Meta Gallatin
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Gallatin
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.43 km away
- →transmission161 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.42 km away). Not confirmed as the supply path.
- →utilityCumberland Elec Member Corp[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 36.40616, -86.36712
- Address
- County
- Sumner County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
114 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Tennessee statewide average, July 2026.
- State avg. commercial price
Tennessee statewide average, July 2026.
- Generation within 50 km
9 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 161 kV line | Transmission line | 0.42 km | 161 kV | [5] |
| Gallatin (Tn) · Tennessee Valley Authority | Power plant (Coal) | 10.5 km | 1.56 GW | [7] |
| Old Hickory · USCE-Nashville District | Power plant (Hydroelectric) | 28.5 km | 116 MW | [7] |
| J P Priest · USCE-Nashville District | Power plant (Hydroelectric) | 35.8 km | 30 MW | [7] |
| Opryland Usa · Gaylord Entertainment Co | Power plant (Natural Gas) | 36.5 km | 4 MW | [7] |
| Sr Warren, LLC · SR Warren, LLC | Power plant (Solar) | 37.6 km | 4 MW | [7] |
| Sr Franklin, LLC · SR Franklin, LLC | Power plant (Solar) | 37.8 km | 3 MW | [7] |
| Cordell Hull · USCE-Nashville District | Power plant (Hydroelectric) | 40 km | 106 MW | [7] |
| Vanderbilt University Power Plant · Vanderbilt University | Power plant (Natural Gas) | 48.7 km | 18 MW | [7] |
| Unnamed substation | Substation | 0.43 km | 161 kV | [5] |
| Meta Switching Station · Tennessee Valley Authority | Substation | 0.5 km | 161 kV | [5] |
| Bledsoe Substation · Cumberland Electric Membership Corporation | Substation | 1.22 km | 161 kV | [5] |
| Cumberland Electric Membership Corporation substation · Cumberland Electric Membership Corporation | Substation | 1.59 km | 161 kV | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startSep 11, 2023[1]
- First operationalJun 15, 2026[1]
- Expected completion—
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 114 MW | Jun 15, 2026 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
Buildings on this campus
4- Gallatin Data CenterOperating
- Meta Gallatin Data CenterOperating · 627,800 sq ft footprint
- Meta Gallatin Data CenterOperating · 627,800 sq ft footprint
- Meta Gallatin Data CenterOperating · 627,900 sq ft footprint
All claims (provenance audit)
29| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Gallatin | [1] | Likely | 2026-06-15 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-09-11 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-09 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-06-15 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-15 | Shown |
| Address | 1 Meta Lp, Gallatin, TN 37066 | [1] | Likely | 2026-06-15 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-06-15 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-06-15 | Shown |
| Utility | Cumberland Elec Member Corpterritory 4624: CUMBERLAND ELEC MEMBER CORP (COOPERATIVE, CUMBERLAND ELEC MEMBER | [2] derived | Likely | 2022 | Shown |
| Current facility power | 114 MW | [1] estimated | Likely | 2026-06-15 | Shown |
| Current IT capacity | 87 MW | [1] estimated | Likely | 2026-06-15 | Shown |
| Estimated annual consumption | 699 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | TVA | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (161 kV)way/1213758204 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 161 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 7.13¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.43¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.84 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-06-15 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-06-15 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-09-11 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-09 | Superseded / alternative |
| Capital cost / investment | $3.3B | [1] estimated | Likely | 2026-06-15 | Shown |
| Compute (H100-equivalents) | 99,500 | [1] estimated | Likely | 2026-06-15 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-06-15 | Shown |
| Construction start | Sep 11, 2023 | [1] derived | Likely | 2026-06-15 | Shown |
| First operational | Jun 15, 2026 | [1] derived | Likely | 2026-06-15 | Shown |