New Mexico
Totals only include facilities with a reported or estimated figure; most sites don't disclose power, so these are floors, not market size estimates. Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Average industrial electricity price: 4.16¢/kWh (EIA).
AI data center capacity over time
Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly
Construction pipeline by expected completion
MW from phases with a projected completion date
Power reality
Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.
- Announced2.45 GW
- Interconnection requests—
- Contracted / approved—
- Under construction2.45 GW
- Operational105 MW
Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.
No large gaps in this scope.
Interconnection queues
Active requests to connect to the grid (SPP). Requests are applications, not commitments — most never get built.
Largest operators & owners
Online + pipeline MW at linked facilities
- Oracle0 MW + 2.45 GW · 1 sites
- Meta105 MW + 0 MW · 6 sites
- Oso Grande— · 1 sites
- bigbyte.cc— · 1 sites
- UNM— · 1 sites
- UNMH— · 1 sites
- Molina Healthcare— · 1 sites
- SONM— · 1 sites
- Lumen Technologies— · 1 sites
- WSMR— · 1 sites
- Sandia National Laboratories— · 1 sites
Largest customers & end users
Tenants and workload owners, where sourced
Utility exposure
Most likely retail utility by location (approximate)
- Continental Divide El Coop INC105 MW + 0 MW · 6 sites
- Public Service CO of Nm— · 9 sites
- El Paso Electric— · 2 sites
Grid operators (ISO / RTO)
By facility location
- None (non-RTO region)105 MW + 2.45 GW · 19 sites
Largest facilities
By online + pipeline MW
| Facility | Status | Online | Pipeline |
|---|---|---|---|
| OpenAI Stargate New Mexico | Under construction | — | 2.45 GW |
| Meta Los Lunas | Operating | 105 MW | — |
Facilities by status
- Operating18
- Under construction1