DC
/

Meta Kuna

OperatingAI campusCampusAda County, Idaho
70% profile completeness
30 claims from 14 sources
Current facility power
198 MW[1]
Likelyestimated
Planned capacity
Not yet sourced
Building footprint
686,100 sq ft[5]
Likelyderived
Buildings (planned)
Likelyderived
Capital cost / investment
$5.8B[1]
Likelyestimated
First operational
Jun 1, 2026[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Idaho Power · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
198 MW[1]
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 3, 2022
    Model estimate · Satellite imagery
    • Oct 3, 2022 · Reported status: under construction[1]
    • Oct 3, 2022 · Construction start[1]
    • Oct 3, 2022 · Land clearing begins.[1]
  3. EnergizationJun 1, 2026
    Satellite imagery
    • Jun 1, 2026 · Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes tha[1]
  4. OperationalJun 1, 2026
    Satellite imagery
    • Jun 1, 2026 · Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes tha[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Kuna
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    3 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.31 km away
  3. transmission
    230 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.19 km away). Not confirmed as the supply path.
  4. utility
    Idaho Power[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    None (non-RTO region)[3]
    Service territoryLikely
    Balancing authority: IPCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Orchard Ranch Solar (Solar, 20 MW) is 1.2 km away[7]
    EIA plant within 1.5 km; proximity does not establish that it supplies the facility
    SolarCo-located20 MWUnverified

Location & imagery

Mapped outline
Coordinates
43.47163, -116.27199
Address
601 Kuna Mora Rd, Kuna ID 83634[1]Likely
County
Ada County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Power (all fields)

Current facility power
198 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
152 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
1,214 GWh/yr[2]Speculativeestimated

198 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[3]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
IPCO[4]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (230 kV)[5]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.3 km[5]Likelyderived
Highest-voltage line nearby
230 kV[5]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.02¢/kWh[6]Confirmed

Idaho statewide average, July 2026.

State avg. commercial price
10.16¢/kWh[6]Confirmed

Idaho statewide average, July 2026.

Generation within 50 km
254 MW[7]Confirmedderived

14 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV lineTransmission line0.19 km230 kV[5]
Orchard Ranch Solar · Orchard Ranch Solar, LLCPower plant (Solar)1.2 km20 MW[7]
Id Solar · AES Distributed EnergyPower plant (Solar)5.8 km40 MW[7]
Lucky Peak Power Plant Project · Boise-Kuna Irrigation DistrictPower plant (Hydroelectric)18.3 km83 MW[7]
Swan Falls · Idaho Power CoPower plant (Hydroelectric)26.8 km24 MW[7]
Arrowrock Hydroelectric Project · Boise-Kuna Irrigation DistrictPower plant (Hydroelectric)31.3 km16 MW[7]
Murphy Flat Solar · Murphy Flat Power, LLCPower plant (Solar)31.8 km20 MW[7]
Simcoe Solar · Simcoe SolarPower plant (Solar)32.7 km20 MW[7]
Horseshoe Bend Hydroelectric CO · Horseshoe Bend Hydroelectric CoPower plant (Hydroelectric)48.1 km9 MW[7]
Unnamed substationSubstation0.31 km230 kV[5]
Unnamed substationSubstation0.64 km—[5]
Unnamed substationSubstation0.71 km—[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Oct 3, 2022[1]
  5. First operational
    Jun 1, 2026[1]
  6. Expected completion
    —
Buildings (planned)
2[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
2[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2operational198 MWJun 1, 2026[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$5.8B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
686,100 sq ft[5]Likelyderived

Sum of 2 building outlines mapped in OpenStreetMap within this campus.

Floor area
Not yet sourced

Compute

Chip types
B300[1]Confirmed
Compute (H100-equivalents)
173,200[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Oct 3, 2022[1]→2Jun 1, 2026[1]
  • Status
    Under constructionOct 3, 2022[1]→OperatingJun 1, 2026[1]

Timeline

Construction start: Oct 3, 2022[1]
First operational: Jun 1, 2026[1]
  1. Oct 3, 2022[1]

    Land clearing begins.

  2. Mar 15, 2026[1]

    Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the following week.

  3. Jun 1, 2026198 MW facility power· 2 buildings operational[1]

    Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.

All claims (provenance audit)

30
FieldValueSourceConfidenceAs ofStatus
NameMeta Kuna[1] Likely2026-06-01Shown
StatusUnder construction[1] derivedLikely2022-10-03Superseded / alternative
StatusUnder construction[1] derivedLikely2026-03-15Superseded / alternative
StatusOperating[1] derivedLikely2026-06-01Shown
Facility typeAI campus[1] derivedLikely2026-06-01Shown
Address601 Kuna Mora Rd, Kuna ID 83634[1] Likely2026-06-01Shown
OwnerMetaOwner: Meta[1] Confirmed2026-06-01Shown
End usersMetaUsers: Meta[1] Confirmed2026-06-01Shown
UtilityIdaho PowerEnergy companies: Idaho Power Company[1] Confirmed2026-06-01Shown
Current facility power198 MW[1] estimatedLikely2026-06-01Shown
Current IT capacity152 MW[1] estimatedLikely2026-06-01Shown
Estimated annual consumption1,214 GWh/yr[2] estimatedSpeculative2026-09-29Shown
ISO / RTONone (non-RTO region)[3] derivedLikely—Shown
Balancing authorityIPCO[4] derivedLikely—Shown
Nearest mapped substationUnnamed substation (230 kV)way/1340670700[5] derivedLikely2026-09-28Shown
Distance to substation0.3 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[5] derivedLikely2026-09-28Shown
State avg. industrial price9.02¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price10.16¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km254 MW[7] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-06-01Shown
Buildings operational2[1] estimatedLikely2026-06-01Shown
Buildings operational0[1] estimatedLikely2022-10-03Superseded / alternative
Buildings operational0[1] estimatedLikely2026-03-15Superseded / alternative
Building footprint686,100 sq ftway/1455915217 way/1455915218[5] derivedLikely2026-09-27Shown
Capital cost / investment$5.8B[1] estimatedLikely2026-06-01Shown
Compute (H100-equivalents)173,200[1] estimatedLikely2026-06-01Shown
Chip typesB300[1] Confirmed2026-06-01Shown
Construction startOct 3, 2022[1] derivedLikely2026-06-01Shown
First operationalJun 1, 2026[1] derivedLikely2026-06-01Shown