Meta Bowling Green
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Bowling Green
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- 1 on-site power generator outline traced on satellite imagery[1]Epoch AI satellite annotations (fuel type and capacity not identified)Unknown typeBehind-the-meterLikely
Location & imagery
Mapped outline- Coordinates
- 41.46602, -83.64130
- Address
- County
- Wood County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
36 EIA-reported plants within 50 km.
- Generation queued in county
10 active generation interconnection requests in Wood County: Storage 950 MW, Solar 940 MW, Solar + storage 130 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Bowling Green Generating Station · American Mun Power-Ohio, Inc | Power plant (Natural Gas) | 7.6 km | 38 MW | [6] |
| Bowling Green Peaking · American Mun Power-Ohio, Inc | Power plant (Natural Gas) | 8.6 km | 29 MW | [6] |
| Troy Energy LLC · Troy Energy LLC | Power plant (Natural Gas) | 15.2 km | 707 MW | [6] |
| Oregon Clean Energy Center · Oregon Clean Energy Center | Power plant (Natural Gas) | 27.8 km | 849 MW | [6] |
| Firstenergy Bay Shore · Walleye Power, LLC | Power plant (Petroleum) | 30.3 km | 154 MW | [6] |
| Napoleon Peaking Station · American Mun Power-Ohio, Inc | Power plant (Natural Gas) | 39.6 km | 38 MW | [6] |
| Fremont Energy Center · American Mun Power-Ohio, Inc | Power plant (Natural Gas) | 41.2 km | 685 MW | [6] |
| Davis Besse · Energy Harbor Nuclear Generation LLC | Power plant (Nuclear) | 48.4 km | 894 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Lemoyne 345kVPJM AH1-565 | Storage | In study · proposed 2025-06 | 950 MW | [4] |
| Fostoria - Lemoyne 345 kVPJM AG2-470 | Solar | In study · proposed 2025-12 | 300 MW | [4] |
| Fostoria Central - Lemoyn 345 kVPJM AI2-164 | Solar | In study · proposed 2025-12 | 300 MW | [4] |
| Pemberville - West End Fostoria 69 kVPJM AH2-068 | Solar | In study · proposed 2027-12 | 100 MW | [4] |
| Fostoria - Lemoyne 138 kV IIPJM AH2-409 | Solar + storage | In study · proposed 2025-06 | 80 MW | [4] |
| Dowling 138 kV IIPJM AH1-122 | Solar | In study · proposed 2024-12 | 75 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startNov 1, 2024[1]
- First operationalFeb 1, 2027[1]Projected
- Expected completionJan 1, 2028[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Nov 1, 2024[1]
Land clearing begins.
- Feb 14, 2026[1]
Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowling Substation, an existing substation to the northeast of the data center, appear complete.
- Jul 30, 2026[1]
Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.
Building 1 is operational, based on a 5 month extrapolation from its roof completion date.
Building 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1.
Buildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project.
All claims (provenance audit)
26| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Bowling Green | [1] | Likely | 2026-07-30 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-11-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-14 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-07-30 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-30 | Shown |
| Address | 12356 Middleton Pike, Bowling Green, OH 43402 | [1] | Likely | 2026-07-30 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-07-30 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-07-30 | Shown |
| Utility | The Toledo Edison COterritory 18997: THE TOLEDO EDISON CO (INVESTOR OWNED, FIRSTENERGY CORP) | [2] derived | Likely | 2022 | Shown |
| Energy partners | WilliamsEnergy companies: Williams | [1] | Confirmed | 2026-07-30 | Shown |
| Planned capacity | 570 MW | [1] estimated | Likely | 2026-07-30 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Generation queued in county | 2.02 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.55 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 4 | [1] derived | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-07-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-11-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-14 | Superseded / alternative |
| Chip types | B300 | [1] | Confirmed | 2026-07-30 | Shown |
| Chip types | Rubin | [1] | Confirmed | 2026-07-30 | Shown |
| Construction start | Nov 1, 2024 | [1] derived | Likely | 2026-07-30 | Shown |
| First operational | Feb 1, 2027 | [1] estimated | Speculative | 2026-07-30 | Shown |
| Expected completion | Jan 1, 2028 | [1] estimated | Speculative | 2026-07-30 | Shown |