DC
/

Google Fort Wayne

Under constructionAI campusCampusFort Wayne, Allen County, Indiana
60% profile completeness
30 claims from 10 sources
Current facility power
Not yet sourced
Planned capacity
1.04 GW[1]
Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
Not yet sourced
First operational
Dec 1, 2026[1]
Speculativeestimated

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H2 2027
Medium confidencewindow, not a prediction
Project verification
Under construction
Construction documented by satellite imagery.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
Indiana Michigan Power (AEP) · PJM
Substation: On-site substation

Power reality

Announced
1.04 GW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
1.04 GW[1]
Building 1, Building 2, Building 3, Building 4, Building 5 under construction (satellite-tracked phases)
Operational
No record
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Construction elapsed: Construction documented since 2024-04-01 (2.5 years).
  • Stated date: Next projected milestone: 2026-12-01 (modeled/speculative)[1]
  • Required: 1.04 GW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • Construction to first power typically takes 1.25–2.5 years.
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2027

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 1, 2024
    Model estimate · Satellite imagery
    • Apr 1, 2024 · Reported status: under construction[1]
    • Apr 1, 2024 · Construction start[1]
    • Apr 1, 2024 · First signs of development/land clearing[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Google Fort Wayne
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    3 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Indiana Michigan Power (AEP)[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[3]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
41.03182, -85.04732
Address
6015 Adams Center Road, Fort Wayne, IN 46806[1]Likely
County
Allen County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Capital & construction
Investor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Google[1]Confirmed
End user
Utility

Most likely retail provider among 4 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heartland Remc, Paulding-Putman Elec Coop, INC, Noble County R E M C.

Investor
Google[1]Confirmed

Power (all fields)

Planned capacity
1.04 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-06-23); not necessarily full build-out.

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Likelyderived

Control area of the containing utility territory.

State avg. industrial price
9.16¢/kWh[5]Confirmed

Indiana statewide average, July 2026.

State avg. commercial price
13.30¢/kWh[5]Confirmed

Indiana statewide average, July 2026.

Generation within 50 km
1.26 GW[6]Confirmedderived

14 EIA-reported plants within 50 km.

Generation queued in county
1.36 GW[4]Confirmedderived

14 active generation interconnection requests in Allen County: Solar 1,060 MW, Storage 300 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Paulding Wind Farm II · Paulding Wind Farm II LLCPower plant (Wind)22.5 km99 MW[6]
Timber Road IV · Paulding Wind Farm IV LLCPower plant (Wind)26.7 km125 MW[6]
Paulding Wind Farm III · Paulding Wind Farm III LLCPower plant (Wind)26.7 km101 MW[6]
Timber Road Solar Park · Timber Road Solar ParkPower plant (Solar)27.8 km50 MW[6]
Robert P Mone Plant · Buckeye Power, IncPower plant (Natural Gas)28.2 km441 MW[6]
Auburn Renewables LLC · Auburn Renewables, LLCPower plant (Solar)34.8 km11 MW[6]
Northwest Ohio Wind · Northwest Ohio Wind, LLCPower plant (Wind)38.1 km105 MW[6]
Blue Creek Wind Project · Avangrid Power LLCPower plant (Wind)42.3 km302 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
Allen - RP Mone 345 kVPJM AH1-549SolarIn study · proposed 2025-12180 MW[4]
Allen - RP Mone 345 kVPJM AI2-426SolarIn study · proposed 2027-12180 MW[4]
Flatrock Creek Solar IPJM AF2-224SolarIn study · proposed 2022-09100 MW[4]
Flatrock Creek Solar IIPJM AG1-365SolarIn study · proposed 2024-10100 MW[4]
Tillman 138 kVPJM AG1-368SolarIn study · proposed 2024-10100 MW[4]
Allen 345 kVPJM AG2-400SolarIn study · proposed 2025-10100 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Apr 1, 2024[1]
  5. First operational
    Dec 1, 2026[1]
    Projected
  6. Expected completion
    Jun 23, 2028[1]
    Projected
Planned capacity
1.04 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-06-23); not necessarily full build-out.

