Google Pryor (North)
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationSep 6, 2026
Satellite imagery
- Sep 6, 2026 · Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.[1]
- OperationalSep 6, 2026
Satellite imagery
- Sep 6, 2026 · Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Pryor (North)
- →substationOn-site substation[1]Satellite imageryLikely3 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityPublic Service CO of Oklahoma[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 36.24564, -95.32436
- Address
- County
- Mayes County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- End user
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Grand River Dam Authority, Northeast Oklahoma Electric CO.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
442 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Oklahoma statewide average, July 2026.
- State avg. commercial price
Oklahoma statewide average, July 2026.
- Generation within 50 km
8 EIA-reported plants within 50 km.
- Generation queued in county
7 active generation interconnection requests in Mayes County: Solar + storage 500 MW, Storage 374 MW, Solar 350 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Chouteau · Associated Electric Coop, Inc | Power plant (Natural Gas) | 5 km | 888 MW | [7] |
| Grec · Grand River Dam Authority | Power plant (Natural Gas) | 6.9 km | 960 MW | [7] |
| Markham · Grand River Dam Authority | Power plant (Hydroelectric) | 12.8 km | 126 MW | [7] |
| Salina · Grand River Dam Authority | Power plant (Pumped Storage) | 19.9 km | 242 MW | [7] |
| Pensacola · Grand River Dam Authority | Power plant (Hydroelectric) | 35.4 km | 115 MW | [7] |
| Northeastern · Public Service Co of Oklahoma | Power plant (Natural Gas) | 39.6 km | 1.34 GW | [7] |
| Oneta Energy Center · Oneta Power LLC | Power plant (Natural Gas) | 42.4 km | 1.09 GW | [7] |
| Fort Gibson · USCE-Tulsa District | Power plant (Hydroelectric) | 42.8 km | 51 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| GEN-2024-294 at Tulsa North - Igloo Valley 345 kV lineSPP GEN-2024-294 | Solar + storage | In study · proposed 2030-12 | 500 MW | [5] |
| GEN-2021-047 at Tulsa (Bus #509852) - Igloo (Bus #513596) 345kV lineSPP GEN-2021-047 | Solar | IA signed · proposed 2028-12 | 250 MW | [5] |
| GEN-2023-SR27 at GRDA1 to CLARMR 5 161kV lineSPP GEN-2023-SR27 | Storage | IA signed · proposed 2028-06 | 102 MW | [5] |
| GEN-2023-055 at Kerr Grove 161 kVSPP GEN-2023-055 | Storage | IA signed · proposed 2029-06 | 100 MW | [5] |
| GEN-2020-092 at Pryor Junction - Midwest Carbide 138kV line SPP GEN-2020-092 | Solar | IA signed · proposed 2028-11 | 100 MW | [5] |
| GEN-2019-002 at Maid 161kV substationSPP GEN-2019-002 | Storage | IA signed · proposed 2027-11 | 100 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
Building 1 is operational, based on default roof-to-operational time.
Building 2 is being retrofitted from a warehouse. The roof is being painted white, and cooling towers and a new substation are being built just south of the building (based on later imagery).
The new substation for Building 2 looks mostly complete, half of the cooling towers are installed. The black patch in the top left of the building suggests that the new roof is not quite complete.
Building 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.
Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.
All claims (provenance audit)
40| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Pryor (North) | [1] | Likely | 2026-09-06 | Shown |
| Status | Operating + expanding | [1] derived | Likely | 2024-07-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-01-28 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-26 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-09-06 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-09-06 | Shown |
| Address | 4581 Webb St, Pryor, OK 74361 | [1] | Likely | 2026-09-06 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-09-06 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-09-06 | Shown |
| Utility | Public Service CO of Oklahomaterritory 15474: PUBLIC SERVICE CO OF OKLAHOMA (INVESTOR OWNED, AMERICAN ELECTRI | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 442 MW | [1] estimated | Likely | 2026-09-06 | Shown |
| Current facility power | 63 MW | [1] estimated | Likely | 2024-07-19 | Superseded / alternative |
| Current facility power | 63 MW | [1] estimated | Likely | 2025-01-28 | Superseded / alternative |
| Current facility power | 63 MW | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Current facility power | 63 MW | [1] estimated | Likely | 2026-05-26 | Superseded / alternative |
| Current IT capacity | 368 MW | [1] estimated | Likely | 2026-09-06 | Shown |
| Current IT capacity | 53 MW | [1] estimated | Likely | 2024-07-19 | Superseded / alternative |
| Current IT capacity | 53 MW | [1] estimated | Likely | 2025-01-28 | Superseded / alternative |
| Current IT capacity | 53 MW | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Current IT capacity | 53 MW | [1] estimated | Likely | 2026-05-26 | Superseded / alternative |
| Estimated annual consumption | 2,710 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | SPPSOUTHWEST POWER POOL | [4] derived | Likely | — | Shown |
| Balancing authority | SWPP | [2] derived | Likely | — | Shown |
| Generation queued in county | 1.22 GW | [5] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 8.16¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.32¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.81 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-09-06 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-09-06 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2024-07-19 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-01-28 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-26 | Superseded / alternative |
| Capital cost / investment | $13.9B | [1] estimated | Likely | 2026-09-06 | Shown |
| Compute (H100-equivalents) | 636,700 | [1] estimated | Likely | 2026-09-06 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-09-06 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-09-06 | Shown |
| Construction start | Jul 19, 2024 | [1] derived | Likely | 2026-09-06 | Shown |
| First operational | Jul 19, 2024 | [1] derived | Likely | 2026-09-06 | Shown |