Cedar Rapids[1] Likely2026-04-16Shown
StatusUnder construction[1] derivedLikely2024-06-14Superseded / alternative
StatusUnder construction[1] derivedLikely2025-10-27Superseded / alternative
StatusUnder construction[1] derivedLikely2025-12-29Superseded / alternative
StatusUnder construction[1] derivedLikely2026-04-16Shown
Facility typeAI campus[1] derivedLikely2026-04-16Shown
Address5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404[1] Likely2026-04-16Shown
OwnerGoogleOwner: Google[1] Confirmed2026-04-16Shown
End usersGoogle DeepMindUsers: Google DeepMind[1] Speculative2026-04-16Shown
UtilityMidAmerican Energyterritory 12341: MIDAMERICAN ENERGY CO (INVESTOR OWNED, BERKSHIRE HATHAWAY ENERG[2] derivedUnverified2022Shown
Planned capacity314 MW[1] estimatedLikely2026-04-16Shown
ISO / RTOMISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC..[3] derivedLikely—Shown
Balancing authorityMISO[2] derivedLikely—Shown
Generation queued in county2.61 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price9.99¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price13.27¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km1.11 GW[6] derivedConfirmed202502Shown
Buildings (planned)4[1] derivedLikely2026-04-16Shown
Buildings operational0[1] estimatedLikely2026-04-16Shown
Buildings operational0[1] estimatedLikely2024-06-14Superseded / alternative
Buildings operational0[1] estimatedLikely2025-10-27Superseded / alternative
Buildings operational0[1] estimatedLikely2025-12-29Superseded / alternative
Construction startJun 14, 2024[1] derivedLikely2026-04-16Shown
First operationalDec 31, 2026[1] estimatedSpeculative2026-04-16Shown
Expected completionMay 23, 2027[1] estimatedSpeculative2026-04-16Shown