Buildings (planned)
3[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
0[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1under construction207 MWDec 1, 2026 (projected)[1]
Building 2under construction207 MWMar 31, 2027 (projected)[1]
Building 3under construction207 MWAug 28, 2027 (projected)[1]
Building 4under construction207 MWJan 25, 2028 (projected)[1]
Building 5under construction207 MWJun 23, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

Construction start: Apr 1, 2024[1]
First operational: Dec 1, 2026[1]
  1. Apr 1, 2024[1]

    First signs of development/land clearing

  2. Sep 13, 2024[1]

    Roof complete on Building 1 (the 'H'), although we suspect this building is not for AI compute due to the construction speed, irregular design, and lack of external cooling.

  3. Jun 10, 2025[1]

    After a long quiet period they've laid foundations for Building 2 and the substation.

  4. Oct 1, 2025[1]

    Building 2 looks externally complete

  5. Mar 1, 2026[1]

    The cooling towers for Buildings 2 and 3 are both a little less than half done and the buildings still look like active construction sites.

  6. Aug 19, 2026[1]

    Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.

  7. Dec 1, 2026Projected207 MW facility power· 1 buildings operational[1]

    Estimated operational date of Building 2.

  8. Mar 31, 2027Projected414 MW facility power· 2 buildings operational[1]

    Estimated operational date of Building 3. Based on Building 3 construction looking about 4 months behind Building 2.

  9. Aug 28, 2027Projected621 MW facility power· 3 buildings operational[1]

    Estimated operational date of Building 4. Based on Building 4 construction looking about 10 months behind Building 2.

  10. Jan 25, 2028Projected828 MW facility power· 4 buildings operational[1]

    Estimated operational date of Building 5. Based on previous buildings being separated by about 5 months.

  11. Jun 23, 2028Projected1.04 GW facility power· 5 buildings operational[1]

    Estimated operational date of Building 6. Based on previous buildings being separated by about 5 months.

All claims (provenance audit)

30
FieldValueSourceConfidenceAs ofStatus
NameGoogle Fort Wayne[1] Likely2026-08-19Shown
StatusUnder construction[1] derivedLikely2024-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2024-09-13Superseded / alternative
StatusUnder construction[1] derivedLikely2025-06-10Superseded / alternative
StatusUnder construction[1] derivedLikely2025-10-01Superseded / alternative
StatusUnder construction[1] derivedLikely2026-03-01Superseded / alternative
StatusUnder construction[1] derivedLikely2026-08-19Shown
Facility typeAI campus[1] derivedLikely2026-08-19Shown
Address6015 Adams Center Road, Fort Wayne, IN 46806[1] Likely2026-08-19Shown
OwnerGoogleOwner: Google[1] Confirmed2026-08-19Shown
End usersGoogle DeepMindUsers: Google DeepMind[1] Speculative2026-08-19Shown
UtilityIndiana Michigan Power (AEP)territory 9324: INDIANA MICHIGAN POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POW[2] derivedUnverified2022Shown
InvestorsGoogleInvestors: Google[1] Confirmed2026-08-19Shown
Planned capacity1.04 GW[1] estimatedLikely2026-08-19Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[3] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Generation queued in county1.36 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price9.16¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price13.30¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km1.26 GW[6] derivedConfirmed202502Shown
Buildings (planned)3[1] derivedLikely2026-08-19Shown
Buildings operational0[1] estimatedLikely2026-08-19Shown
Buildings operational0[1] estimatedLikely2024-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2024-09-13Superseded / alternative
Buildings operational0[1] estimatedLikely2025-06-10Superseded / alternative
Buildings operational0[1] estimatedLikely2025-10-01Superseded / alternative
Buildings operational0[1] estimatedLikely2026-03-01Superseded / alternative
Construction startApr 1, 2024[1] derivedLikely2026-08-19Shown
First operationalDec 1, 2026[1] estimatedSpeculative2026-08-19Shown
Expected completionJun 23, 2028[1] estimatedSpeculative2026-08-19Shown