Google Cedar Rapids
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Cedar Rapids
- →substationOn-site substation[1]Satellite imageryLikely3 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.91716, -91.72105
- Address
- County
- Linn County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- End user
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Interstate Power and Light CO, Linn County REC.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-05-23); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Iowa statewide average, July 2026.
- State avg. commercial price
Iowa statewide average, July 2026.
- Generation within 50 km
22 EIA-reported plants within 50 km.
- Generation queued in county
12 active generation interconnection requests in Linn County: Nuclear 1,261 MW, Solar 660 MW, Storage 595 MW, Gas 95 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Archer Daniels Midland Cedar Rapids · Archer Daniels Midland Co | Power plant (Coal) | 2.8 km | 295 MW | [6] |
| Prairie Creek · Interstate Power and Light Co | Power plant (Natural Gas) | 7.4 km | 156 MW | [6] |
| Amana Society Service Company · Amana Society Service Co | Power plant (Petroleum) | 19.7 km | 22 MW | [6] |
| Pleasant Creek Unit 2 · Interstate Power and Light Co | Power plant (Solar) | 21.4 km | 150 MW | [6] |
| Pleasant Creek Unit 1 · Interstate Power and Light Co | Power plant (Solar) | 21.4 km | 50 MW | [6] |
| Coralville Gt · MidAmerican Energy Co | Power plant (Natural Gas) | 30.2 km | 63 MW | [6] |
| University of Iowa Main Power Plant · University of Iowa | Power plant (Natural Gas) | 32.6 km | 41 MW | [6] |
| Diamond Trail Wind Farm · MidAmerican Energy Co | Power plant (Wind) | 45.6 km | 250 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J3932 at Duane Arnold 161 kVMISO J3932 | Nuclear | In study · proposed 2029-06 | 646 MW | [4] |
| J2268 at Duane ArnoldMISO J2268 | Solar | In study · proposed 2024-10 | 400 MW | [4] |
| J2469 at Sub K (Tiffin)-Duane Arnold 345kVMISO J2469 | Storage | In study · proposed 2027-10 | 300 MW | [4] |
| R5071 at Duane Arnold (ARNOLD 5)MISO R5071 | Nuclear | In study | 251 MW | [4] |
| J1444 at Duane Arnold 345kV SubstationMISO J1444 | Solar | IA signed · proposed 2015-08 | 200 MW | [4] |
| R5069 at Duane Arnold (ARNOLD 5)MISO R5069 | Nuclear | In study | 200 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJun 14, 2024[1]
- First operationalDec 31, 2026[1]Projected
- Expected completionMay 23, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-05-23); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 105 MW | Dec 31, 2026 (projected) | [1] |
| Building 2 | under construction | 104 MW | Feb 22, 2027 (projected) | [1] |
| Building 3 | under construction | 105 MW | May 23, 2027 (projected) | [1] |
| Building 4 | planned | — | Outlines traced on imagery; no completion date projected yet | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Jun 14, 2024[1]
Land clearing begins.
- Oct 27, 2025[1]
Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.
- Dec 29, 2025[1]
About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.
- Apr 16, 2026[1]
Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.
Building 1 is operational. There is still work to be done since April, and Q4 2026 operational estimate was based on visible progress then.
Building 2 is operational. Based on Google Omaha Building 3 taking about 14 months from starting the roof to operation.
Building 3 is operational. Earlier satellite images suggest it was about 3 months behind Building 2.
All claims (provenance audit)
25| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Cedar Rapids | [1] | Likely | 2026-04-16 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-06-14 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-10-27 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-12-29 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-04-16 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-04-16 | Shown |
| Address | 5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404 | [1] | Likely | 2026-04-16 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-04-16 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-04-16 | Shown |
| Utility | MidAmerican Energyterritory 12341: MIDAMERICAN ENERGY CO (INVESTOR OWNED, BERKSHIRE HATHAWAY ENERG | [2] derived | Unverified | 2022 | Shown |
| Planned capacity | 314 MW | [1] estimated | Likely | 2026-04-16 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [3] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Generation queued in county | 2.61 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.99¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.27¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.11 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 4 | [1] derived | Likely | 2026-04-16 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-04-16 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-06-14 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-27 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-12-29 | Superseded / alternative |
| Construction start | Jun 14, 2024 | [1] derived | Likely | 2026-04-16 | Shown |
| First operational | Dec 31, 2026 | [1] estimated | Speculative | 2026-04-16 | Shown |
| Expected completion | May 23, 2027 | [1] estimated | Speculative | 2026-04-16 | Shown |