Meta Los Lunas
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Los Lunas
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps South Substation 0.45 km away
- →transmission115 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.28 km away). Not confirmed as the supply path.
- →utilityContinental Divide El Coop INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 34.82511, -106.78545
- Address
- County
- Valencia County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
105 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
New Mexico statewide average, July 2026.
- State avg. commercial price
New Mexico statewide average, July 2026.
- Generation within 50 km
26 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line | Transmission line | 0.28 km | 115 kV | [5] |
| West Mesa to Belen 115 kV transmission line · Public Service Company of New Mexico | Transmission line | 1.36 km | 115 kV | [5] |
| Sky Ranch Solar · Sky Ranch Solar and Storage | Power plant (Solar) | 4.9 km | 240 MW | [7] |
| La Luz Energy Center · Public Service Co of NM | Power plant (Natural Gas) | 23.4 km | 40 MW | [7] |
| Valencia Energy Facility · Valencia Power LLC | Power plant (Natural Gas) | 24.2 km | 144 MW | [7] |
| Rio Bravo · Public Service Co of NM | Power plant (Natural Gas) | 25.8 km | 141 MW | [7] |
| Ford Utilities Center · University of New Mexico | Power plant (Natural Gas) | 32.3 km | 13 MW | [7] |
| Atrisco Solar LLC · Atrisco Solar LLC | Power plant (Solar) | 41 km | 300 MW | [7] |
| Reeves · Public Service Co of NM | Power plant (Natural Gas) | 41.9 km | 146 MW | [7] |
| Atrisco Energy Storage · Atrisco Energy Storage LLC | Power plant (Batteries) | 42.9 km | 300 MW | [7] |
| South Substation · Meta | Substation | 0.45 km | 115 kV | [5] |
| Depot Substation · Meta | Substation | 0.51 km | 115 kV | [5] |
| Unnamed substation | Substation | 1.83 km | 115 kV | [5] |
| Unnamed substation | Substation | 2.87 km | — | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJul 24, 2024[1]
- First operationalMar 1, 2026[1]
- Expected completion—
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 105 MW | Mar 1, 2026 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
Buildings on this campus
1- MetaOperating · 641,600 sq ft footprint
All claims (provenance audit)
27| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Los Lunas | [1] | Likely | 2026-03-01 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-07-24 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-03-01 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-03-01 | Shown |
| Address | 4250 Messenger Lp, Los Lunas, NM 87031 | [1] | Likely | 2026-03-01 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-03-01 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-03-01 | Shown |
| Utility | Continental Divide El Coop INCterritory 4265: CONTINENTAL DIVIDE EL COOP INC (COOPERATIVE, CONTINENTAL DIVIDE | [2] derived | Likely | 2022 | Shown |
| Current facility power | 105 MW | [1] estimated | Likely | 2026-03-01 | Shown |
| Current IT capacity | 87 MW | [1] estimated | Likely | 2026-03-01 | Shown |
| Estimated annual consumption | 644 GWh/yr | [3] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | PNM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | South Substation (115 kV)way/1191496041 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.5 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 115 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 4.16¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.90¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.45 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-03-01 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-01 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-07-24 | Superseded / alternative |
| Capital cost / investment | $3.3B | [1] estimated | Likely | 2026-03-01 | Shown |
| Compute (H100-equivalents) | 99,500 | [1] estimated | Likely | 2026-03-01 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-03-01 | Shown |
| Construction start | Jul 24, 2024 | [1] derived | Likely | 2026-03-01 | Shown |
| First operational | Mar 1, 2026 | [1] derived | Likely | 2026-03-01 | Shown |