What changed — AI XPV Platform

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Subscribe to the feed in any RSS reader to follow a facility, state or company.

Clear
  1. May 31, 2026
    Anthropic Lake Mariner · NY
    • Buildings operational: 0 → 1
    • Status: Under construction → Operating + expanding
    • New capacity online: Building 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore lik…
    Source: Epoch AI
  2. Jun 11, 2025
    Anthropic Lake Mariner · NY
    • Construction started: Land clearing begins for Building 1 (AKA CB3).
    Source: Epoch AI
  3. Jan 23, 2024
    Anthropic Lake Mariner · NY
    • Permit / site plan filed: NYISO load interconnection request 1670 filed (250 MW).
    Source: New York ISO