Google Storey County
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionAug 30, 2023
Model estimate · Satellite imagery
- EnergizationJun 30, 2025
Satellite imagery
- Jun 30, 2025 · Building 2 is operational. Based on a [Google Earth image](https://earth.google.com/web/@39.49733738,-119.43113543,1552.05877612a,1467.7067385d,35y,0h,0t,0r/) showing complete buil[1]
- OperationalJun 30, 2025
Satellite imagery
- Jun 30, 2025 · Building 2 is operational. Based on a [Google Earth image](https://earth.google.com/web/@39.49733738,-119.43113543,1552.05877612a,1467.7067385d,35y,0h,0t,0r/) showing complete buil[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Storey County
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmission120 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.54 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 39.49558, -119.43176
- County
- Storey County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.
- Estimated annual consumption
214 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Nevada statewide average, July 2026.
- State avg. commercial price
Nevada statewide average, July 2026.
- Generation within 50 km
24 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 120 kV line | Transmission line | 0.54 km | 120 kV | [5] |
| Western 102 Power Plant · Nevada Gold Mines | Power plant (Natural Gas) | 9.9 km | 117 MW | [7] |
| Tracy · Sierra Pacific Power Co | Power plant (Natural Gas) | 10.9 km | 954 MW | [7] |
| Turquoise Nevada, LLC · Greenbacker Renewable Energy Corporation | Power plant (Solar) | 11.8 km | 60 MW | [7] |
| Richard Burdette Geothermal · Ormat Nevada Inc | Power plant (Geothermal) | 30.1 km | 20 MW | [7] |
| Steamboat Hills LP · Ormat Nevada Inc | Power plant (Geothermal) | 32 km | 27 MW | [7] |
| Patua Acquisition Project, LLC · Patua Acquisition Company, LLC | Power plant (Geothermal) | 32.4 km | 41 MW | [7] |
| Fort Churchill · Sierra Pacific Power Co | Power plant (Natural Gas) | 48.3 km | 226 MW | [7] |
| Brady · Ormat Nevada Inc | Power plant (Geothermal) | 49.2 km | 22 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startAug 30, 2023[1]
- First operationalAug 30, 2023[1]
- Expected completionJun 30, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-06-30); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed.
Building 2 now has generators in place, but there is still a crane and construction work present.
Building 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front.
Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped.
Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.
Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the number of generators reported in an air quality permit application (p.92-93). The dry cooler array is more than double the size of the Building 1 array, which suggests an even larger power capacity than we estimate, but we believe the generator-based estimate is more reliable here.
All claims (provenance audit)
43| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Storey County | [1] | Likely | 2026-04-13 | Shown |
| Status | Operating + expanding | [1] derived | Likely | 2023-08-30 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-11 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-06-30 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-28 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-04-13 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-04-13 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-04-13 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-04-13 | Shown |
| Utility | NV Energyterritory 17166: SIERRA PACIFIC POWER CO (INVESTOR OWNED, NEVADA ENERGY) | [2] derived | Likely | 2022 | Shown |
| Current facility power | 214 MW | [1] estimated | Likely | 2026-04-13 | Shown |
| Current facility power | 107 MW | [1] estimated | Likely | 2023-08-30 | Superseded / alternative |
| Current facility power | 107 MW | [1] estimated | Likely | 2025-03-11 | Superseded / alternative |
| Current facility power | 214 MW | [1] estimated | Likely | 2025-06-30 | Superseded / alternative |
| Current facility power | 214 MW | [1] estimated | Likely | 2025-09-28 | Superseded / alternative |
| Current IT capacity | 161 MW | [1] estimated | Likely | 2026-04-13 | Shown |
| Current IT capacity | 81 MW | [1] estimated | Likely | 2023-08-30 | Superseded / alternative |
| Current IT capacity | 81 MW | [1] estimated | Likely | 2025-03-11 | Superseded / alternative |
| Current IT capacity | 161 MW | [1] estimated | Likely | 2025-06-30 | Superseded / alternative |
| Current IT capacity | 161 MW | [1] estimated | Likely | 2025-09-28 | Superseded / alternative |
| Planned capacity | 389 MW | [1] estimated | Likely | 2026-04-13 | Shown |
| Estimated annual consumption | 1,312 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | NEVP | [2] derived | Likely | — | Shown |
| Highest-voltage line nearby | 120 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 10.04¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 9.72¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.61 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-04-13 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-04-13 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2023-08-30 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-03-11 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-06-30 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-09-28 | Superseded / alternative |
| Capital cost / investment | $6.1B | [1] estimated | Likely | 2026-04-13 | Shown |
| Compute (H100-equivalents) | 133,900 | [1] estimated | Likely | 2026-04-13 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-04-13 | Shown |
| Chip types | TPU v4 | [1] | Confirmed | 2026-04-13 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-04-13 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-04-13 | Shown |
| Construction start | Aug 30, 2023 | [1] derived | Likely | 2026-04-13 | Shown |
| First operational | Aug 30, 2023 | [1] derived | Likely | 2026-04-13 | Shown |
| Expected completion | Jun 30, 2027 | [1] estimated | Speculative | 2026-04-13 | Shown |