Unnamed data center — 2236 Airport Drive
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center — 2236 Airport Drive
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 2.46 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.27 km away). Not confirmed as the supply path.
- →utilityOncor Electric Delivery[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 33.95345, -98.52491
- Address
- County
- Wichita County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: AEP Texas North Company, Southwest Rural Elec Assn INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
3 EIA-reported plants within 50 km.
- Generation queued in county
13 active generation interconnection requests in Wichita County: Storage 1,819 MW, Solar 752 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.27 km | 138 kV | [1] |
| Works 4 · Vitro Architectural Glass | Power plant (Petroleum) | 6.2 km | 5 MW | [6] |
| Wal414 · Walmart Stores Texas, LLC | Power plant (Natural Gas) | 11 km | 1 MW | [6] |
| Signal Hill Generating LLC · Signal Hill Generating LLC | Power plant (Natural Gas) | 11.7 km | 76 MW | [6] |
| Unnamed substation | Substation | 2.46 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.74 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.89 km | — | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Short Creek SolarERCOT 24INR0201 · Wichita Solar I, LLC | Solar | IA signed · proposed 2027-12 | 628 MW | [4] |
| Copperleaf Energy StorageERCOT 28INR0118 · Copperleaf Energy Storage, LLC | Storage | In study · proposed 2029-04 | 306 MW | [4] |
| Wichita Creek StorageERCOT 28INR0378 · Wichita Creek Storage, LLC | Storage | In study · proposed 2028-10 | 300 MW | [4] |
| Bologna BESSERCOT 26INR0472 · MALONEY BESS LLC | Storage | In study · proposed 2028-04 | 203 MW | [4] |
| Spinosa BESSERCOT 27INR0412 · Spinosa Energy Center, LLC | Storage | In study · proposed 2030-05 | 201 MW | [4] |
| Pethrus BESSERCOT 26INR0280 · Pethrus BESS, LLC | Storage | In study · proposed 2029-03 | 174 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
13| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Address | 2236 Airport Drive, Wichita Falls, TX 76306 | [1] | Likely | 2026-09-27 | Shown |
| Utility | Oncor Electric Deliveryterritory 44372: ONCOR ELECTRIC DELIVERY COMPANY LLC (INVESTOR OWNED, ONCOR ELEC | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | SPPSOUTHWEST POWER POOL | [3] derived | Likely | — | Shown |
| Balancing authority | SWPP | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1124325453 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 2.5 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.57 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 82 MW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 39,200 sq ft | [1] derived | Likely | 2026-09-27 | Shown |