POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.23 km away. Proximity does not establish that it serves the site.
- →transmission138 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.26 km away). Not confirmed as the supply path.
- →utilityRio Grande Electric Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 31.53275, -103.80627
- County
- Reeves County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 3 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Texas-New Mexico Power CO, AEP Texas North Company.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
12 EIA-reported plants within 50 km.
- Generation queued in county
21 active generation interconnection requests in Reeves County: Gas 4,602 MW, Solar 1,566 MW, Wind 1,031 MW, Storage 951 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.26 km | 138 kV | [1] |
| West of The Pecos Solar · RWE Renewables Americas, LLC | Power plant (Solar) | 13.5 km | 100 MW | [6] |
| Coyote Springs (Tx) · HEN Infrastructure, L.L.C. | Power plant (Batteries) | 22.7 km | 10 MW | [6] |
| Faulkner · HEN Infrastructure, L.L.C. | Power plant (Batteries) | 30.1 km | 10 MW | [6] |
| Cedarville (Tx) · HEN Infrastructure, L.L.C. | Power plant (Batteries) | 33.6 km | 10 MW | [6] |
| Hayhurst Texas Solar · Hayhurst Texas Solar | Power plant (Solar) | 41.1 km | 25 MW | [6] |
| Swoose II · Swoose II | Power plant (Batteries) | 43.1 km | 101 MW | [6] |
| Tx8 Worsham · Key Capture Energy | Power plant (Batteries) | 48.7 km | 10 MW | [6] |
| Rodeo Ranch Energy Storage · Rodeo Ranch Energy Storage, LLC | Power plant (Batteries) | 49.1 km | 300 MW | [6] |
| Unnamed substation | Substation | 0.23 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.15 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.39 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.4 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.73 km | — | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Wolf Bone North Energy Center (OLD)ERCOT 29INR0162 · NRG Wolf Bone Energy Center LLC | Gas | In study · proposed 2029-11 | 1.2 GW | [4] |
| Kilby1 Part 6 Large Block Combined CycleERCOT 29INR0199 · Energy Forge One LLC | Gas | In study · proposed 2029-07 | 1.06 GW | [4] |
| Kilby1 Part 4 Large Block Simple CycleERCOT 28INR0459 · Energy Forge One LLC | Gas | In study · proposed 2028-04 | 950 MW | [4] |
| Glass Mountain Wind 2ERCOT 28INR0468 · Glass Mountain Wind, LLC | Wind | In study · proposed 2028-12 | 519 MW | [4] |
| Glass Mountain Wind 1ERCOT 29INR0194 · Glass Mountain Wind, LLC | Wind | In study · proposed 2028-12 | 512 MW | [4] |
| Trumpet SolarERCOT 29INR0360 · NextEra Energy Resources Interconnection Holdings LLC | Solar | In study · proposed 2029-07 | 455 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
12| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Rio Grande Electric Coop, INCterritory 16057: RIO GRANDE ELECTRIC COOP, INC (COOPERATIVE, RIO GRANDE ELECTRIC | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | EPE, ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1120484077 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 8.28 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 605 MW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 57,600 sq ft | [1] derived | Likely | 2026-09-27 | Shown |