Google Fort Wayne
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Fort Wayne
- →substationOn-site substation[1]Satellite imageryLikely3 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityIndiana Michigan Power (AEP)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.03182, -85.04732
- Address
- County
- Allen County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- End user
- Utility
Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heartland Remc, Paulding-Putman Elec Coop, INC, Noble County R E M C.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2028-06-23); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Indiana statewide average, July 2026.
- State avg. commercial price
Indiana statewide average, July 2026.
- Generation within 50 km
14 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Allen County: Solar 1,060 MW, Storage 300 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Paulding Wind Farm II · Paulding Wind Farm II LLC | Power plant (Wind) | 22.5 km | 99 MW | [6] |
| Timber Road IV · Paulding Wind Farm IV LLC | Power plant (Wind) | 26.7 km | 125 MW | [6] |
| Paulding Wind Farm III · Paulding Wind Farm III LLC | Power plant (Wind) | 26.7 km | 101 MW | [6] |
| Timber Road Solar Park · Timber Road Solar Park | Power plant (Solar) | 27.8 km | 50 MW | [6] |
| Robert P Mone Plant · Buckeye Power, Inc | Power plant (Natural Gas) | 28.2 km | 441 MW | [6] |
| Auburn Renewables LLC · Auburn Renewables, LLC | Power plant (Solar) | 34.8 km | 11 MW | [6] |
| Northwest Ohio Wind · Northwest Ohio Wind, LLC | Power plant (Wind) | 38.1 km | 105 MW | [6] |
| Blue Creek Wind Project · Avangrid Power LLC | Power plant (Wind) | 42.3 km | 302 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Allen - RP Mone 345 kVPJM AH1-549 | Solar | In study · proposed 2025-12 | 180 MW | [4] |
| Allen - RP Mone 345 kVPJM AI2-426 | Solar | In study · proposed 2027-12 | 180 MW | [4] |
| Flatrock Creek Solar IPJM AF2-224 | Solar | In study · proposed 2022-09 | 100 MW | [4] |
| Flatrock Creek Solar IIPJM AG1-365 | Solar | In study · proposed 2024-10 | 100 MW | [4] |
| Tillman 138 kVPJM AG1-368 | Solar | In study · proposed 2024-10 | 100 MW | [4] |
| Allen 345 kVPJM AG2-400 | Solar | In study · proposed 2025-10 | 100 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startApr 1, 2024[1]
- First operationalDec 1, 2026[1]Projected
- Expected completionJun 23, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-06-23); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | under construction | 207 MW | Dec 1, 2026 (projected) | [1] |
| Building 2 | under construction | 207 MW | Mar 31, 2027 (projected) | [1] |
| Building 3 | under construction | 207 MW | Aug 28, 2027 (projected) | [1] |
| Building 4 | under construction | 207 MW | Jan 25, 2028 (projected) | [1] |
| Building 5 | under construction | 207 MW | Jun 23, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Apr 1, 2024[1]
First signs of development/land clearing
- Sep 13, 2024[1]
Roof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.
- Jun 10, 2025[1]
After a long quiet period they've laid foundations for Building 2 and the substation.
- Oct 1, 2025[1]
Building 2 looks externally complete
- Mar 1, 2026[1]
The cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.
- Aug 19, 2026[1]
Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.
Estimated operational date of Building 2.
Estimated operational date of Building 3. Based on Building 3 construction looking about 4 months behind Building 2.
Estimated operational date of Building 4. Based on Building 4 construction looking about 10 months behind Building 2.
Estimated operational date of Building 5. Based on previous buildings being separated by about 5 months.
Estimated operational date of Building 6. Based on previous buildings being separated by about 5 months.
All claims (provenance audit)
30| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Fort Wayne | [1] | Likely | 2026-08-19 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-04-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2024-09-13 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-06-10 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-08-19 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-08-19 | Shown |
| Address | 6015 Adams Center Road, Fort Wayne, IN 46806 | [1] | Likely | 2026-08-19 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-08-19 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-08-19 | Shown |
| Utility | Indiana Michigan Power (AEP)territory 9324: INDIANA MICHIGAN POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POW | [2] derived | Unverified | 2022 | Shown |
| Investors | GoogleInvestors: Google | [1] | Confirmed | 2026-08-19 | Shown |
| Planned capacity | 1.04 GW | [1] estimated | Likely | 2026-08-19 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Generation queued in county | 1.36 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.16¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.30¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.26 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-08-19 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-08-19 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2024-09-13 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-06-10 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-01 | Superseded / alternative |
| Construction start | Apr 1, 2024 | [1] derived | Likely | 2026-08-19 | Shown |
| First operational | Dec 1, 2026 | [1] estimated | Speculative | 2026-08-19 | Shown |
| Expected completion | Jun 23, 2028 | [1] estimated | Speculative | 2026-08-19 | Shown |