Hut 8 West Feliciana
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ Announced 1 GW is 3.0× the 330 MW documented by grid, construction or operating records.
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- Current stage: Interconnection agreement / service contract (furthest stage with documented evidence)[1]
- Required: 1 GW
- From “Interconnection agreement / service contract”, large loads have typically taken 0.75–2.5 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- AnnouncedSep 11, 2026
Utility filing / announcement
- Sep 11, 2026 · Planned capacity reported: 1000 MW[1]
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contractSep 11, 2026
Utility filing / announcement
- Sep 11, 2026 · Contracted / committed power: 330 MW[1]
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Utility filing / announcement.
Grid path
- →facilityHut 8 West Feliciana
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 30.88053, -91.41142
- County
- West Feliciana Parish
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
“Entergy Louisiana to provide 330 MW initially, with potential to expand to 1,000 MW.” — Potential expansion.
- Contracted / committed power
“Entergy Louisiana to provide 330 MW initially, with potential to expand to 1,000 MW.”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Contracted / committed power
“Entergy Louisiana to provide 330 MW initially, with potential to expand to 1,000 MW.”
- State avg. industrial price
Louisiana statewide average, July 2026.
- State avg. commercial price
Louisiana statewide average, July 2026.
- Generation within 50 km
13 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| River Bend · Entergy Louisiana LLC | Power plant (Nuclear) | 15.7 km | 976 MW | [5] |
| Big Cajun 2 · Louisiana Generating LLC | Power plant (Coal) | 17.6 km | 1.67 GW | [5] |
| Big Cajun 1 · Louisiana Generating LLC | Power plant (Natural Gas) | 23.6 km | 367 MW | [5] |
| Oxbow Solar 1 · Lightsource Renewable Energy Asset Management, LLC | Power plant (Solar) | 23.7 km | 300 MW | [5] |
| Sidney A Murray Jr Hydroelectric · First National Bank-Commerce | Power plant (Hydroelectric) | 30.4 km | 192 MW | [5] |
| Formosa Plastics · Formosa Plastics Corp | Power plant (Natural Gas) | 47.5 km | 82 MW | [5] |
| Louisiana 1 · Entergy Louisiana LLC | Power plant (Natural Gas) | 48.2 km | 382 MW | [5] |
| Louisiana 2 · Entergy Louisiana LLC | Power plant (Natural Gas) | 48.2 km | 138 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
- Planned capacity
“Entergy Louisiana to provide 330 MW initially, with potential to expand to 1,000 MW.” — Potential expansion.
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
9| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Developer | Hut 8 | [1] | Confirmed | 2026-09-11 | Shown |
| Utility | Entergy | [1] | Confirmed | 2026-09-11 | Shown |
| Planned capacity | 1 GW | [1] | Likely | 2026-09-11 | Shown |
| Contracted / committed power | 330 MW | [1] | Likely | 2026-09-11 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [2] derived | Likely | — | Shown |
| Balancing authority | MISO | [3] derived | Likely | — | Shown |
| State avg. industrial price | 6.08¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.97¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.26 GW | [5] derived | Confirmed | 202502 | Shown |