Meta Huntsville Data center
Part of Meta Huntsville
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityMeta Huntsville Data center
- →substationGladstone Switching Station (161 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.62 km away. Proximity does not establish that it serves the site.
- →transmission161 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.07 km away). Not confirmed as the supply path.
- →utilityCity of Huntsville - (Al)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 34.84732, -86.62679
- County
- Madison County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Alabama statewide average, July 2026.
- State avg. commercial price
Alabama statewide average, July 2026.
- Generation within 50 km
8 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 161 kV line | Transmission line | 1.07 km | 161 kV | [1] |
| Tai Huntsville Solar Hybrid · TAI Huntsville Solar, LLC | Power plant (Solar) | 2 km | 32 MW | [5] |
| Cumblerland Land Holdings, LLC · Cumberland Land Holdings, LLC | Power plant (Solar) | 24.8 km | 15 MW | [5] |
| Redstone Arsenal Hybrid · MN8 Energy LLC | Power plant (Solar) | 26.3 km | 8 MW | [5] |
| Elora Solar · Elora Solar | Power plant (Solar) | 35.2 km | 150 MW | [5] |
| Decatur Energy Center · Decatur Energy Center LLC | Power plant (Natural Gas) | 43.5 km | 800 MW | [5] |
| Morgan Energy Center · Morgan Energy Center LLC | Power plant (Natural Gas) | 46.1 km | 782 MW | [5] |
| Browns Ferry · Tennessee Valley Authority | Power plant (Nuclear) | 47.7 km | 3.66 GW | [5] |
| Decatur-Morgan CO Lfg Recovery Project · Energy Developments, Inc d/b/a EDL | Power plant (Biomass) | 50 km | 2 MW | [5] |
| Gladstone Switching Station · Tennessee Valley Authority | Substation | 0.62 km | 161 kV | [1] |
| Flash Substation · Meta | Substation | 1.11 km | 161 kV | [1] |
| Liberty Hill Substation | Substation | 1.95 km | 161 kV | [1] |
| Unnamed substation | Substation | 2.66 km | — | [1] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
1- Meta HuntsvilleOperating · 669,000 sq ft footprint
All claims (provenance audit)
14| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Huntsville Data centerway/1160814413 name=Meta Huntsville Data center | [1] | Likely | 2026-09-27 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-09-27 | Shown |
| Operator | Metaoperator=Meta | [1] | Likely | 2026-09-27 | Shown |
| Utility | City of Huntsville - (Al)territory 9094: CITY OF HUNTSVILLE - (AL) (MUNICIPAL, CITY OF HUNTSVILLE - (AL)) | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | TVA | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Gladstone Switching Station (161 kV)way/1221572498 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.6 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 161 kV | [1] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 8.42¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.83¢/kWh | [4] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.45 GW | [5] derived | Confirmed | 202502 | Shown |
| Building footprint | 579,700 sq ft | [1] derived | Likely | 2026-09-27 | Shown |