DC
/

Meta Prometheus

Also known as Prometheus

Operating + expandingAI campusCampusNew Albany, Licking County, Ohio
80% profile completeness
68 claims from 13 sources
Current facility power
645 MW[1]
Likelyestimated
Planned capacity
1.33 GW[1]
Likelyestimated
Building footprint
95,300 sq ft[7]
Likelyderived
Buildings (planned)
27[1]
Likelyderived
Capital cost / investment
$18.8B[1]
Likelyestimated
First operational
Oct 14, 2025[1]
Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery and government record.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
American Electric Power · PJM
Substation: On-site substation

Power reality

Announced
1.33 GW[1]
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
683 MW[1]
Buildings 12–18, Building 19, Building 20, Building 21, Buildings 22–27 under construction (satellite-tracked phases)
Operational
645 MW[1]
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2026-11-30 (modeled/speculative)[1]
  • Required: 1.33 GW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredDec 29, 2022
    Government record
    • Dec 29, 2022 · Land acquisition / deed recorded[3]
    • Dec 29, 2022 · Deed/transfer recorded for parcel 093-107268-00.000 (no sale price disclosed).[3]
    • May 28, 2026 · Deed/transfer recorded for parcel 095-112218-00.000 (no sale price disclosed).[3]
    • Sep 27, 2026 · Owner of record in county parcel data[3]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 14, 2022
    Model estimate · Satellite imagery
    • Apr 14, 2022 · Reported status: under construction[1]
    • Apr 14, 2022 · Construction start[1]
    • Apr 14, 2022 · Land clearing begins for Building 1-2[1]
    • Oct 14, 2025 · Reported status: expanding[1]
  3. EnergizationOct 14, 2025
    Satellite imagery
    • Oct 14, 2025 · Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18[1]
    • Jan 18, 2026 · Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of po[1]
    • May 18, 2026 · Building 7-11 (Meta tents) are operational. In January we saw them look almost complete, with some work still ongoing for power equipment. Assuming 3 more months for commissioning,[1]
  4. OperationalOct 14, 2025
    Satellite imagery · Government record
    • Oct 14, 2025 · Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18[1]
    • Jan 18, 2026 · Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of po[1]
    • May 18, 2026 · Building 7-11 (Meta tents) are operational. In January we saw them look almost complete, with some work still ongoing for power equipment. Assuming 3 more months for commissioning,[1]
    • Sep 27, 2026 · County land use: 350: Industrial Warehouses[3]
    • Sep 27, 2026 · County land use: 399: Other Industrial Structures[3]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Prometheus
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    6 substation outlines traced inside the campus on satellite imagery
  3. transmission
    Jug Street - Kirk 345kV transmission line[7]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.52 km away). Not confirmed as the supply path.
  4. utility
    American Electric Power[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    PJM[5]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Nuclear (contracted)[2]
    “agreements with three nuclear power providers”
    NuclearPPA / contractConfirmed
  • 3 on-site power generator outlines traced on satellite imagery[1]
    Epoch AI satellite annotations (fuel type and capacity not identified)
    Unknown typeBehind-the-meterLikely

Location & imagery

Mapped outline
Coordinates
40.08384, -82.74401
Address
1 Community Cir, New Albany, OH 43054[1]Likely
County
Licking County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Energy partner:
Energy partner:
Energy partner:
Energy partner:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Property owner of record
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Energy partner
Vistra[2]Confirmed

“The arrangements with Vistra, TerraPower and Oklo ... are for Meta's Prometheus supercluster”

TerraPower[2]Confirmed

“The arrangements with Vistra, TerraPower and Oklo ... are for Meta's Prometheus supercluster”

Oklo[2]Confirmed

“The arrangements with Vistra, TerraPower and Oklo ... are for Meta's Prometheus supercluster”

Williams[1]Confirmed

Power (all fields)

Current facility power
645 MW[1]Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
496 MW[1]Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
1.33 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-07-01); not necessarily full build-out.

Estimated annual consumption
3,955 GWh/yr[4]Speculativeestimated

645 MW × 8,760 h × 70% utilization.

Power sources
Nuclear (contracted)[2]Confirmed

“agreements with three nuclear power providers”

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[5]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[6]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Babbitt Substation (138 kV)[7]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
1 km[7]Likelyderived
Highest-voltage line nearby
345 kV[7]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.95¢/kWh[9]Confirmed

Ohio statewide average, July 2026.

State avg. commercial price
14.06¢/kWh[9]Confirmed

Ohio statewide average, July 2026.

