Meta Huntsville
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationMar 4, 2026
Satellite imagery
- Mar 4, 2026 · We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.[1]
- Jun 2, 2026 · We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers constr[1]
- OperationalMar 4, 2026
Satellite imagery
- Mar 4, 2026 · We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.[1]
- Jun 2, 2026 · We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers constr[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Huntsville
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmission161 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.82 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 34.85389, -86.62518
- Address
- County
- Madison County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
- Energy partner
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
198 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Alabama statewide average, July 2026.
- State avg. commercial price
Alabama statewide average, July 2026.
- Generation within 50 km
8 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 161 kV line | Transmission line | 1.82 km | 161 kV | [5] |
| Tai Huntsville Solar Hybrid · TAI Huntsville Solar, LLC | Power plant (Solar) | 2.7 km | 32 MW | [7] |
| Cumblerland Land Holdings, LLC · Cumberland Land Holdings, LLC | Power plant (Solar) | 24.6 km | 15 MW | [7] |
| Redstone Arsenal Hybrid · MN8 Energy LLC | Power plant (Solar) | 27 km | 8 MW | [7] |
| Elora Solar · Elora Solar | Power plant (Solar) | 34.7 km | 150 MW | [7] |
| Decatur Energy Center · Decatur Energy Center LLC | Power plant (Natural Gas) | 44 km | 800 MW | [7] |
| Morgan Energy Center · Morgan Energy Center LLC | Power plant (Natural Gas) | 46.6 km | 782 MW | [7] |
| Browns Ferry · Tennessee Valley Authority | Power plant (Nuclear) | 48.1 km | 3.66 GW | [7] |
| Tims Ford · Tennessee Valley Authority | Power plant (Hydroelectric) | 49.5 km | 40 MW | [7] |
| Gladstone Switching Station · Tennessee Valley Authority | Substation | 0.61 km | 161 kV | [5] |
| Flash Substation · Meta | Substation | 1.86 km | 161 kV | [5] |
| Liberty Hill Substation | Substation | 2.66 km | 161 kV | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Sum of 2 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Dec 13, 2021[1]
Building 1 land clearing begins.
- Mar 3, 2025[1]
Building 2 roof starts to go on and its cooling installation is in progress.
- Nov 4, 2025[1]
We believe Building 1 and 2 are still being finished due to continued construction vehicles and unfinished land around the data center sites.
- Feb 2, 2026[1]
Color artifacts appear on small number of Building 1 fans. Continued presence of construction equipment and unfinished land around Building 2 suggests the final phase of construction.
We estimate that Building 1 is operational 30 days after the appearance of color artifacts on the fans.
We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.
Buildings on this campus
1- Meta Huntsville Data centerOperating · 579,700 sq ft footprint
All claims (provenance audit)
40| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Huntsville | [1] | Likely | 2026-06-02 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-12-13 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-03-03 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-11-04 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-02-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-04 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-06-02 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-02 | Shown |
| Address | 5400 Prosperity Dr NW, Toney, AL | [1] | Likely | 2026-06-02 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-06-02 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-06-02 | Shown |
| Utility | Tennessee Valley AuthorityEnergy companies: Tennessee Valley Authority | [1] | Confirmed | 2026-06-02 | Shown |
| Energy partners | NextEra Energy ResourcesEnergy companies: NextEra Energy Resources | [1] | Confirmed | 2026-06-02 | Shown |
| Energy partners | First SolarEnergy companies: First Solar | [1] | Confirmed | 2026-06-02 | Shown |
| Current facility power | 198 MW | [1] estimated | Likely | 2026-06-02 | Shown |
| Current facility power | 105 MW | [1] estimated | Likely | 2026-03-04 | Superseded / alternative |
| Current IT capacity | 146 MW | [1] estimated | Likely | 2026-06-02 | Shown |
| Current IT capacity | 78 MW | [1] estimated | Likely | 2026-03-04 | Superseded / alternative |
| Estimated annual consumption | 1,214 GWh/yr | [2] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | TVA | [4] derived | Likely | — | Shown |
| Nearest mapped substation | Gladstone Switching Station (161 kV)way/1221572498 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.6 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 161 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 8.42¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.83¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.49 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-06-02 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-06-02 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-12-13 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-03-03 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-11-04 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-02-02 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-04 | Superseded / alternative |
| Building footprint | 669,000 sq ftway/1540172608 way/1540172612 | [5] derived | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $5.5B | [1] estimated | Likely | 2026-06-02 | Shown |
| Compute (H100-equivalents) | 166,800 | [1] estimated | Likely | 2026-06-02 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-06-02 | Shown |
| Construction start | Dec 13, 2021 | [1] derived | Likely | 2026-06-02 | Shown |
| First operational | Mar 4, 2026 | [1] derived | Likely | 2026-06-02 | Shown |