DC
/

Meta Gallatin

OperatingAI campusCampusGallatin, Sumner County, Tennessee
70% profile completeness
29 claims from 9 sources
Current facility power
114 MW[1]
Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Likelyderived
Capital cost / investment
$3.3B[1]
Likelyestimated
First operational
Jun 15, 2026[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Cumberland Elec Member Corp · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
114 MW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionSep 11, 2023
    Model estimate · Satellite imagery
    • Sep 11, 2023 · Reported status: under construction[1]
    • Sep 11, 2023 · Construction start[1]
    • Sep 11, 2023 · Land clearing starts for Building 1.[1]
  3. EnergizationJun 15, 2026
    Satellite imagery
    • Jun 15, 2026 · Building 1 is operational (estimate).[1]
  4. OperationalJun 15, 2026
    Satellite imagery
    • Jun 15, 2026 · Building 1 is operational (estimate).[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Gallatin
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.43 km away
  3. transmission
    161 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.42 km away). Not confirmed as the supply path.
  4. utility
    Cumberland Elec Member Corp[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[4]
    Service territoryLikely
    Balancing authority: TVA
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
36.40616, -86.36712
Address
1 Meta Lp, Gallatin, TN 37066[1]Likely
County
Sumner County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Current facility power
114 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
87 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
699 GWh/yr[3]Speculativeestimated

114 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[4]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
TVA[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (161 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.4 km[5]Likelyderived
Highest-voltage line nearby
161 kV[5]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
7.13¢/kWh[6]Confirmed

Tennessee statewide average, July 2026.

State avg. commercial price
13.43¢/kWh[6]Confirmed

Tennessee statewide average, July 2026.

Generation within 50 km
1.84 GW[7]Confirmedderived

9 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
161 kV lineTransmission line0.42 km161 kV[5]
Gallatin (Tn) · Tennessee Valley AuthorityPower plant (Coal)10.5 km1.56 GW[7]
Old Hickory · USCE-Nashville DistrictPower plant (Hydroelectric)28.5 km116 MW[7]
J P Priest · USCE-Nashville DistrictPower plant (Hydroelectric)35.8 km30 MW[7]
Opryland Usa · Gaylord Entertainment CoPower plant (Natural Gas)36.5 km4 MW[7]
Sr Warren, LLC · SR Warren, LLCPower plant (Solar)37.6 km4 MW[7]
Sr Franklin, LLC · SR Franklin, LLCPower plant (Solar)37.8 km3 MW[7]
Cordell Hull · USCE-Nashville DistrictPower plant (Hydroelectric)40 km106 MW[7]
Vanderbilt University Power Plant · Vanderbilt UniversityPower plant (Natural Gas)48.7 km18 MW[7]
Unnamed substationSubstation0.43 km161 kV[5]
Meta Switching Station · Tennessee Valley AuthoritySubstation0.5 km161 kV[5]
Bledsoe Substation · Cumberland Electric Membership CorporationSubstation1.22 km161 kV[5]
Cumberland Electric Membership Corporation substation · Cumberland Electric Membership CorporationSubstation1.59 km161 kV[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Sep 11, 2023[1]
  5. First operational
    Jun 15, 2026[1]
  6. Expected completion
    —
Buildings (planned)
1[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
1[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational114 MWJun 15, 2026[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$3.3B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed
Compute (H100-equivalents)
99,500[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Sep 11, 2023[1]→1Jun 15, 2026[1]
  • Status
    Under constructionSep 11, 2023[1]→OperatingJun 15, 2026[1]

Timeline

Construction start: Sep 11, 2023[1]
First operational: Jun 15, 2026[1]
  1. Sep 11, 2023[1]

    Land clearing starts for Building 1.

  2. Feb 9, 2026[1]

    Building 1 shell and cooling looks complete, but construction equipment still seen around cooling and building. We estimate another 4 months to operational.

  3. Jun 15, 2026114 MW facility power· 1 buildings operational[1]

    Building 1 is operational (estimate).

Buildings on this campus

4

All claims (provenance audit)

29
FieldValueSourceConfidenceAs ofStatus
NameMeta Gallatin[1] Likely2026-06-15Shown
StatusUnder construction[1] derivedLikely2023-09-11Superseded / alternative
StatusUnder construction[1] derivedLikely2026-02-09Superseded / alternative
StatusOperating[1] derivedLikely2026-06-15Shown
Facility typeAI campus[1] derivedLikely2026-06-15Shown
Address1 Meta Lp, Gallatin, TN 37066[1] Likely2026-06-15Shown
OwnerMetaOwner: Meta[1] Confirmed2026-06-15Shown
End usersMetaUsers: Meta[1] Confirmed2026-06-15Shown
UtilityCumberland Elec Member Corpterritory 4624: CUMBERLAND ELEC MEMBER CORP (COOPERATIVE, CUMBERLAND ELEC MEMBER[2] derivedLikely2022Shown
Current facility power114 MW[1] estimatedLikely2026-06-15Shown
Current IT capacity87 MW[1] estimatedLikely2026-06-15Shown
Estimated annual consumption699 GWh/yr[3] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[4] derivedLikely—Shown
Balancing authorityTVA[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (161 kV)way/1213758204[5] derivedLikely2026-09-28Shown
Distance to substation0.4 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby161 kV[5] derivedLikely2026-09-28Shown
State avg. industrial price7.13¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price13.43¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km1.84 GW[7] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-06-15Shown
Buildings operational1[1] estimatedLikely2026-06-15Shown
Buildings operational0[1] estimatedLikely2023-09-11Superseded / alternative
Buildings operational0[1] estimatedLikely2026-02-09Superseded / alternative
Capital cost / investment$3.3B[1] estimatedLikely2026-06-15Shown
Compute (H100-equivalents)99,500[1] estimatedLikely2026-06-15Shown
Chip typesB300[1] Confirmed2026-06-15Shown
Construction startSep 11, 2023[1] derivedLikely2026-06-15Shown
First operationalJun 15, 2026[1] derivedLikely2026-06-15Shown