Unnamed data center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center
- →substationScrubgrass Substation (115 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.15 km away. Proximity does not establish that it serves the site.
- →transmissionHandsome Lake - Armstrong 345kV[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.83 km away). Not confirmed as the supply path.
- →utilityPennsylvania Electric CO[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
- Scrubgrass Reclamation CO. LP. (Coal, 83 MW) is 0.3 km away[6]EIA plant within 1.5 km; proximity does not establish that it supplies the facilityUnknown typeCo-located83 MWUnverified
Location & imagery
Mapped outline- Coordinates
- 41.27163, -79.81337
- County
- Venango County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Central Electric Coop, INC - (Pa).
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Pennsylvania statewide average, July 2026.
- State avg. commercial price
Pennsylvania statewide average, July 2026.
- Generation within 50 km
5 EIA-reported plants within 50 km.
- Generation queued in county
14 active generation interconnection requests in Venango County: Solar 274 MW, Storage 220 MW, Solar + storage 25 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line | Transmission line | 0.03 km | 115 kV | [1] |
| Handsome Lake - Armstrong 345kV | Transmission line | 1.83 km | 345 kV | [1] |
| Scrubgrass Reclamation CO. LP. · Scrubgrass Reclamation CO. LP. | Power plant (Coal) | 0.3 km | 83 MW | [6] |
| Handsome Lake Energy LLC · Handsome Lake Energy LLC | Power plant (Natural Gas) | 2.2 km | 268 MW | [6] |
| Wabtec U.S Rail, Grove City Engine Plant · General Electric Co | Power plant (Petroleum) | 26.9 km | 4 MW | [6] |
| Piney · BP Piney & Deep Creek LLC | Power plant (Hydroelectric) | 33 km | 33 MW | [6] |
| Allegheny Hydro No 9 · Allegheny Hydro LP | Power plant (Hydroelectric) | 41.4 km | 18 MW | [6] |
| Scrubgrass Substation | Substation | 0.15 km | 115 kV | [1] |
| Unnamed substation | Substation | 2.25 km | — | [1] |
| Handsome Lake Substation | Substation | 2.25 km | 345 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Grandview 115 kVPJM AI1-181 | Storage | In study · proposed 2027-12 | 140 MW | [4] |
| Eclipse-Piney 115 kV IIPJM AH1-051 | Solar | In study · proposed 2023-07 | 80 MW | [4] |
| Eclipse-Piney 115 kV IIIPJM AH1-158 | Storage | In study · proposed 2023-08 | 80 MW | [4] |
| Eclipse-Piney 115 kVPJM AH1-050 | Solar | In study · proposed 2023-07 | 50 MW | [4] |
| Eclipse #2 34.5 kVPJM AG2-420 | Solar + storage | In study · proposed 2023-05 | 25 MW | [4] |
| Long BridgePJM AF2-166 | Solar | Suspended · proposed 2026-08 | 20 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
12| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Pennsylvania Electric COterritory 14711: PENNSYLVANIA ELECTRIC CO (INVESTOR OWNED, FIRSTENERGY CORP) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Scrubgrass Substation (115 kV)way/1050125611 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 519 MW | [4] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 11.04¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.86¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 405 MW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 700 sq ft | [1] derived | Likely | 2026-09-27 | Shown |