QTS Cedar Rapids
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — MISO does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityQTS Cedar Rapids
- →substationOn-site substation[1]Satellite imageryLikely2 substation outlines traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 41.90931, -91.74194
- Address
- County
- Linn County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
No tenants or end users identified in our sources yet.
Power (all fields)
- Planned capacity
Projected facility power at the last tracked milestone (2027-11-15); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Iowa statewide average, July 2026.
- State avg. commercial price
Iowa statewide average, July 2026.
- Generation within 50 km
22 EIA-reported plants within 50 km.
- Generation queued in county
12 active generation interconnection requests in Linn County: Nuclear 1,261 MW, Solar 660 MW, Storage 595 MW, Gas 95 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Archer Daniels Midland Cedar Rapids · Archer Daniels Midland Co | Power plant (Coal) | 4.7 km | 295 MW | [6] |
| Prairie Creek · Interstate Power and Light Co | Power plant (Natural Gas) | 9.3 km | 156 MW | [6] |
| Amana Society Service Company · Amana Society Service Co | Power plant (Petroleum) | 17.9 km | 22 MW | [6] |
| Pleasant Creek Unit 2 · Interstate Power and Light Co | Power plant (Solar) | 22 km | 150 MW | [6] |
| Pleasant Creek Unit 1 · Interstate Power and Light Co | Power plant (Solar) | 22 km | 50 MW | [6] |
| Coralville Gt · MidAmerican Energy Co | Power plant (Natural Gas) | 30.2 km | 63 MW | [6] |
| University of Iowa Main Power Plant · University of Iowa | Power plant (Natural Gas) | 32.7 km | 41 MW | [6] |
| Diamond Trail Wind Farm · MidAmerican Energy Co | Power plant (Wind) | 43.7 km | 250 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| J3932 at Duane Arnold 161 kVMISO J3932 | Nuclear | In study · proposed 2029-06 | 646 MW | [4] |
| J2268 at Duane ArnoldMISO J2268 | Solar | In study · proposed 2024-10 | 400 MW | [4] |
| J2469 at Sub K (Tiffin)-Duane Arnold 345kVMISO J2469 | Storage | In study · proposed 2027-10 | 300 MW | [4] |
| R5071 at Duane Arnold (ARNOLD 5)MISO R5071 | Nuclear | In study | 251 MW | [4] |
| J1444 at Duane Arnold 345kV SubstationMISO J1444 | Solar | IA signed · proposed 2015-08 | 200 MW | [4] |
| R5069 at Duane Arnold (ARNOLD 5)MISO R5069 | Nuclear | In study | 200 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJan 17, 2025[1]
- First operationalNov 15, 2026[1]Projected
- Expected completionNov 15, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-11-15); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Jan 17, 2025[1]
Land clearing begins for Building 1-3.
- Oct 27, 2025[1]
Building 1 roof complete, with air-cooled chillers in place. Building 2 and 3 roofs are partly completed. Building 4 and 5 have a foundation.
- Apr 16, 2026[1]
Based on satellite imagery, the Buildings 1-3 shells look complete. Buildings 4-6 are far along, with roofs largely in place, while the eastern Building 7 foundation is well underway. No buildings operational yet.
- May 7, 2026[1]
Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.
Buildings 1-3 are operational. Based on the expected completion date reported by local news: “A QTS spokesperson said in July [2025] that the first phase of the project was expected to be completed in late 2026."
Buildings 4-7 are operational. Based on the expected completion date reported by local news: “A QTS spokesperson said in July [2025] that [...] The second phase is expected to be completed in late 2027."
All claims (provenance audit)
23| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | QTS Cedar Rapids | [1] | Likely | 2026-05-07 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-01-17 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-10-27 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-04-16 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-05-07 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-07 | Shown |
| Address | 6200 76th Ave SW, Fairfax, IA 52228 | [1] | Likely | 2026-05-07 | Shown |
| Utility | Alliant EnergyEnergy companies: Alliant Energy | [1] | Confirmed | 2026-05-07 | Shown |
| Planned capacity | 1.59 GW | [1] estimated | Likely | 2026-05-07 | Shown |
| ISO / RTO | MISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC.. | [2] derived | Likely | — | Shown |
| Balancing authority | MISO | [3] derived | Likely | — | Shown |
| Generation queued in county | 2.61 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 9.99¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.27¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.11 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 7 | [1] derived | Likely | 2026-05-07 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-05-07 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-01-17 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-10-27 | Superseded / alternative |
| Chip types | Rubin | [1] | Confirmed | 2026-05-07 | Shown |
| Construction start | Jan 17, 2025 | [1] derived | Likely | 2026-05-07 | Shown |
| First operational | Nov 15, 2026 | [1] estimated | Speculative | 2026-05-07 | Shown |
| Expected completion | Nov 15, 2027 | [1] estimated | Speculative | 2026-05-07 | Shown |