Meta Kuna
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationJun 1, 2026
Satellite imagery
- Jun 1, 2026 · Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes tha[1]
- OperationalJun 1, 2026
Satellite imagery
- Jun 1, 2026 · Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes tha[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Kuna
- →substationSatellite imageryLikely3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.31 km away
- →transmission230 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.19 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Orchard Ranch Solar (Solar, 20 MW) is 1.2 km away[7]EIA plant within 1.5 km; proximity does not establish that it supplies the facilitySolarCo-located20 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 43.47163, -116.27199
- Address
- County
- Ada County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
198 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Idaho statewide average, July 2026.
- State avg. commercial price
Idaho statewide average, July 2026.
- Generation within 50 km
14 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 0.19 km | 230 kV | [5] |
| Orchard Ranch Solar · Orchard Ranch Solar, LLC | Power plant (Solar) | 1.2 km | 20 MW | [7] |
| Id Solar · AES Distributed Energy | Power plant (Solar) | 5.8 km | 40 MW | [7] |
| Lucky Peak Power Plant Project · Boise-Kuna Irrigation District | Power plant (Hydroelectric) | 18.3 km | 83 MW | [7] |
| Swan Falls · Idaho Power Co | Power plant (Hydroelectric) | 26.8 km | 24 MW | [7] |
| Arrowrock Hydroelectric Project · Boise-Kuna Irrigation District | Power plant (Hydroelectric) | 31.3 km | 16 MW | [7] |
| Murphy Flat Solar · Murphy Flat Power, LLC | Power plant (Solar) | 31.8 km | 20 MW | [7] |
| Simcoe Solar · Simcoe Solar | Power plant (Solar) | 32.7 km | 20 MW | [7] |
| Horseshoe Bend Hydroelectric CO · Horseshoe Bend Hydroelectric Co | Power plant (Hydroelectric) | 48.1 km | 9 MW | [7] |
| Unnamed substation | Substation | 0.31 km | 230 kV | [5] |
| Unnamed substation | Substation | 0.64 km | — | [5] |
| Unnamed substation | Substation | 0.71 km | — | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 3, 2022[1]
- First operationalJun 1, 2026[1]
- Expected completion—
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Buildings 1–2 | operational | 198 MW | Jun 1, 2026 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Sum of 2 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Oct 3, 2022[1]
Land clearing begins.
- Mar 15, 2026[1]
Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the following week.
Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.
All claims (provenance audit)
30| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Kuna | [1] | Likely | 2026-06-01 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-10-03 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-15 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-06-01 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-01 | Shown |
| Address | 601 Kuna Mora Rd, Kuna ID 83634 | [1] | Likely | 2026-06-01 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-06-01 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-06-01 | Shown |
| Utility | Idaho PowerEnergy companies: Idaho Power Company | [1] | Confirmed | 2026-06-01 | Shown |
| Current facility power | 198 MW | [1] estimated | Likely | 2026-06-01 | Shown |
| Current IT capacity | 152 MW | [1] estimated | Likely | 2026-06-01 | Shown |
| Estimated annual consumption | 1,214 GWh/yr | [2] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | IPCO | [4] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (230 kV)way/1340670700 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 9.02¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.16¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 254 MW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-06-01 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-06-01 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-10-03 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-15 | Superseded / alternative |
| Building footprint | 686,100 sq ftway/1455915217 way/1455915218 | [5] derived | Likely | 2026-09-27 | Shown |
| Capital cost / investment | $5.8B | [1] estimated | Likely | 2026-06-01 | Shown |
| Compute (H100-equivalents) | 173,200 | [1] estimated | Likely | 2026-06-01 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-06-01 | Shown |
| Construction start | Oct 3, 2022 | [1] derived | Likely | 2026-06-01 | Shown |
| First operational | Jun 1, 2026 | [1] derived | Likely | 2026-06-01 | Shown |