Unnamed data center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center
- →substationJersey Central Power and Light substation (34.5 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 1.01 km away. Proximity does not establish that it serves the site.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityJersey Central Power & Light[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 40.20846, -74.11924
- County
- Monmouth County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- State avg. industrial price
New Jersey statewide average, July 2026.
- State avg. commercial price
New Jersey statewide average, July 2026.
- Generation within 50 km
164 EIA-reported plants within 50 km.
- Generation queued in county
17 active generation interconnection requests in Monmouth County: Offshore wind 15,507 MW, Wind 1,342 MW, Storage 507 MW, Solar 44 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Naea Ocean Peaking Power LLC · Essential Power Operating Company, LLC | Power plant (Natural Gas) | 16.6 km | 336 MW | [6] |
| Red Oak Power LLC · Red Oak Operating Services LLC | Power plant (Natural Gas) | 33.1 km | 776 MW | [6] |
| Woodbridge Energy Center · Woodbridge Energy Center | Power plant (Natural Gas) | 38.1 km | 727 MW | [6] |
| Pseg Sewaren Generating Station · Sewaren Generating Station | Power plant (Natural Gas) | 40.1 km | 538 MW | [6] |
| Arthur Kill Generating Station · NRG Arthur Kill Operations Inc | Power plant (Natural Gas) | 43.1 km | 896 MW | [6] |
| Pseg Linden Generating Station · Linden Combined Cycle | Power plant (Natural Gas) | 46.5 km | 1.64 GW | [6] |
| Linden Cogen Plant · EFS Cogen Holdings I LLC | Power plant (Natural Gas) | 47.8 km | 904 MW | [6] |
| Bayonne Energy Center · Bayonne Energy Center LLC | Power plant (Natural Gas) | 49.5 km | 599 MW | [6] |
| Jersey Central Power and Light substation · Jersey Central Power and Light | Substation | 1.01 km | 34.5 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Oceanview Wind 4 230 kVPJM AH1-507 | Offshore wind | In study · proposed 2028-12 | 2.79 GW | [4] |
| Larrabee 230 kVPJM AI2-129 | Offshore wind | In study · proposed 2030-02 | 2.25 GW | [4] |
| Larrabee 230 kVPJM AI1-001 | Offshore wind | In study · proposed 2029-10 | 2.1 GW | [4] |
| Oceanview Wind 3 230 kVPJM AH1-506 | Offshore wind | In study · proposed 2028-12 | 2.06 GW | [4] |
| Smithburg 500 kVPJM AI1-046 | Offshore wind | In study · proposed 2031-12 | 1.6 GW | [4] |
| Larrabee Collector 230 kVPJM AJ1-015 | Wind | In study · proposed 2030-05 | 1.34 GW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
11| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Jersey Central Power & Lightterritory 9726: JERSEY CENTRAL POWER & LT CO (INVESTOR OWNED, FIRSTENERGY CORP) | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Jersey Central Power and Light substation (34.5 kV)way/1215856720 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1 km | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 17.4 GW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 15.63¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 19.17¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 8.35 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 59,400 sq ft | [1] derived | Likely | 2026-09-27 | Shown |