Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Average industrial electricity price: 9.02¢/kWh (EIA).
AI data center capacity over time
Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly
Construction pipeline by expected completion
MW from phases with a projected completion date
No dated pipeline yet.
Power reality
Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.
- Announced—
- Interconnection requests—
- Contracted / approved—
- Under construction—
- Operational198 MW
Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.
No large gaps in this scope.
Largest operators & owners
Online + pipeline MW at linked facilities
- Meta198 MW + 0 MW · 1 sites
Largest customers & end users
Tenants and workload owners, where sourced
- Meta198 MW + 0 MW · 1 sites
Utility exposure
Most likely retail utility by location (approximate)
- Idaho Power198 MW + 0 MW · 1 sites
- Fall River Rural Elec Coop INC— · 1 sites
- PacifiCorp— · 1 sites
Grid operators (ISO / RTO)
By facility location
- None (non-RTO region)198 MW + 0 MW · 3 sites
Largest facilities
By online + pipeline MW
| Facility | Status | Online | Pipeline |
|---|---|---|---|
| Meta Kuna | Operating | 198 MW | — |
Facilities by status
- Operating3