Greenidge Power Plant and Data Center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection applicationOct 22, 2018
ISO/RTO queue
- Oct 22, 2018 · NYISO load request 0776 (60 MW): Status 7 (FS pending); studies available: SIS; proposed initial backfeed: 04-2030[2]
- Dec 20, 2024 · NYISO load request 1725 (200 MW): Status 5 (SRIS/SIS in progress); proposed initial backfeed: 05-2028[2]
- Sep 27, 2026 · Load interconnection request: 60 MW[2]
- Sep 27, 2026 · Load interconnection request: 200 MW[2]
- Feasibility study
- System impact study
- Facilities study
ISO/RTO queue
- NYISO load request 0776 (60 MW): Status 7 (FS pending); studies available: SIS; proposed initial backfeed: 04-2030 (queue status as of 2026-09-27)[2]
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: ISO/RTO queue, Community map.
Grid path
- →facilityGreenidge Power Plant and Data Center
- →
- →transmission115 kV[2]Queue POILikelyVoltage at the requested point of interconnection (Greenidge 115kV)
- →utilityNew York State Elec & Gas Corp[3]Service territoryLikelyRetail service territory containing the site · Transmission owner (queue): NYSEG
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
NYISO 0776 Greenidge Load · Greenidge Generation LLC | This site's load request Likely Request name/customer shares “generation” with this facility, in the same county. | Facilities study Status 7 (FS pending); studies available: SIS; proposed initial backfeed: 04-2030 | 60 | — | Oct 22, 2018 | Apr 2030 | Greenidge 115kV TO: NYSEG | [2] Sep 27, 2026 |
NYISO 1725 Greenidge 200 MW Data Center Project · Greenidge Generation, LLC | This site's load request Likely Request name/customer shares “generation” with this facility, in the same county. | System impact study Status 5 (SRIS/SIS in progress); proposed initial backfeed: 05-2028 | 200 | — | Dec 20, 2024 | May 2028 | New York State Electric & Gas (NYSEG) - Greenidge 115 kV Substation TO: NYSEG | [2] Sep 27, 2026 |
On-site & dedicated generation
- Greenidge Generation LLC (Natural Gas, 105 MW) is 0.1 km away[6]EIA plant within 1.5 km; proximity does not establish that it supplies the facilityNatural gasCo-located105 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 42.67938, -76.94874
- County
- Yates County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
- Developer
Interconnection customer on the load request.
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Interconnection status
- Load interconnection request
NYISO load interconnection request 0776 (Data center (crypto mining)).
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
New York statewide average, July 2026.
- State avg. commercial price
New York statewide average, July 2026.
- Generation within 50 km
59 EIA-reported plants within 50 km.
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line | Transmission line | 0.19 km | 115 kV | [1] |
| Greenidge Generation LLC · Greenidge Generation Holdings LLC | Power plant (Natural Gas) | 0.1 km | 105 MW | [6] |
| Ontario Lfgte · Seneca Energy II | Power plant (Biomass) | 22.9 km | 11 MW | [6] |
| Seneca Energy · Seneca Energy II | Power plant (Biomass) | 29 km | 18 MW | [6] |
| Lansing Renewables, LLC · Lansing Renewables, LLC | Power plant (Solar) | 32.8 km | 8 MW | [6] |
| Newfield Community Solar LLC · Newfield Solar LLC | Power plant (Solar) | 44.9 km | 12 MW | [6] |
| Cornell University Central Heat · Cornell University | Power plant (Natural Gas) | 46.8 km | 33 MW | [6] |
| Dutch Hill Wind Project · Evergreen Wind, LLC | Power plant (Wind) | 47.2 km | 38 MW | [6] |
| Ellis Solar · Altus Power America Management, LLC | Power plant (Solar) | 49.6 km | 18 MW | [6] |
| Unnamed substation | Substation | 0.05 km | — | [1] |
| Unnamed substation | Substation | 0.19 km | 115 kV | [1] |
| Unnamed substation | Substation | 0.46 km | — | [1] |
| NYSEG substation · NYSEG | Substation | 0.63 km | — | [1] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)Timeline
All claims (provenance audit)
19| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Greenidge Power Plant and Data Centerway/253670255 name=Greenidge Power Plant and Data Center | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Operator | Greenidge Generation Holdings Inc.operator=Greenidge Generation Holdings Inc. | [1] | Likely | 2026-09-27 | Shown |
| Developer | Greenidge Generation LLC | [2] | Likely | 2026-09-27 | Shown |
| Developer | Greenidge Generation LLC | [2] | Likely | 2026-09-27 | Shown |
| Utility | New York State Elec & Gas Corpterritory 13511: NEW YORK STATE ELEC & GAS CORP (INVESTOR OWNED, IBERDROLA USA I | [3] derived | Likely | 2022 | Shown |
| ISO / RTO | NYISONEW YORK INDEPENDENT SYSTEM OPERATOR | [4] derived | Likely | — | Shown |
| Balancing authority | NYIS | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substationway/1485150951 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.1 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 115 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Interconnection status | NYISO load request 0776: 60 MW, in study at Greenidge 115kVStatus 7 (FS pending); studies available: SIS; proposed initial backfeed: 04-203 | [2] | Confirmed | 2026-09-27 | Shown |
| Interconnection status | NYISO load request 1725: 200 MW, in study at New York State Electric & Gas (NYSEG) - Greenidge 115 kV SubstationStatus 5 (SRIS/SIS in progress); proposed initial backfeed: 05-2028 · requested | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| Load interconnection request | 60 MW | [2] | Confirmed | 2026-09-27 | Shown |
| Load interconnection request | 200 MW | [2] | Confirmed | 2026-09-27 | Superseded / alternative |
| State avg. industrial price | 10.81¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 24.18¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 419 MW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 95,900 sq ft | [1] derived | Likely | 2026-09-27 | Shown |