Meta Cheyenne
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Cheyenne
- →substationSatellite imageryLikely2 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.07 km away
- →transmissionCheyenne to 230=Terry Ranch Road & 115=Rockford[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.9 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.07935, -104.82283
- Address
- County
- Laramie County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-02-15); not necessarily full build-out.
- Estimated annual consumption
182 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Wyoming statewide average, July 2026.
- State avg. commercial price
Wyoming statewide average, July 2026.
- Generation within 50 km
10 EIA-reported plants within 50 km.
- Generation queued in county
3 active generation interconnection requests in Laramie County: Wind 650 MW, Hybrid 330 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line | Transmission line | 0.08 km | 115 kV | [6] |
| Cheyenne to 230=Terry Ranch Road & 115=Rockford · Western Area Power Administration | Transmission line | 0.9 km | 230 kV | [6] |
| South Cheyenne Solar · Southern Power Co | Power plant (Solar) | 7 km | 150 MW | [9] |
| Cheyenne Prairie Generating Station · Black Hills Service Company LLC | Power plant (Natural Gas) | 9.9 km | 131 MW | [9] |
| Corriedale Wind Energy · Black Hills Service Company LLC | Power plant (Wind) | 14 km | 53 MW | [9] |
| Roundhouse Renewable Energy II · Roundhouse Renewable Energy II, LLC | Power plant (Wind) | 14.7 km | 106 MW | [9] |
| Silver Sage Windpower · Duke Energy Renewables Services | Power plant (Wind) | 17.8 km | 42 MW | [9] |
| Roundhouse Wind Energy Project · Roundhouse Renewable Energy, LLC | Power plant (Wind) | 23.9 km | 226 MW | [9] |
| Bison Solar LLC · Bison Solar LLC | Power plant (Solar) | 28.7 km | 30 MW | [9] |
| Rawhide · Platte River Power Authority | Power plant (Natural Gas) | 29.5 km | 668 MW | [9] |
| Unnamed substation | Substation | 0.07 km | 115 kV | [6] |
| Unnamed substation | Substation | 0.55 km | 115 kV | [6] |
| Unnamed substation | Substation | 1.96 km | 115 kV | [6] |
| Unnamed substation | Substation | 2.89 km | — | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| GI-TC-2024-16 at Ault-Laramie River Station 345 LineSPP GI-TC-2024-16 | Wind | IA signed · proposed 2029-06 | 400 MW | [7] |
| GI-CS-2025-04 at Ault LRS 345 LineSPP GI-CS-2025-04 | Hybrid | In study · proposed 2029-11 | 330 MW | [7] |
| GI-TC-2024-15 at Big Bear 345 Switching StationSPP GI-TC-2024-15 | Wind | IA signed · proposed 2029-09 | 250 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startMay 15, 2024[1]
- First operationalJul 25, 2026[1]
- Expected completionFeb 15, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-02-15); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Sum of 2 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- May 15, 2024[1]
Ground is being cleared.
- Jan 30, 2025[1]
Structure for Building 1 and 2 under construction.
- Mar 22, 2026[1]
Building 1 shell and cooling looks complete, Building 2 roof almost complete.
Both buildings estimated to be operational.
Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.
All claims (provenance audit)
35| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Cheyenne | [1] | Likely | 2026-07-25 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-05-15 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-01-30 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-22 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-07-25 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-25 | Shown |
| Address | Cheyenne, WY 82007, USA | [1] | Likely | 2026-07-25 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-07-25 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-07-25 | Shown |
| Utility | Black Hills Energy | [2] | Confirmed | 2026-09-11 | Shown |
| Current facility power | 182 MW | [1] estimated | Likely | 2026-07-25 | Shown |
| Current IT capacity | 152 MW | [1] estimated | Likely | 2026-07-25 | Shown |
| Planned capacity | 249 MW | [1] estimated | Likely | 2026-07-25 | Shown |
| Estimated annual consumption | 1,116 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | WACM | [5] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (115 kV)way/1493658682 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.1 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 980 MW | [7] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 8.62¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.26¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.46 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 4 | [1] derived | Likely | 2026-07-25 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-07-25 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-05-15 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-01-30 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-22 | Superseded / alternative |
| Building footprint | 635,300 sq ftway/1485867768 way/1485867769 | [6] derived | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $5.8B | [1] estimated | Likely | 2026-07-25 | Shown |
| Compute (H100-equivalents) | 172,800 | [1] estimated | Likely | 2026-07-25 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-07-25 | Shown |
| Construction start | May 15, 2024 | [1] derived | Likely | 2026-07-25 | Shown |
| First operational | Jul 25, 2026 | [1] derived | Likely | 2026-07-25 | Shown |
| Expected completion | Feb 15, 2027 | [1] estimated | Speculative | 2026-07-25 | Shown |