Generation within 50 km
21 MW[10]Confirmedderived

8 EIA-reported plants within 50 km.

Generation queued in county
2.52 GW[8]Confirmedderived

14 active generation interconnection requests in Licking County: Solar 1,773 MW, Storage 750 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Jug Street - Kirk 345kV transmission line · American Electric PowerTransmission line0.52 km345 kV[7]
138 kV lineTransmission line0.6 km138 kV[7]
345 kV line · American Electric PowerTransmission line1.38 km345 kV[7]
Jug Street - Corridor 345kV transmission line · American Electric PowerTransmission line1.44 km345 kV[7]
Conesville - Corridor 345kV transmission line · American Electric PowerTransmission line1.89 km345 kV[7]
Denison Solar Array · AEP Onsite Partners, LLCPower plant (Solar)19.3 km2 MW[10]
Dodge Park Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)27.3 km2 MW[10]
St-1/1a Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)27.5 km1 MW[10]
3100 Valleyview Drive · Madison Energy Investments LLCPower plant (Solar)28.1 km1 MW[10]
Renick Run Pumping Station 03-04 · City of Columbus - (OH)Power plant (Petroleum)28.6 km2 MW[10]
Ps St-8 Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)29.3 km2 MW[10]
O'Shaughnessy Hydro · City of Columbus - (OH)Power plant (Hydroelectric)33.4 km5 MW[10]
Suburban Landfill Gas Recovery · WM Renewable Energy LLCPower plant (Biomass)46.6 km6 MW[10]
Babbitt Substation · American Electric PowerSubstation1.04 km138 kV[7]
Babbitt Substation · American Electric PowerSubstation1.12 km345 kV[7]
Jug Street Substation · AEP OhioSubstation1.36 km345 kV[7]
Smith's Mill Substation · Energy CooperativeSubstation1.42 km138 kV[7]
Unnamed substationSubstation1.81 km138 kV[7]
Badger Substation · American Electric PowerSubstation1.84 km138 kV[7]
Largest queued generation in this countyFuelQueue statusMWSource
Centerburg 138 kVPJM AI2-088SolarIn study · proposed 2025-12413 MW[8]
Centerburg 138 kVPJM AG1-034SolarIn study · proposed 2023-10363 MW[8]
Centerburg 138 kVPJM AH1-036StorageIn study · proposed 2024-07278 MW[8]
Centerburg 138 kVPJM AG1-024SolarIn study · proposed 2023-10235 MW[8]
Flint GridPJM AF1-062StorageIA signed · proposed 2026-11200 MW[8]
Jug Street 138 kVPJM AI2-226StorageIn study · proposed 2022-08200 MW[8]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    Dec 29, 2022[3]
  3. Permitting
    —
  4. Construction start
    Apr 14, 2022[1]
  5. First operational
    Oct 14, 2025[1]
  6. Expected completion
    Jul 1, 2028[1]
    Projected
Planned capacity
1.33 GW[1]Likelyestimated

Projected facility power at the last tracked milestone (2028-07-01); not necessarily full build-out.

Buildings (planned)
27[1]Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
11[1]Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational99 MWOct 14, 2025[1]
Buildings 2–6operational379 MWJan 18, 2026[1]
Buildings 7–11operational167 MWMay 18, 2026[1]
Buildings 12–18under construction233 MWNov 30, 2026 (projected)[1]
Building 19under construction84 MWJan 15, 2027 (projected)[1]
Building 20under construction83 MWApr 15, 2027 (projected)[1]
Building 21under construction83 MWJul 14, 2027 (projected)[1]
Buildings 22–27under construction200 MWJul 1, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year
  • $38.9M[3]
    Market value · tax year current (2026) · parcel 093-107268-00.000
  • $17.6M[3]
    Market value — land · tax year current (2026) · parcel 093-107268-00.000
  • $21.3M[3]
    Market value — improvements · tax year current (2026) · parcel 093-107268-00.000
  • $30.1M[3]
    Market value · tax year current (2026) · parcel 095-112218-00.000
  • $29.5M[3]
    Market value — land · tax year current (2026) · parcel 095-112218-00.000
  • $593,100[3]
    Market value — improvements · tax year current (2026) · parcel 095-112218-00.000
Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
093-107268-00.000
Licking County, OH
DISTRIBUTION LAND CORP
3 LIMITED PKWY , COLUMBUS, OH
142.43350: Industrial Warehouses—[3]
095-112218-00.000
Licking County, OH
SIDECAT LLC
1 META WAY , MENLO PARK, CA
414.01399: Other Industrial Structures—[3]
Site area
556.4 acres[3]Confirmed

Sum of county land area across parcels.

Land use
350: Industrial Warehouses[3]Confirmed
Capital cost / investment
$18.8B[1]Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced
Nearby comparable transactions

Size

Building footprint
95,300 sq ft[7]Likelyderived

Sum of 1 building outlines mapped in OpenStreetMap within this campus.

