North Country Data Center

PlannedCrypto / HPCSiteSt. Lawrence County, New York
10% profile completeness
7 claims from 1 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Grid-backed
Construction documented by ISO/RTO queue; grid record on file.
Current stage
Under construction
Furthest stage with documented evidence
Utility · ISO
NYPA · NYISO
Substation: Reynolds 115kV

Power reality

Announced
No record
Interconnection request
435 MW[1]
1 active load interconnection request(s): NYISO 0979
Contracted / approved
435 MW[1]
Interconnection agreement executed: NYISO 0979
Under construction
No record
Operational
No record
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Under construction (furthest stage with documented evidence)[1]
  • Stated date: Requested in-service date (NYISO 0979): 2026-01[1]
  • Date passed: The stated 2026-01 has passed without a confirmed energization record.[1]
  • Required: 435 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection applicationJan 22, 2020
    ISO/RTO queue
    • Jan 22, 2020 · NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026[1]
    • Sep 27, 2026 · Load interconnection request: 435 MW[1]
  2. Feasibility study
    ISO/RTO queue
    • NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026 (queue status as of 2026-09-27)[1]
  3. System impact study
    ISO/RTO queue
    • NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026 (queue status as of 2026-09-27)[1]
  4. Facilities study
    ISO/RTO queue
    • NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026 (queue status as of 2026-09-27)[1]
  5. Interconnection agreement / service contract
    ISO/RTO queue
    • NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026 (queue status as of 2026-09-27)[1]
Build & energization
  1. Financing
  2. Under construction
    ISO/RTO queue
    • NYISO load request 0979 (435 MW): Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026 (queue status as of 2026-09-27)[1]
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: ISO/RTO queue.

Grid path

  1. facility
    North Country Data Center
  2. substation
    Reynolds 115kV[1]
    Queue POIConfirmed
    Point of interconnection in NYISO load request 0979
  3. transmission
    115 kV[1]
    Queue POILikely
    Voltage at the requested point of interconnection (Reynolds 115kV)
  4. utility
    NYPA[1]
    Queue POILikely
    Transmission owner on the interconnection request
  5. ISO / RTO
    NYISO[1]
    Service territoryConfirmed
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

QueueRelationshipStageMW req.MW appr.QueuedExpected in servicePOI / TOSource · as of
NYISO 0979
North Country Data Center
This site's load request
Confirmed
Site record created from this queue entry.
Under construction
Status 12 (Under construction); studies available: SIS; proposed initial backfeed: 01-2026
435—Jan 22, 2020Jan 2026Reynolds 115kV
TO: NYPA
[1] Sep 27, 2026

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

County-level (approximate)

Location is approximate (county-level (approximate)); the marker does not identify the exact site.

Coordinates
44.49689, -75.06752
County
St. Lawrence County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Not identified

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Developer

Interconnection customer on the load request.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
NYISO[1]Confirmed

The request is in this ISO's queue.

Interconnection status
NYISO load request 0979: 435 MW, under construction at Reynolds 115kV[1]Confirmed
Load interconnection request
435 MW[1]Confirmed

NYISO load interconnection request 0979 (Data center (crypto mining)).

Contracted / committed power
Not yet sourced

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    Jan 22, 2020[1]
  4. Construction start
    —
  5. First operational
    Jan 2026[1]
    Projected
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

  1. Jan 22, 2020[1]

    NYISO load interconnection request 0979 filed (435 MW).

  2. Jan 2026Projected[1]

    Proposed initial backfeed / in-service for NYISO load request 0979 (date has passed; not confirmed in service).

All claims (provenance audit)

7
FieldValueSourceConfidenceAs ofStatus
NameNorth Country Data Center[1] Confirmed2026-09-27Shown
StatusPlanned[1] derivedConfirmed2026-09-27Shown
Facility typeCrypto / HPC[1] derivedConfirmed2026-09-27Shown
DeveloperNorth Country Data Center[1] Likely2026-09-27Shown
ISO / RTONYISO[1] Confirmed2026-09-27Shown
Interconnection statusNYISO load request 0979: 435 MW, under construction at Reynolds 115kVStatus 12 (Under construction); studies available: SIS; proposed initial backfee[1] Confirmed2026-09-27Shown
Load interconnection request435 MW[1] Confirmed2026-09-27Shown