Unnamed data center
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityUnnamed data center
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.12 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.15 km away). Not confirmed as the supply path.
- →utilityTexas-New Mexico Power CO[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
ERCOT 23INR0094 BRP Pyxis BESS · BRP Pyxis BESS LLC · Storage | Generation at a nearby substation Unverified Queue POI “tap 138kV 1009 Yucca - 11197 Sand Tank Pod ” names Sand Lake Switching Station, a substation mapped 1.49 km from the site (OSM). Sharing a POI does not mean this generation serves the facility. | System impact study SS Completed, FIS Started, No IA | 206.9 | — | — | Dec 1, 2028 | tap 138kV 1009 Yucca - 11197 Sand Tank Pod | [4] Sep 1, 2026 |
ERCOT 24INR0538 FLIFER Solar I · FLIFER LLC · Solar | Generation at a nearby substation Unverified Queue POI “Tap 138 kV Yucca Drive Switch (bus# 1009) – Sand Tank (bus# 11197)” names Sand Lake Switching Station, a substation mapped 1.49 km from the site (OSM). Sharing a POI does not mean this generation serves the facility. | System impact study SS Completed, FIS Started, No IA | 84 | — | — | Apr 15, 2027 | Tap 138 kV Yucca Drive Switch (bus# 1009) – Sand Tank (bus# 11197) | [4] Sep 1, 2026 |
ERCOT 25INR0008 BasRanch (TEF - Due Diligence) · CPV Basin Ranch, LLC · Gas | Generation at a nearby substation Unverified Queue POI “tap 345kV Riverton Switch - Sand Lake Switch” names Sand Lake Switching Station, a substation mapped 1.49 km from the site (OSM). Sharing a POI does not mean this generation serves the facility. | Interconnection agreement executed SS Completed, FIS Completed, IA | 1,350 | — | — | Dec 1, 2028 | tap 345kV Riverton Switch - Sand Lake Switch | [4] Sep 1, 2026 |
ERCOT 27INR0255 New Minglewood Energy Center · Nova Clean Energy LLC · Storage | Generation at a nearby substation Unverified Queue POI “#11098 Sand Lake Switch Station (SANDLAKE_5) 345kV” names Sand Lake Switching Station, a substation mapped 1.49 km from the site (OSM). Sharing a POI does not mean this generation serves the facility. | System impact study SS Completed, FIS Started, No IA | 208.3 | — | — | Sep 29, 2029 | #11098 Sand Lake Switch Station (SANDLAKE_5) 345kV | [4] Sep 1, 2026 |
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 31.51343, -103.44912
- County
- Ward County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Oncor Electric Delivery Company LLC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Nearest mapped substation
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- Highest-voltage line nearby
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
Texas statewide average, July 2026.
- State avg. commercial price
Texas statewide average, July 2026.
- Generation within 50 km
19 EIA-reported plants within 50 km.
- Generation queued in county
10 active generation interconnection requests in Ward County: Gas 2,248 MW, Storage 803 MW, Solar 264 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.14 km | 138 kV | [1] |
| 345 kV line | Transmission line | 1.15 km | 345 kV | [1] |
| Swoose II · Swoose II | Power plant (Batteries) | 10.8 km | 101 MW | [6] |
| Rodeo Ranch Energy Storage · Rodeo Ranch Energy Storage, LLC | Power plant (Batteries) | 20.5 km | 300 MW | [6] |
| West of The Pecos Solar · RWE Renewables Americas, LLC | Power plant (Solar) | 28.1 km | 100 MW | [6] |
| Flower Valley II · Flower Valley II | Power plant (Batteries) | 36.1 km | 101 MW | [6] |
| Tx7 Flat Top · Key Capture Energy | Power plant (Batteries) | 36.1 km | 10 MW | [6] |
| Permian Basin · Luminant Generation Company LLC | Power plant (Natural Gas) | 46.7 km | 320 MW | [6] |
| Taygete II Energy Project · West Texas Solar Project II LLC | Power plant (Solar) | 47.5 km | 204 MW | [6] |
| Taygete Energy Project LLC · Taygete Energy Project LLC | Power plant (Solar) | 49.4 km | 255 MW | [6] |
| Unnamed substation | Substation | 0.12 km | 138 kV | [1] |
| Mi Vida Substation · Texas-New Mexico Power | Substation | 0.27 km | 138 kV | [1] |
| Cochise Substation · Texas-New Mexico Power | Substation | 0.29 km | 138 kV | [1] |
| Sand Lake Switching Station · Oncor | Substation | 1.49 km | 345 kV | [1] |
| Unnamed substation | Substation | 1.61 km | 138 kV | [1] |
| Barstow Northwest Substation · Oncor | Substation | 2.81 km | 138 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| BasRanch (TEF - Due Diligence)ERCOT 25INR0008 · CPV Basin Ranch, LLC | Gas | IA signed · proposed 2028-12 | 1.35 GW | [4] |
| Vast Sands Power I (TEF -Due Diligence)ERCOT 28INR0105 · Permian Power I LLC | Gas | IA signed · proposed 2028-05 | 440 MW | [4] |
| Vast Sands Power II (TEF-Due Diligence)ERCOT 28INR0109 · Permian Power I LLC | Gas | IA signed · proposed 2028-06 | 440 MW | [4] |
| New Minglewood Energy CenterERCOT 27INR0255 · Nova Clean Energy LLC | Storage | In study · proposed 2029-09 | 208 MW | [4] |
| BRP Rhine BESSERCOT 23INR0075 · BRP Rhine BESS LLC | Storage | In study · proposed 2028-12 | 207 MW | [4] |
| BRP Pyxis BESSERCOT 23INR0094 · BRP Pyxis BESS LLC | Storage | In study · proposed 2028-12 | 207 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
All claims (provenance audit)
11| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Status | Operating | [1] derived | Unverified | 2026-09-27 | Shown |
| Utility | Texas-New Mexico Power COterritory 40051: TEXAS-NEW MEXICO POWER CO (INVESTOR OWNED, PNM RESOURCES INC) | [2] derived | Unverified | 2022 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1454568155 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.1 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 3.32 GW | [4] derived | Confirmed | 2026-09-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.5 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 56,800 sq ft | [1] derived | Likely | 2026-09-27 | Shown |