Related Digital / CoreWeave Cheyenne

UnknownUnclassifiedCampusCheyenne, Laramie County, Wyoming
10% profile completeness
11 claims from 6 sources
Current facility power
Not yet sourced
Planned capacity
302 MW[1]
Likely
Floor area
Not yet sourced
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H2 2027 – H1 2029
Medium confidencewindow, not a prediction
Project verification
Grid-backed
Interconnection agreement / service contract documented by utility filing / announcement.
Current stage
Interconnection agreement / service contract
Furthest stage with documented evidence
Utility · ISO
Black Hills Energy · None (non-RTO region)
Substation: Not identified

Power reality

Announced
302 MW[1]
Reported by Edison Electric Institute
Interconnection request
No record
Contracted / approved
88 MW[1]
Reported utility / power contract
Under construction
No record
Operational
No record
  • ⚠ Announced 302 MW is 3.4× the 88 MW documented by grid, construction or operating records.
  • ⚠ No recorded land acquisition found.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Interconnection agreement / service contract (furthest stage with documented evidence)[1]
  • Required: 302 MW
Assumptions
  • From “Interconnection agreement / service contract”, large loads have typically taken 0.75–2.5 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H2 2027 – H1 2029

Project verification

Development
  1. AnnouncedSep 11, 2026
    Utility filing / announcement
    • Sep 11, 2026 · Planned capacity reported: 302 MW[1]
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contractSep 11, 2026
    Utility filing / announcement
    • Sep 11, 2026 · Contracted / committed power: 88 MW[1]
Build & energization
  1. Financing
  2. Under construction
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Utility filing / announcement.

Grid path

  1. facility
    Related Digital / CoreWeave Cheyenne
  2. substation
    Not identified
    UnknownUnverified
    No substation mapped within 3 km and none named in filings.
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Black Hills Energy[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    None (non-RTO region)[2]
    Service territoryLikely
    Balancing authority: WACM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

County-level (approximate)

Location is approximate (county-level (approximate)); the marker does not identify the exact site.

Coordinates
41.30709, -104.68875
County
Laramie County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Developer

“Related Digital, CoreWeave / Data Center Cheyenne, WY”

Tenant

“Related Digital, CoreWeave / Data Center Cheyenne, WY”

Utility

“Related Digital, CoreWeave / Data Center Cheyenne, WY” Listed by EEI under this member utility.

Power (all fields)

Planned capacity
302 MW[1]Likely

“Power to ramp from 88 MW in first phase, expanding to 302 MW total.”

Contracted / committed power
88 MW[1]Likely

“Power to ramp from 88 MW in first phase, expanding to 302 MW total.” — First-phase service described by the utility (via EEI).

Current facility power
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[2]Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
WACM[3]Likelyderived

Control area of the containing utility territory.

Contracted / committed power
88 MW[1]Likely

“Power to ramp from 88 MW in first phase, expanding to 302 MW total.” — First-phase service described by the utility (via EEI).

State avg. industrial price
8.62¢/kWh[5]Confirmed

Wyoming statewide average, July 2026.

State avg. commercial price
10.26¢/kWh[5]Confirmed

Wyoming statewide average, July 2026.

Generation within 50 km
737 MW[6]Confirmedderived

7 EIA-reported plants within 50 km.

Generation queued in county
980 MW[4]Confirmedderived

3 active generation interconnection requests in Laramie County: Wind 650 MW, Hybrid 330 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Cheyenne Prairie Generating Station · Black Hills Service Company LLCPower plant (Natural Gas)20.6 km131 MW[6]
Happy Jack Windpower Project · Duke Energy Renewables ServicesPower plant (Wind)31.8 km29 MW[6]
South Cheyenne Solar · Southern Power CoPower plant (Solar)32 km150 MW[6]
Corriedale Wind Energy · Black Hills Service Company LLCPower plant (Wind)32.8 km53 MW[6]
Silver Sage Windpower · Duke Energy Renewables ServicesPower plant (Wind)34.3 km42 MW[6]
Roundhouse Renewable Energy II · Roundhouse Renewable Energy II, LLCPower plant (Wind)38 km106 MW[6]
Roundhouse Wind Energy Project · Roundhouse Renewable Energy, LLCPower plant (Wind)42.2 km226 MW[6]
Largest queued generation in this countyFuelQueue statusMWSource
GI-TC-2024-16 at Ault-Laramie River Station 345 LineSPP GI-TC-2024-16WindIA signed · proposed 2029-06400 MW[4]
GI-CS-2025-04 at Ault LRS 345 LineSPP GI-CS-2025-04HybridIn study · proposed 2029-11330 MW[4]
GI-TC-2024-15 at Big Bear 345 Switching StationSPP GI-TC-2024-15WindIA signed · proposed 2029-09250 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —
Planned capacity
302 MW[1]Likely

“Power to ramp from 88 MW in first phase, expanding to 302 MW total.”

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

11
FieldValueSourceConfidenceAs ofStatus
DeveloperRelated Digital[1] Confirmed2026-09-11Shown
TenantsCoreWeave[1] Likely2026-09-11Shown
UtilityBlack Hills Energy[1] Confirmed2026-09-11Shown
Planned capacity302 MW[1] Likely2026-09-11Shown
Contracted / committed power88 MW[1] Likely2026-09-11Shown
ISO / RTONone (non-RTO region)[2] derivedLikely—Shown
Balancing authorityWACM[3] derivedLikely—Shown
Generation queued in county980 MW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price8.62¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price10.26¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km737 MW[6] derivedConfirmed202502Shown