Parcel / land records
093-107268-00.000 (Licking County),095-112218-00.000 (Licking County)[3]Confirmed
Floor area
Not yet sourced

Compute

Project
Prometheus[1]Confirmed
Chip types
B200, B300[1]Confirmed
Compute (H100-equivalents)
599,800[1]Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    76 MWOct 14, 2025[1]→368 MWJan 18, 2026[1]→496 MWMay 18, 2026[1]
  • Current facility power
    99 MWOct 14, 2025[1]→478 MWJan 18, 2026[1]→645 MWMay 18, 2026[1]
  • Buildings operational
    0Apr 14, 2022[1]→1Oct 14, 2025[1]→6Jan 18, 2026[1]→11May 18, 2026[1]
  • Status
    Under constructionApr 14, 2022[1]→Operating + expandingOct 14, 2025[1]

Timeline

Construction start: Apr 14, 2022[1]
First operational: Oct 14, 2025[1]
  1. Apr 14, 2022[1]

    Land clearing begins for Building 1-2

  2. Jun 1, 2025[1]

    Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's unlikely to be operational.

  3. Sep 20, 2025[1]

    Building 4 operational. Based on our default estimate of roof-to-operational time.

  4. Oct 14, 202599 MW facility power· 1 buildings operational[1]

    Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at Socrates South and Socrates North has some outlines of gas turbines, to be installed later.

  5. Jan 18, 2026478 MW facility power· 6 buildings operational[1]

    Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their right side which are not fully installed. Building 14 has chillers installed. Buildings 16-20 roofs are complete. The Socrates South power plant to the right of Buildings 7-11 has 7 gas turbines in place, judging by the exhaust stacks.

  6. Mar 12, 2026478 MW facility power· 6 buildings operational[1]

    The Socrates South power plant to the right of Buildings 7-11 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of tent buildings has begun east of Buildings 16-20. It is unclear how those buildings will be powered, if we assume that the Socrates North power plant is just powering Buildings 16-20.

  7. May 18, 2026645 MW facility power· 11 buildings operational[1]

    Building 7-11 (Meta tents) are operational. In January we saw them look almost complete, with some work still ongoing for power equipment. Assuming 3 more months for commissioning, we expect operation by May. Northern tents numbered 16-27 are all roofed except for 21 and 27.

  8. Aug 31, 2026645 MW facility power· 11 buildings operational[1]

    Tent buildings 16-27 look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.

  9. Nov 30, 2026Projected878 MW facility power· 18 buildings operational[1]

    Socrates South and Socrates North gas power plants are operational, enabling the operability of Buildings 12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and Socrates North. This is based on documents stating "late Third or early Fourth Quarter of 2026", "late 2026", "November 2026", "third quarter of 2026". The timeline also lines up with RAAD drone imagery from 09/08/26 seeing operating turbines at Socrates South and a full set of turbines installed but not yet operating at Socrates North.

  10. Jan 15, 2027Projected962 MW facility power· 19 buildings operational[1]

    Building 13 is operational, based on similar building completion timeframes by Vantage.

  11. Apr 15, 2027Projected1.05 GW facility power· 20 buildings operational[1]

    Building 14 (Vantage) is operational, based on it starting construction about 3 months after Building 12.

  12. Jul 14, 2027Projected1.13 GW facility power· 21 buildings operational[1]

    Building 15 (Vantage) operational, based on it starting construction about 3 months after Building 13.

  13. Jul 1, 2028Projected1.33 GW facility power· 27 buildings operational[1]

    Buildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the Socrates the Younger power plant. The power plant is operational by Q3 of 2028 based on the project schedule. It is announced to produce a maximum of 250MW.

  14. Dec 29, 2022[3]

    Deed/transfer recorded for parcel 093-107268-00.000 (no sale price disclosed).

  15. May 28, 2026[3]

    Deed/transfer recorded for parcel 095-112218-00.000 (no sale price disclosed).

Buildings on this campus

5
  • NAO 1/NAO 2Operating · 664,000 sq ft footprint
  • NAO 3Operating · 366,300 sq ft footprint
  • NAO 5/NAO 6Operating · 609,500 sq ft footprint
  • LCO 1Operating · 366,000 sq ft footprint
  • LCO 2Operating · 304,500 sq ft footprint

All claims (provenance audit)

