Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityLearning GIS!
- →substationPurdue University (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.56 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.57 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Street address- Coordinates
- 40.42179, -86.91415
- County
- Tippecanoe County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Tipmont Rural Elec Member Corp.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Indiana statewide average, July 2026.
- State avg. commercial price
Indiana statewide average, July 2026.
- Generation within 50 km
31 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Tippecanoe County: Wind 200 MW, Storage 100 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line · Duke Energy | Transmission line | 0.57 km | 138 kV | [1] |
| Meadow Lake Wind Farm LLC · Meadow Lake Wind Farm LLC | Power plant (Wind) | 22.9 km | 200 MW | [6] |
| Indiana Crossroads Wind Farm LLC · Indiana Crossroads Wind Farms LLC | Power plant (Wind) | 27.1 km | 302 MW | [6] |
| Indiana Crossroads Solar Park · Meadow Lake Solar Park | Power plant (Solar) | 34.3 km | 200 MW | [6] |
| Meadow Lake Wind Farm Vi LLC · Meadow Lake Wind Farm VI LLC | Power plant (Wind) | 35.1 km | 200 MW | [6] |
| Hardy Hills Solar Energy LLC · Hardy Hills Solar LLC | Power plant (Solar) | 36 km | 195 MW | [6] |
| Fowler Ridge Wind Farm LLC · AE Power Services LLC | Power plant (Wind) | 39.8 km | 588 MW | [6] |
| Indiana Crossroads Wind Farm II · Indiana Crossroads Wind Farm II LLC | Power plant (Wind) | 41.2 km | 200 MW | [6] |
| Jordan Creek Wind Farm, LLC · Jordan Creek Wind Farm, LLC | Power plant (Wind) | 41.4 km | 399 MW | [6] |
| Purdue University | Substation | 0.56 km | 138 kV | [1] |
| Purdue Northwest | Substation | 1.48 km | 138 kV | [1] |
| Unnamed substation | Substation | 1.63 km | 138 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J2509 at Westwood 345 kVMISO J2509 | Wind | In study · proposed 2025-10 | 200 MW | [4] |
| J2450 at WESTWOOD 345 KVMISO J2450 | Storage | In study · proposed 2026-10 | 100 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
12| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Learning GIS!node/7264976228 name=Learning GIS! | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Duke Energyterritory 15470: DUKE ENERGY INDIANA, LLC (INVESTOR OWNED, DUKE ENERGY CORP) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [3] derived | Likely | — | Shown |
| Balancing authority | MISO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Purdue University (138 kV)way/369597733 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.6 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 300 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.16¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.30¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.38 GW | [6] derived | Confirmed | 202502 | Shown |