Anthropic Lake Mariner
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Stated dates slip; the window allows up to 0.75 years past the stated date at this stage.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Feasibility study
ISO/RTO queue
- NYISO load request 1670 (250 MW): Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 (queue status as of 2026-09-27)[2]
- System impact study
ISO/RTO queue
- NYISO load request 1670 (250 MW): Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 (queue status as of 2026-09-27)[2]
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationMay 31, 2026
Satellite imagery
- May 31, 2026 · Building 1 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
- OperationalMay 31, 2026
Satellite imagery
- May 31, 2026 · Building 1 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: ISO/RTO queue, Model estimate, Satellite imagery.
Grid path
- →facilityAnthropic Lake Mariner
- →substationKintigh 345kV Substation[2]Queue POILikelyPoint of interconnection in NYISO load request 1670
- →transmission345 kV[2]Queue POILikelyVoltage at the requested point of interconnection (Kintigh 345kV Substation)
- →utilityNiagara Mohawk Power Corp.[3]Service territoryLikelyRetail service territory containing the site · Transmission owner (queue): NYSEG
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
NYISO 1670 Lake Mariner Data II · Lake Mariner Data LLC | This site's load request Likely Request name/customer shares “mariner” with this facility, in the same county. | System impact study Status 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: 02-2027 | 250 | — | Jan 23, 2024 | Feb 2027 | Kintigh 345kV Substation TO: NYSEG | [2] Sep 27, 2026 |
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
Location & imagery
Mapped outline- Coordinates
- 43.35873, -78.59833
- Address
- County
- Niagara County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- Developer
Interconnection customer on the load request.
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: New York State Elec & Gas Corp.
- Investor
Power (all fields)
- Current facility power
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
Projected facility power at the last tracked milestone (2027-03-31); not necessarily full build-out.
- Estimated annual consumption
49 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
Location falls inside this ISO/RTO footprint.
- Balancing authority
Control area of the containing utility territory.
- Interconnection status
- Load interconnection request
NYISO load interconnection request 1670 (Data center (AI)).
- State avg. industrial price
New York statewide average, July 2026.
- State avg. commercial price
New York statewide average, July 2026.
- Generation within 50 km
47 EIA-reported plants within 50 km.
- Generation queued in county
2 active generation interconnection requests in Niagara County: Solar 225 MW. Queued projects often don't get built.
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Slayton Settlement Road Solar Csg · RPNY Solar 3, LLC | Power plant (Solar) | 17.7 km | 7 MW | [7] |
| Lockport Energy Associates LP · Lockport Energy Associates LP | Power plant (Natural Gas) | 24.9 km | 219 MW | [7] |
| Modern Innovative Energy LLC · Innovative Energy Systems Inc | Power plant (Biomass) | 35.3 km | 6 MW | [7] |
| Model City Energy Facility · Model City Energy LLC | Power plant (Biomass) | 35.3 km | 6 MW | [7] |
| World Generation X · North American Energy Services | Power plant (Natural Gas) | 40.3 km | 52 MW | [7] |
| Lewiston Niagara · New York Power Authority | Power plant (Pumped Storage) | 41.9 km | 240 MW | [7] |
| Robert Moses Niagara · New York Power Authority | Power plant (Hydroelectric) | 43 km | 2.44 GW | [7] |
| Reworld Niagara I · Reworld Niagara I, LLC | Power plant (Biomass) | 45 km | 36 MW | [7] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Somerset SolarNYISO 1079 · Somerset Solar, LLC | Solar | IA signed · proposed 2028-06 | 125 MW | [2] |
| Bear Ridge SolarNYISO 0704 · Bear Ridge Solar, LLC | Solar | IA signed · proposed 2028-04 | 100 MW | [2] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- PermittingJan 23, 2024[2]
- Construction startJun 11, 2025[1]
- First operationalMay 31, 2026[1]
- Expected completionMar 31, 2027[1]Projected
- Planned capacity
Projected facility power at the last tracked milestone (2027-03-31); not necessarily full build-out.
- Buildings (planned)
Count of building outlines traced on satellite imagery.
- Buildings operational
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
What changed (last 3 years)
Follow this facility (RSS)Timeline
- Jun 11, 2025[1]
Land clearing begins for Building 1 (AKA CB3).
- Mar 2, 2026[1]
Building 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation.
Building 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.
Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.
Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf stated that CB5 was expected to be energized by Q4 2026. However, based on the pace of Building 2, and comparisons to other projects like Stargate Abilene, we think this is optimistic. We expect a 3-month delay past the end of Q4 2026 to get to full operational capacity.
- Jan 23, 2024[2]
NYISO load interconnection request 1670 filed (250 MW).
Proposed initial backfeed / in-service for NYISO load request 1670.
All claims (provenance audit)
38| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Anthropic Lake Mariner | [1] | Likely | 2026-07-23 | Shown |
| Status | Under construction | [1] derived | Likely | 2025-06-11 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-03-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-07-23 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-23 | Shown |
| Address | 7725 Lake Rd, Barker, NY 14012 | [1] | Likely | 2026-07-23 | Shown |
| Owner | AI XPV PlatformOwner: AI XPV Platform | [1] | Confirmed | 2026-07-23 | Shown |
| Developer | Lake Mariner Data LLC | [2] | Likely | 2026-09-27 | Shown |
| End users | AnthropicUsers: Anthropic | [1] | Likely | 2026-07-23 | Shown |
| Utility | Niagara Mohawk Power Corp.territory 13573: NIAGARA MOHAWK POWER CORP. (INVESTOR OWNED, NATIONAL GRID GROUP | [3] derived | Unverified | 2022 | Shown |
| Investors | GoogleInvestors: Google | [1] | Confirmed | 2026-07-23 | Shown |
| Investors | BlackstoneInvestors: Blackstone | [1] | Confirmed | 2026-07-23 | Shown |
| Current facility power | 49 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current facility power | 49 MW | [1] estimated | Likely | 2026-05-31 | Superseded / alternative |
| Current IT capacity | 42 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current IT capacity | 42 MW | [1] estimated | Likely | 2026-05-31 | Superseded / alternative |
| Planned capacity | 441 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Estimated annual consumption | 300 GWh/yr | [4] estimated | Speculative | 2026-09-29 | Shown |
| ISO / RTO | NYISONEW YORK INDEPENDENT SYSTEM OPERATOR | [5] derived | Likely | — | Shown |
| Balancing authority | NYIS | [3] derived | Likely | — | Shown |
| Interconnection status | NYISO load request 1670: 250 MW, in study at Kintigh 345kV SubstationStatus 6 (SRIS/SIS approved); studies available: SIS; proposed initial backfeed: | [2] | Confirmed | 2026-09-27 | Shown |
| Load interconnection request | 250 MW | [2] | Confirmed | 2026-09-27 | Shown |
| Generation queued in county | 225 MW | [2] derived | Confirmed | 2026-09-27 | Shown |
| State avg. industrial price | 10.81¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 24.18¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.16 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-07-23 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-07-23 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2025-06-11 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-05-31 | Superseded / alternative |
| Capital cost / investment | $1.6B | [1] estimated | Likely | 2026-07-23 | Shown |
| Compute (H100-equivalents) | 58,600 | [1] estimated | Likely | 2026-07-23 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-07-23 | Shown |
| Construction start | Jun 11, 2025 | [1] derived | Likely | 2026-07-23 | Shown |
| First operational | May 31, 2026 | [1] derived | Likely | 2026-07-23 | Shown |
| Expected completion | Mar 31, 2027 | [1] estimated | Speculative | 2026-07-23 | Shown |