Meta Hyperion
Also known as Richland Parish Data Center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ Announced 5 GW is 2.3× the 2.2 GW documented by grid, construction or operating records.
- ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Company announcement, Model estimate, Satellite imagery.
Grid path
- →facilityMeta Hyperion
- →substationOn-site substation[1]Satellite imageryLikely8 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Natural gas (new Entergy generating plants)[2]“seven new natural gas-fueled generating plants”Natural gasDedicated plantConfirmed
Location & imagery
Mapped outline- Coordinates
- 32.49795, -91.63490
- Address
- County
- Richland Parish
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
- Utility
- Contractor
“we’ve worked closely with three general contractors — DPR Construction, Turner Construction Company, and Mortenson Construction — to hire locally”
“we’ve worked closely with three general contractors — DPR Construction, Turner Construction Company, and Mortenson Construction — to hire locally”
“we’ve worked closely with three general contractors — DPR Construction, Turner Construction Company, and Mortenson Construction — to hire locally”
Power (all fields)
- Planned capacity
- Power sources
“seven new natural gas-fueled generating plants”
“three grid-scale batteries”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Louisiana statewide average, July 2026.
- State avg. commercial price
Louisiana statewide average, July 2026.
- Generation within 50 km
6 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Richland Parish: Solar 600 MW, Hybrid 150 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Oak Ridge Solar · AES Clean Energy | Power plant (Solar) | 16.7 km | 200 MW | [8] |
| Bayou Galion Solar Project · Bayou Galion Solar Project, LLC | Power plant (Solar) | 36.1 km | 98 MW | [8] |
| Perryville Power Station · Entergy Louisiana LLC | Power plant (Natural Gas) | 41.8 km | 726 MW | [8] |
| Ouachita · Entergy Louisiana LLC | Power plant (Natural Gas) | 46.7 km | 722 MW | [8] |
| Sterlington · Entergy Louisiana LLC | Power plant (Natural Gas) | 47.5 km | 46 MW | [8] |
| Plant 31 Paper Mill · Graphic Packaging International | Power plant (Biomass) | 48.3 km | 77 MW | [8] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J2519 at SmallingMISO J2519 | Solar | In study · proposed 2026-10 | 600 MW | [6] |
| J2838 at DUNN - OAK RIDGE (LA) 115.0kVMISO J2838 | Hybrid | In study · proposed 2025-03 | 150 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- AnnouncedJul 13, 2026[2]
- Land acquired—
- Permitting—
- Construction startDec 20, 2024[1]
- First operationalJan 1, 2028[1]Projected
- Expected completionJan 1, 2028[1]Projected
- Planned capacity
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Buildings 1–9 | under construction | 2.2 GW | Jan 1, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Site area
“Meta’s data center will be built on what is referred to as the Franklin Farm mega site, a more than 1,400-acre certified site, in Richland Parish, Louisiana”
- Capital cost / investment
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
“Once completed, it will be Meta’s largest data center at more than 4-million square feet.”
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Dec 20, 2024[1]
Land clearing begins.
- Oct 19, 2025[1]
Foundations are underway for the main buildings, and the overall layout aligns with the architectural renderings published in 2025.
- Apr 19, 2026[1]
Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.
New power stations are in service for a 1.8 GW load at Holly Ridge. However, the data center is still not operational.
First phase is operational, based on a Meta blog post. We assume that this aligns with the three natural gas turbines being completed, for a total of 2262 MW capacity, but that these turbines have a backup role. This is close to the 1800 MW of load requested from the grid. Meta claims that "The Hyperion cluster will have a 5-gigawatt capacity once complete", but so far there is no concrete evidence for this happening at the Holly Ridge site alone.
All claims (provenance audit)
48| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Hyperion | [1] | Likely | 2026-04-19 | Shown |
| Also known as | Richland Parish Data Center | [2] | Confirmed | 2026-07-13 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-12-20 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-10-19 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-04-19 | Superseded / alternative |
| Status | Planned | [3] AI-extracted | Likely | 2024-12-06 | Superseded / alternative |
| Status | Operating + expanding | [2] AI-extracted | Likely | 2026-07 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-04-19 | Shown |
| Project | Hyperion | [1] | Confirmed | 2026-04-19 | Shown |
| Project | Hyperion | [2] AI-extracted | Likely | 2026-07 | Shown |
| Address | Holly Ridge, LA 71269 | [1] | Likely | 2026-04-19 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-04-19 | Shown |
| Owner | Meta | [2] | Confirmed | 2026-07-13 | Shown |
| Operator | Meta | [3] AI-extracted | Likely | 2024-12-06 | Shown |
| Operator | Meta | [2] AI-extracted | Likely | 2026-07-13 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-04-19 | Shown |
| Utility | EntergyEnergy companies: Entergy | [1] | Confirmed | 2026-04-19 | Shown |
| Utility | Entergy | [2] | Confirmed | 2026-07-13 | Shown |
| Utility | Entergy | [3] AI-extracted | Likely | 2024-12-06 | Shown |
| Construction | MortensonConstruction companies: Mortenson | [1] | Confirmed | 2026-04-19 | Shown |
| Construction | DPR Construction | [2] AI-extracted | Likely | 2026-07-13 | Shown |
| Construction | Turner Construction Company | [2] AI-extracted | Likely | 2026-07-13 | Shown |
| Construction | Mortenson Construction | [2] AI-extracted | Likely | 2026-07-13 | Shown |
| Planned capacity | 2.2 GW | [1] estimated | Likely | 2026-04-19 | Superseded / alternative |
| Planned capacity | 5 GW | [2] | Confirmed | 2026-07-13 | Shown |
| Planned capacity | 5 GW | [2] AI-extracted | Likely | 2026-07 | Superseded / alternative |
| Power sources | Natural gas (new Entergy generating plants) | [2] | Confirmed | 2026-07-13 | Shown |
| Power sources | Grid-scale battery storage | [2] | Confirmed | 2026-07-13 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [4] derived | Likely | — | Shown |
| Balancing authority | MISO | [5] derived | Likely | — | Shown |
| Generation queued in county | 750 MW | [6] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 6.08¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.97¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.87 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 9 | [1] derived | Likely | 2026-04-19 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-04-19 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-12-20 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-19 | Superseded / alternative |
| Floor area | 4M sq ft | [3] AI-extracted | Likely | 2024-12-06 | Shown |
| Site area | 1,400 acres | [3] AI-extracted | Likely | 2024-12-06 | Shown |
| Capital cost / investment | $50B | [2] | Confirmed | 2026-07-13 | Shown |
| Capital cost / investment | $10B | [3] AI-extracted | Likely | 2024-12-06 | Superseded / alternative |
| Capital cost / investment | $50B | [2] AI-extracted | Likely | 2026-07 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-04-19 | Shown |
| Announced | Jul 13, 2026 | [2] AI-extracted | Likely | 2026-07 | Shown |
| Construction start | Dec 20, 2024 | [1] derived | Likely | 2026-04-19 | Shown |
| First operational | Jan 1, 2028 | [1] estimated | Speculative | 2026-04-19 | Shown |
| Expected completion | Jan 1, 2028 | [1] estimated | Speculative | 2026-04-19 | Shown |