QTS Van Wert (Mega Site)
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No grid, construction or operating record yet backs the 500 MW announced.
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No recorded land acquisition found.
How the time-to-power window was estimated
- Current stage: Announced (furthest stage with documented evidence)[1]
- No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
- Required: 500 MW
- From “Announced”, large loads have typically taken 2–5 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Land acquired
- Planning / zoning
- Permitting
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under construction
- Energization
- Operational
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: News report.
Grid path
- →facilityQTS Van Wert (Mega Site)
- →substationNot identifiedUnknownUnverifiedNo substation mapped within 3 km and none named in filings.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityNot identifiedUnknownUnverified
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
County-level (approximate)Location is approximate (county-level (approximate)); the marker does not identify the exact site.
- Coordinates
- 40.85543, -84.59126
- County
- Van Wert County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Operator
“QTS Data Centers, which is headquartered in Overland Park, Kansas, was named as the end user of the $10 billion, 500 megawatt data center at the Mega Site”
No tenants or end users identified in our sources yet.
Power (all fields)
- Planned capacity
“$10 billion, 500 megawatt data center”
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- State avg. industrial price
Ohio statewide average, July 2026.
- State avg. commercial price
Ohio statewide average, July 2026.
- Generation within 50 km
17 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Van Wert County: Solar 1,831 MW, Solar + storage 407 MW, Storage 232 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Blue Creek Wind Project · Avangrid Power LLC | Power plant (Wind) | 8.8 km | 302 MW | [6] |
| Robert P Mone Plant · Buckeye Power, Inc | Power plant (Natural Gas) | 14.9 km | 441 MW | [6] |
| Northwest Ohio Wind · Northwest Ohio Wind, LLC | Power plant (Wind) | 18 km | 105 MW | [6] |
| Paulding Wind Farm II · Paulding Wind Farm II LLC | Power plant (Wind) | 24.6 km | 99 MW | [6] |
| Timber Road Solar Park · Timber Road Solar Park | Power plant (Solar) | 28.7 km | 50 MW | [6] |
| Timber Road IV · Paulding Wind Farm IV LLC | Power plant (Wind) | 32.4 km | 125 MW | [6] |
| Paulding Wind Farm III · Paulding Wind Farm III LLC | Power plant (Wind) | 32.4 km | 101 MW | [6] |
| Blue Harvest Solar Park · Blue Harvest Solar Park LLC | Power plant (Solar) | 37.4 km | 50 MW | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Blue Creek Wind FarmPJM AE1-102 | Solar | Suspended · proposed 2024-11 | 396 MW | [4] |
| Blue Creek Wind FarmPJM AC2-044 | Solar | Suspended · proposed 2024-11 | 370 MW | [4] |
| Maddox Creek-RP Mone 345 kVPJM AG1-410 - moved to TC1 | Solar | In study · proposed 2024-09 | 300 MW | [4] |
| Maddox Creek-RP Mone 345 kVPJM AI2-366 | Solar | In study · proposed 2024-09 | 300 MW | [4] |
| East Lima - Haviland 138 kVPJM AH1-538 | Solar + storage | In study · proposed 2025-03 | 242 MW | [4] |
| Wild Grains SolarPJM AF2-014 | Solar | IA signed · proposed 2027-12 | 150 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
Real estate
None sourced yet
None sourced yet
None sourced yet
- Site area
“will have up to seven buildings on 902 acres of land at the Mega Site”
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Project
“the $10 billion, 500 megawatt data center at the Mega Site”
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
All claims (provenance audit)
13| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Project | QTS data center at Mega Site | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| Operator | QTS Data Centers | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| Planned capacity | 500 MW | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [2] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Generation queued in county | 2.47 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.95¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.33 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 7 | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| Site area | 902 acres | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| First operational | Jan 2029 | [1] AI-extracted | Likely | 2026-09-27 | Shown |
| Expected completion | 2032 | [1] AI-extracted | Likely | 2026-09-27 | Shown |