DC
/

Unnamed data center — 5225 Exchange Drive

OperatingUnclassifiedBuildingFlint, Genesee County, Michigan
20% profile completeness
13 claims from 6 sources
Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
36,900 sq ft[1]
Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Consumers Energy CO · MISO
Substation: Consumers Energy substation (46 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalSep 27, 2026
    Community map
    • Sep 27, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Unnamed data center — 5225 Exchange Drive
  2. substation
    Consumers Energy substation (46 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 1.7 km away. Proximity does not establish that it serves the site.
  3. transmission
    46 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.15 km away). Not confirmed as the supply path.
  4. utility
    Consumers Energy CO[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    MISO[3]
    Service territoryLikely
    Balancing authority: MISO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

Location & imagery

Mapped outline
Coordinates
42.96871, -83.77948
Address
5225 Exchange Drive, Flint, MI 48507[1]Likely
County
Genesee County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
MISO[3]Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
MISO[2]Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Consumers Energy substation (46 kV)[1]Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
1.7 km[1]Likelyderived
Highest-voltage line nearby
46 kV[1]Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.81¢/kWh[5]Confirmed

Michigan statewide average, July 2026.

State avg. commercial price
16.46¢/kWh[5]Confirmed

Michigan statewide average, July 2026.

Generation within 50 km
451 MW[6]Confirmedderived

22 EIA-reported plants within 50 km.

Generation queued in county
1.6 GW[4]Confirmedderived

6 active generation interconnection requests in Genesee County: Gas 975 MW, Storage 450 MW, Solar 175 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
46 kV line · Consumers EnergyTransmission line0.15 km46 kV[1]
Assembly Solar III · Assembly Solar III, LLCPower plant (Solar)14.6 km79 MW[6]
Assembly Solar Project · Assembly Solar I, LLCPower plant (Solar)14.8 km50 MW[6]
Genesee Power Station LP · NorthStar Clean EnergyPower plant (Biomass)15.7 km35 MW[6]
Assembly Solar II LLC · Assembly Solar II LLCPower plant (Solar)16.9 km110 MW[6]
Lyons Road · Lyons Road Solar, LLCPower plant (Solar)29.6 km20 MW[6]
Midcontinent Solar, LLC · Midcontinent Solar, LLCPower plant (Solar)30.8 km20 MW[6]
Demille Solar Farm · DTE Electric CompanyPower plant (Solar)37.1 km28 MW[6]
Turrill Solar Farm · DTE Electric CompanyPower plant (Solar)39 km20 MW[6]
Consumers Energy substation · Consumers EnergySubstation1.7 km46 kV[1]
Lennon Road Substation · Consumers EnergySubstation2.1 km46 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
J3935 at THETFORDMISO J3935GasIn study · proposed 2030-03975 MW[4]
J3251 at THETFORDMISO J3251StorageIn study · proposed 2028-06200 MW[4]
J3650 at BEVERIDGEMISO J3650StorageIn study · proposed 2028-11150 MW[4]
J1203 at Thetford 345kV SubstationMISO J1203SolarUnder construction · proposed 2022-06125 MW[4]
J3735 at BEVERIDGE 138kVMISO J3735StorageIn study · proposed 2028-06100 MW[4]
J1172 at Dort - Garfield 138 kV Line TapMISO J1172SolarUnder construction · proposed 2021-0750 MW[4]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
36,900 sq ft[1]Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

All claims (provenance audit)

13
FieldValueSourceConfidenceAs ofStatus
StatusOperating[1] derivedUnverified2026-09-27Shown
Address5225 Exchange Drive, Flint, MI 48507[1] Likely2026-09-27Shown
UtilityConsumers Energy COterritory 4254: CONSUMERS ENERGY CO (INVESTOR OWNED, CMS ENERGY CORPORATION)[2] derivedLikely2022Shown
ISO / RTOMISOMIDCONTINENT INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC..[3] derivedLikely—Shown
Balancing authorityMISO[2] derivedLikely—Shown
Nearest mapped substationConsumers Energy substation (46 kV)way/1234926735[1] derivedLikely2026-09-28Shown
Distance to substation1.7 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby46 kV[1] derivedLikely2026-09-28Shown
Generation queued in county1.6 GW[4] derivedConfirmed2026-09-27Shown
State avg. industrial price9.81¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price16.46¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km451 MW[6] derivedConfirmed202502Shown
Building footprint36,900 sq ft[1] derivedLikely2026-09-27Shown