Meta El Paso Data Center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Plus on-site / dedicated generation: 366 MW[2] — shown separately from grid capacity.
- ⚠ Construction is documented, but no grid record or phase capacity yet backs the 1 GW announced.
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- Current stage: Under construction (furthest stage with documented evidence)[1]
- Construction elapsed: Construction documented since 2025-10-13 (1.0 years).
- Required: 1 GW
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Company announcement, Utility filing / announcement, News report.
Grid path
- →facilityMeta El Paso Data Center
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- 366 MW "bridging" generation planned by El Paso Electric, paid for by Meta (dedicated)[2]“El Paso Electric is planning 366 MW "bridging" power generation to accelerate expansion, with Meta responsible for all costs.”Unknown typeDedicated plant366 MWLikely
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 31.77282, -106.23591
- County
- El Paso County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Developer
- Utility
“El Paso Electric Meta / Data Center Northeast El Paso, TX” Listed by EEI under this member utility.
No tenants or end users identified in our sources yet.
Power (all fields)
- Planned capacity
- On-site / dedicated generation
“El Paso Electric is planning 366 MW "bridging" power generation to accelerate expansion, with Meta responsible for all costs.”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
15 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Montana Power Station · El Paso Electric Co | Power plant (Natural Gas) | 6.1 km | 352 MW | [7] |
| Copper · El Paso Electric Co | Power plant (Natural Gas) | 13.3 km | 63 MW | [7] |
| Phelps Dodge Refining · Phelps Dodge Refining Corp | Power plant (Natural Gas) | 14.7 km | 15 MW | [7] |
| Newman Solar · Newman Solar LLC | Power plant (Solar) | 29.1 km | 10 MW | [7] |
| Rio Grande · El Paso Electric Co | Power plant (Natural Gas) | 29.6 km | 313 MW | [7] |
| Newman · El Paso Electric Co | Power plant (Natural Gas) | 29.9 km | 931 MW | [7] |
| Buena Vista Energy Center · Buena Vista Energy Center, LLC | Power plant (Solar) | 33 km | 170 MW | [7] |
| Roadrunner Solar · NRG Solar Roadrunner | Power plant (Solar) | 41.4 km | 20 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
“Meta executives on Thursday unveiled a massive expansion of its planned data center in Northeast – boosting its investment from $1.5 billion to $10 billion.”
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
All claims (provenance audit)
15| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Under construction | [1] AI-extracted | Likely | Shown | |
| Operator | Meta | [1] AI-extracted | Likely | 2026-03-29 | Shown |
| Developer | Meta | [1] AI-extracted | Likely | 2026-03-29 | Shown |
| Utility | El Paso Electric | [2] | Confirmed | 2026-09-11 | Shown |
| Utility | El Paso Electric | [1] AI-extracted | Likely | 2026-03-29 | Shown |
| Planned capacity | 1 GW | [2] | Likely | 2026-09-11 | Shown |
| Planned capacity | 1 GW | [3] AI-extracted | Likely | 2026-03-26 | Shown |
| On-site / dedicated generation | 366 MW "bridging" generation planned by El Paso Electric, paid for by Meta (dedicated) | [2] | Likely | 2026-09-11 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | EPE | [5] derived | Likely | — | Shown |
| State avg. industrial price | 7.07¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.9 GW | [7] derived | Confirmed | 202502 | Shown |
| Capital cost / investment | $10B | [1] AI-extracted | Likely | Shown | |
| Construction start | Oct 13, 2025 | [1] AI-extracted | Likely | Shown |