68
FieldValueSourceConfidenceAs ofStatus
NameMeta Prometheus[1] Likely2026-08-31Shown
Also known asPrometheus[2] Confirmed2026-01-09Shown
StatusUnder construction[1] derivedLikely2022-04-14Superseded / alternative
StatusUnder construction[1] derivedLikely2025-06-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-09-20Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-10-14Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-01-18Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-12Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-05-18Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-08-31Shown
Facility typeAI campus[1] derivedLikely2026-08-31Shown
ProjectPrometheus[1] Confirmed2026-08-31Shown
Address1 Community Cir, New Albany, OH 43054[1] Likely2026-08-31Shown
Property owner of recordDistribution Land CorpParcel 093-107268-00.000: DISTRIBUTION LAND CORP[3] Confirmed2026-09-27Shown
Property owner of recordSidecat LLCParcel 095-112218-00.000: SIDECAT LLC[3] Confirmed2026-09-27Shown
OwnerMetaOwner: Meta[1] Confirmed2026-08-31Shown
End usersMetaUsers: Meta[1] Confirmed2026-08-31Shown
UtilityAmerican Electric PowerEnergy companies: American Electric Power[1] Confirmed2026-08-31Shown
Energy partnersWilliamsEnergy companies: Williams[1] Confirmed2026-08-31Shown
Energy partnersVistra[2] Confirmed2026-01-09Shown
Energy partnersTerraPower[2] Confirmed2026-01-09Shown
Energy partnersOklo[2] Confirmed2026-01-09Shown
Current facility power645 MW[1] estimatedLikely2026-08-31Shown
Current facility power99 MW[1] estimatedLikely2025-10-14Superseded / alternative
Current facility power478 MW[1] estimatedLikely2026-01-18Superseded / alternative
Current facility power478 MW[1] estimatedLikely2026-03-12Superseded / alternative
Current facility power645 MW[1] estimatedLikely2026-05-18Superseded / alternative
Current IT capacity496 MW[1] estimatedLikely2026-08-31Shown
Current IT capacity76 MW[1] estimatedLikely2025-10-14Superseded / alternative
Current IT capacity368 MW[1] estimatedLikely2026-01-18Superseded / alternative
Current IT capacity368 MW[1] estimatedLikely2026-03-12Superseded / alternative
Current IT capacity496 MW[1] estimatedLikely2026-05-18Superseded / alternative
Planned capacity1.33 GW[1] estimatedLikely2026-08-31Shown
Power sourcesNuclear (contracted)[2] Confirmed2026-01-09Shown
Estimated annual consumption3,955 GWh/yr[4] estimatedSpeculative2026-09-29Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[5] derivedLikely—Shown
Balancing authorityPJM[6] derivedLikely—Shown
Nearest mapped substationBabbitt Substation (138 kV)way/708899014[7] derivedLikely2026-09-28Shown
Distance to substation1 km[7] derivedLikely2026-09-28Shown
Highest-voltage line nearby345 kV[7] derivedLikely2026-09-28Shown
Generation queued in county2.52 GW[8] derivedConfirmed2026-09-27Shown
State avg. industrial price10.95¢/kWh[9] Confirmed2026-07Shown
State avg. commercial price14.06¢/kWh[9] Confirmed2026-07Shown
Generation within 50 km21 MW[10] derivedConfirmed202502Shown
Buildings (planned)27[1] derivedLikely2026-08-31Shown
Buildings operational11[1] estimatedLikely2026-08-31Shown
Buildings operational0[1] estimatedLikely2022-04-14Superseded / alternative
Buildings operational0[1] estimatedLikely2025-06-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-09-20Superseded / alternative
Buildings operational1[1] estimatedLikely2025-10-14Superseded / alternative
Buildings operational6[1] estimatedLikely2026-01-18Superseded / alternative
Buildings operational6[1] estimatedLikely2026-03-12Superseded / alternative
Buildings operational11[1] estimatedLikely2026-05-18Superseded / alternative
Building footprint95,300 sq ftway/1375443893[7] derivedLikely2026-09-27Shown
Site area556.4 acres[3] Confirmed2026-09-27Shown
Capital cost / investment$18.8B[1] estimatedLikely2026-08-31Shown
Parcel / land records093-107268-00.000 (Licking County)[3] Confirmed2026-09-27Shown
Parcel / land records095-112218-00.000 (Licking County)[3] Confirmed2026-09-27Shown
Assessed value (official)$69M[3] Confirmed2026Shown
Land use350: Industrial Warehouses[3] Confirmed2026-09-27Shown
Land use399: Other Industrial Structures[3] Confirmed2026-09-27Superseded / alternative
Compute (H100-equivalents)599,800[1] estimatedLikely2026-08-31Shown
Chip typesB200[1] Confirmed2026-08-31Shown
Chip typesB300[1] Confirmed2026-08-31Shown
Land acquiredDec 29, 2022[3] derivedConfirmed2026-09-27Shown
Construction startApr 14, 2022[1] derivedLikely2026-08-31Shown
First operationalOct 14, 2025[1] derivedLikely2026-08-31Shown
Expected completionJul 1, 2028[1] estimatedSpeculative2026-08-31Shown