Meta Los Lunas
Meta Los Lunas is an operating + expanding ai campus in Los Lunas, New Mexico. Operated or owned by Meta; used by Meta. Current power: 147 MW (estimated). Planned capacity: 273 MW (estimated). Verification: verified operating. 8 cited sources.
Follow
Get changes to Meta Los Lunas
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Meta Los Lunas.” /facilities/meta-los-lunas-los-lunas-nm. Data as of 2026-11-09. Accessed 2026-11-09.
@misc{datacentersource_meta_los_lunas_los_lunas_nm_2026,
title = {{Meta Los Lunas}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/meta-los-lunas-los-lunas-nm}},
note = {Data as of 2026-11-09; accessed 2026-11-09. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationMar 1, 2026
Satellite imagery
- Mar 1, 2026 · Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.[1]
- Oct 26, 2026 · Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.[1]
- OperationalMar 1, 2026
Satellite imagery
- Mar 1, 2026 · Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.[1]
- Oct 26, 2026 · Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Los Lunas
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Depot Substation 0.31 km away
- →transmission115 kV line[3]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.08 km away). Not confirmed as the supply path.
- utilityNot identifiedUnknownUnverified
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling1
- 0 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 24, 2024.Jul 24, 2024modeled water use
Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for the serving utility. Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 34.82674, -106.78768
- Address
- 4250 Messenger Lp, Los Lunas, NM 87031[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likely
- County
- Valencia County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
- 147 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 118 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
- 273 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Estimated annual consumption
- 901 GWh/yr[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Nov 9, 2026.Speculativeestimated
147 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- Nearest mapped substation
- Depot Substation (115 kV)[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.3 km[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 115 kV[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 5.08¢/kWh[4]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Aug 2026.Confirmed
New Mexico statewide average, August 2026.
- State avg. commercial price
- 12.14¢/kWh[4]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Aug 2026.Confirmed
New Mexico statewide average, August 2026.
- Generation within 50 km
- 1.45 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
27 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line | Transmission line | 0.08 km | 115 kV | [3] |
| West Mesa to Belen 115 kV transmission line · Public Service Company of New Mexico | Transmission line | 1.51 km | 115 kV | [3] |
| Sky Ranch Solar · Sky Ranch Solar and Storage | Power plant (Solar) | 5.1 km | 240 MW | [5] |
| La Luz Energy Center · Public Service Co of NM | Power plant (Natural Gas) | 23.6 km | 40 MW | [5] |
| Valencia Energy Facility · Valencia Power LLC | Power plant (Natural Gas) | 24.5 km | 144 MW | [5] |
| Rio Bravo · Public Service Co of NM | Power plant (Natural Gas) | 25.7 km | 141 MW | [5] |
| Ford Utilities Center · University of New Mexico | Power plant (Natural Gas) | 32.2 km | 13 MW | [5] |
| Atrisco Solar LLC · Atrisco Solar LLC | Power plant (Solar) | 40.8 km | 300 MW | [5] |
| Reeves · Public Service Co of NM | Power plant (Natural Gas) | 41.9 km | 146 MW | [5] |
| Atrisco Energy Storage · Atrisco Energy Storage LLC | Power plant (Batteries) | 42.7 km | 300 MW | [5] |
| Depot Substation · Meta | Substation | 0.31 km | 115 kV | [3] |
| South Substation · Meta | Substation | 0.37 km | 115 kV | [3] |
| Unnamed substation | Substation | 2.05 km | 115 kV | [3] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJul 24, 2024[1]
- First operationalMar 1, 2026[1]
- Expected completionJan 1, 2028[1]Projected
- Planned capacity
- 273 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Buildings (planned)
- 3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $4.5B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
- B300[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Confirmed
- Compute (H100-equivalents)
- 133,900[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 26, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity87 MWMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→118 MWOct 26, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power105 MWMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→114 MWMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→147 MWOct 26, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Compute (H100-equivalents)99,500Mar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→133,900Oct 26, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Capital cost / investment$3.3BMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→$4.5BOct 26, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings (planned)
- Buildings operational0Jul 24, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Mar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Oct 26, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionJul 24, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingMar 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Jul 24, 2024[1]
Land clearing starts for new building.
Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.
Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.
Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
Building 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.
Buildings on this campus
5All claims (provenance audit)
34| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Los Lunas | [1] | Likely | 2026-10-26 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-07-24 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-07-28 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-10-26 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-10-26 | Shown |
| Address | 4250 Messenger Lp, Los Lunas, NM 87031 | [1] | Likely | 2026-10-26 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-10-26 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-10-26 | Shown |
| Current facility power | 147 MW | [1] estimated | Likely | 2026-10-26 | Shown |
| Current facility power | 114 MW | [1] estimated | Likely | 2026-03-01 | Superseded / alternative |
| Current facility power | 114 MW | [1] estimated | Likely | 2026-07-28 | Superseded / alternative |
| Current IT capacity | 118 MW | [1] estimated | Likely | 2026-10-26 | Shown |
| Current IT capacity | 87 MW | [1] estimated | Likely | 2026-03-01 | Superseded / alternative |
| Current IT capacity | 87 MW | [1] estimated | Likely | 2026-07-28 | Superseded / alternative |
| Planned capacity | 273 MW | [1] estimated | Likely | 2026-10-26 | Shown |
| Estimated annual consumption | 901 GWh/yr | [2] estimated | Speculative | 2026-11-09 | Shown |
| Nearest mapped substation | Depot Substation (115 kV)way/757092656 | [3] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [3] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 115 kV | [3] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 5.08¢/kWh | [4] | Confirmed | 2026-08 | Shown |
| State avg. commercial price | 12.14¢/kWh | [4] | Confirmed | 2026-08 | Shown |
| Generation within 50 km | 1.45 GW | [5] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-10-26 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-10-26 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-07-24 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-07-28 | Superseded / alternative |
| Capital cost / investment | $4.5B | [1] estimated | Likely | 2026-10-26 | Shown |
| Compute (H100-equivalents) | 133,900 | [1] estimated | Likely | 2026-10-26 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-10-26 | Shown |
| Construction start | Jul 24, 2024 | [1] derived | Likely | 2026-10-26 | Shown |
| First operational | Mar 1, 2026 | [1] derived | Likely | 2026-10-26 | Shown |
| Expected completion | Jan 1, 2028 | [1] estimated | Speculative | 2026-10-26 | Shown |